Archer Western Contractors, LLC v. McDonnel Group, LLC

CourtDistrict Court, E.D. Louisiana
DecidedJuly 18, 2023
Docket2:22-cv-05323
StatusUnknown

This text of Archer Western Contractors, LLC v. McDonnel Group, LLC (Archer Western Contractors, LLC v. McDonnel Group, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Archer Western Contractors, LLC v. McDonnel Group, LLC, (E.D. La. 2023).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

ARCHER WESTERN CONTRACTORS, LLC CIVIL ACTION

VERSUS NO. 22-5323

THE MCDONNEL GROUP, LLC SECTION: D (5)

ORDER AND REASONS

Before the Court is a Motion to Dismiss for Failure to Join a Required Party and Lack of Subject Matter Jurisdiction filed by the Defendant, The McDonnel Group, LLC.1 The Plaintiff, Archer Western Contractors, LLC, has filed a response in opposition to the Motion.2 The Defendant filed a Reply in support of its Motion.3 After careful consideration of the parties’ memoranda, the record, and the applicable law, the Court DENIES the Motion. I. FACTUAL AND PROCEDURAL BACKGROUND This case concerns the alleged failure of Defendant The McDonnel Group, LLC (“TMG”) to abide by certain agreements and commitments made in a Joint Venture Agreement with Plaintiff Archer Western Contractors, LLC (“AWC”). On May 2, 2011, TMG and AWC entered into a Joint Venture Agreement (the “Agreement”) establishing the McDonnel Group, LLC/Archer Western Contractors, Ltd. Joint Venture (the “Joint Venture”) for the purpose of submitting a bid and obtaining a contract for the construction of the Orleans Parish Sheriff’s Office Inmate Processing Center/Templeman III & IV Replacement Administration building (the “Project”)

1 R. Doc. 29. 2 R. Doc. 32. 3 R. Doc. 38. from the Law Enforcement Division of Orleans Parish, State of Louisiana (the “Owner”).4 Not long thereafter, on July 28, 2011, the Joint Venture entered into a contract with the Owner to construct the Project for a sum of $144,929,000.00 (the

“Contract”).5 According to the terms of the Agreement, AWC and TMG are to share any profits and any losses accruing to the Joint Venture from performance of the Contract in accordance with their proportional interest in the Joint Venture; at the outset, AWC held a seventy percent share of the Joint Venture while TMG held the other thirty percent.6 The Agreement establishes that a party cannot “assign, transfer,

pledge or hypothecate its interest . . . in the Joint Venture or in the Contract or in this Agreement or in any property or monies of the Joint Venture except with prior written consent of the other party[.]”7 AWC is designated as the Managing Party of the Joint Venture, giving AWC “charge and supervision over the timely and satisfactory performance of the Contract, subject, however, to the superior authority and control of the Executive Committee.”8 The Executive Committee is also largely controlled by AWC; the representatives of each party on the Executive Committee

have “a vote equal to his party’s Proportionate Share.”9 The Joint Venture’s need for working capital to perform the Contract necessitates that TMG and AWC “shall” make certain capital contributions “in

4 R. Doc. 42 at ¶¶ 19–20. 5 Id. at ¶ 21. 6 Id. at ¶ 22. 7 Id. at ¶ 35 (Article 16). 8 Id. at ¶ 26 (Article 5(a)). 9 Id. at ¶ 28 (Article 4). accordance with their proportionate share.”10 Per the Agreement, the Managing Party, i.e., AWC, determines the need for capital contributions and the date on which the capital is to be furnished to the Joint Venture.11 All working capital contributions

are to be deposited in the Joint Venture bank account opened by AWC.12 Crucially, Article 7(e) of the Agreement provides that: Should any party (the “Defaulting Party”) be unable or fail or neglect to contribute its Proportionate Share of the working capital within 7 calendar days after the date set for the contribution thereof by the Managing Party, the other Party (the “Non-Defaulting Party”) may, at their option, pay the share of the Defaulting Party (the “Defaulting Party’s Contribution”). If the Non-Defaulting Party pays all or part of the Defaulting Party’s Contribution, such payments shall be deemed to be demand loans made by the Non-Defaulting Party to the Defaulting Party. Such loans shall be immediately repayable by the Defaulting Party without notice and shall bear interest at a rate per annum equal to 3% above the Prime Lending Rate, determined on a day to day basis.13

In the event of a default by one party, the voting strength of the Executive Committee representatives of the non-defaulting party is “increased to the proportion that its actual contributions to working capital (including loans therefore to the Defaulting Party) bear to the total contribution made to working capital by the parties,” while the strength of the defaulting party is decreased proportionally.14 Further, Article 15(e) of the Agreement specifies that the defaulting party must pay any legal

