Archer Western Contractors, LLC v. Holder Construction Company

CourtCourt of Appeals of Georgia
DecidedNovember 22, 2013
DocketA13A1331
StatusPublished

This text of Archer Western Contractors, LLC v. Holder Construction Company (Archer Western Contractors, LLC v. Holder Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Archer Western Contractors, LLC v. Holder Construction Company, (Ga. Ct. App. 2013).

Opinion

FIRST DIVISION PHIPPS, C. J., ELLINGTON, P. J., and BRANCH, J.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. http://www.gaappeals.us/rules/

November 22, 2013

In the Court of Appeals of Georgia A13A1331. ARCHER WESTERN CONTRACTORS, LLC et al. v. HOLDER CONSTRUCTION COM PANY et al.

B RANCH, Judge.

Appellants Archer Western Contractors and Capital Contracting Company

(collectively, “AWC”) filed the instant suit against appellees Holder Construction

Company, Manhattan Construction Company, C. D. Moody Construction Company,

and Hunt Construction Group (collectively, “HMMH”) seeking a declaration that

HMMH’s assertion of its right to withhold payments to its subcontractor AWC was

barred by res judicata. HMMH filed a motion to dismiss AWC’s action and to compel

arbitration, which the trial court granted. On appeal from this order, AWC argues that

the trial court erred when it granted HMM H’s motion to dismiss because the

arbitration provision is unenforceable and because the trial court, rather than an arbitrator, was required to determine whether res judicata barred HMMH’s assertion

of its right to withhold payments. We disagree with these contentions and therefore

affirm.

Whether a valid and enforceable arbitration agreement exists is “a question of

law.” Miller v. GGNSC Atlanta, 323 Ga. App. 114, 117 (1) (746 SE2d 680) (2013).

We therefore review a trial court’s order granting or denying a motion to compel

arbitration de novo. Id.

Although this appeal is an outgrowth of litigation that has occupied our

appellate courts since 2011, the relevant facts are not in dispute. In late 2004, the City

of Atlanta

entered into a contract (“the Main Contract”) with a joint venture comprised of defendants [HMMH] regarding the construction project. 1 The General Contractor entered into a contract (“the Subcontract”) with a joint venture comprised of defendants [AWC] to perform work on the project. Pitts was employed by [AWC] to work on the project. [AWC] contracted with A&G Trucking for trucking and hauling work on the project.

1 All of the parties to the current declaratory action were defendants in the Pitts litigation.

2 Pursuant to the Main Contract, [HMMH] would serve as construction manager for the construction of the Atlanta airport’s Maynard Holbrook Jackson, Jr., International Terminal, identified in the Main Contract as the “project.” The Main Contract authorized [HMMH] to enter into subcontracts with other entities. [HMM H] was obligated to require any subcontractors to be bound to it by the terms of the Main Contract and to assume to it all obligations and responsibilities which it assumed to the City under the M ain Contract. The Main Contract also provided that, “where appropriate, [HMMH] shall require each Subcontractor to enter into similar agreements with its Sub-Subcontractor.”

The Main Contract specified that [HMMH], its subcontractors, and its sub-subcontractors were named insureds under the City’s “Owner’s Controlled Insurance Program,” which was made a part of the M ain Contract. The stated purpose of the Owner’s Controlled Insurance Program was “to provide one master insurance program that provides broad coverage with high limits that will benefit all participants involved in the project.” The Main Contract required that the named insureds comply with all requirements of the Owner’s Controlled Insurance Program, which pertinently provided: “[HMMH] shall, at its own expense, purchase and maintain such insurance as will protect Contractor, Owner, Construction Manager, Design Consultant, and their Trustees, Directors, Officers, Partners, Agents, Representatives, and Employees from claims of the type set forth below: Automobile, Bodily Injury and Property Damage Liability Insurance covering all automobiles, whether owned, non-owned, leased or hired, with not less

3 than the following limits:. Bodily Injury - $10,000,000 per person and occurrence.”

(Punctuation omitted.) Estate of Mack Pitts v. City of Atlanta (“Pitts I”), 312 Ga. App.

599, 601-602 (719 SE2d 7) (2011).

HM MH hired AWC as one of its subcontractors on Phase 2 of the project.

Pursuant to the [Phase 2] Subcontract, [AWC] agreed to be bound by the terms of the Main Contract, to assume