10 Id. at ¶ 30 (Article 7(a)). 11 Id. 12 Id. at ¶ 32 (Article 8(a)). 13 Id. at ¶ 31 (Article 7(e)). 14 Id. at ¶ 25 (Article 7(f)(i)). expenses required by the non-defaulting party “to protect their interests or defend any action arising out of the Defaulting Party’s breach.”15 As alleged by AWC, several disputes arose during the performance of the

contract between the Joint Venture and the Owner.16 Although those disputes and accompanying litigation are not directly relevant here, AWC claims (and TMG does not dispute) that by May 2015, the Owner’s “wrongful failure to properly compensate the [Joint Venture] created critical cash flow issues for the [Joint Venture].”17 These cash flow problems required the Joint Venture to obtain additional capital contributions from its constituent parties—AWC and TMG—in order to continue its

work on the Project and to compensate subcontractors.18 It is at this point, May 2015, that the disputes within the Joint Venture relevant to the instant litigation started to take hold. AWC claims that for the first time in May 2015, TMG indicated that it refused to contribute additional capital funding to the Joint Venture despite not denying that additional funding was necessary to complete the Project.19 Then, on September 3, 2015, AWC issued correspondence to TMG requesting additional capital contributions approved by the

Executive Committee and identifying past failures of TMG to satisfy contribution requests.20 About two weeks later, on September 16, 2015, TMG responded to AWC that it refused to provide any additional capital funding.21 Again on December 2,

15 Id. at ¶ 35 (Article 15(e)). 16 Id. at ¶¶ 38–45. 17 Id. at ¶ 46. 18 Id. at ¶ 47. 19 Id. at ¶¶ 48–49. 20 Id. at ¶¶ 50–52. 21 Id. at ¶ 54. 2015, during an Executive Committee meeting, TMG advised that it would not provide any further funding to the Joint Venture.22 On January 20, 2016, AWC sent correspondence to TMG advising TMG of its

default on past-due capital contributions of $1,650,00.00 and that, pursuant to Article 7(e) of the Agreement, TMG’s past-due contributions “will be deemed to be an on- demand loan made by [AWC] to [TMG] . . . immediately repayable by [TMG] with notice and shall bear interest at a rate per annum equal to 3% above the Prime Lending Rate, determined on a day to day basis.”23 Throughout 2016, the Executive Committee continued to approve required capital contributions which TMG refused

to pay.24 AWC advised TMG that TMG’s increasingly large past-due amounts were deemed on-demand loans payable to AWC under the terms of the Agreement.25 This pattern of TMG refusing to contribute capital to the Joint Venture despite the decisions of the Executive Committee and AWC subsequently advising TMG that the past-due amounts would be deemed interest-bearing loans continued throughout 2017 and 2018 and beyond.26 TMG also failed to attend the weekly Joint Venture and Executive Committee meetings throughout this period.27 AWC again notified

TMG on July 31, 2019 that as of July 11, 2019, AWC had loaned $4,092,144.63 to TMG, comprising “$3,194,250.00 in capital loans and $897,894.63 in interest.”28 AWC avers that as of the date of the filing of this lawsuit, “AWC has loaned TMG

22 Id. at ¶ 55. 23 Id. at ¶¶ 57–58. 24 Id. at ¶¶ 61–65. 25 Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bankston v. Burch
27 F.3d 164 (Fifth Circuit, 1994)
Krim v. pcOrder.com, Inc.
402 F.3d 489 (Fifth Circuit, 2005)
Wagstaff v. United States Department of Education
509 F.3d 661 (Fifth Circuit, 2007)
Harvey v. Grey Wolf Drilling Co.
542 F.3d 1077 (Fifth Circuit, 2008)
Hood Ex Rel. Mississippi v. City of Memphis, Tenn.
570 F.3d 625 (Fifth Circuit, 2009)
Provident Tradesmens Bank & Trust Co. v. Patterson
390 U.S. 102 (Supreme Court, 1968)
Republic of Philippines v. Pimentel
553 U.S. 851 (Supreme Court, 2008)
RANDALL D. WOLCOTT, MD, PA v. Sebelius
635 F.3d 757 (Fifth Circuit, 2011)
Thomas D. Boles v. Greeneville Housing Authority
468 F.2d 476 (Sixth Circuit, 1972)
Carol H. Pulitzer-Polster v. Samuel C. Pulitzer
784 F.2d 1305 (Fifth Circuit, 1986)
Hooper v. Wolfe
396 F.3d 744 (Sixth Circuit, 2005)
Miller v. Barnes
135 So. 2d 555 (Louisiana Court of Appeal, 1961)
Latiolais v. BFI of Louisiana, Inc.
567 So. 2d 1159 (Louisiana Court of Appeal, 1990)
Ault Wiborg Co. of Canada v. Carson Carbon Co.
160 So. 298 (Supreme Court of Louisiana, 1935)
Javier Flores v. Mike Pompeo
936 F.3d 273 (Fifth Circuit, 2019)
Gensetix, Inc. v. Baylor College of Medicine
966 F.3d 1316 (Federal Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Archer Western Contractors, LLC v. McDonnel Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/archer-western-contractors-llc-v-mcdonnel-group-llc-laed-2023.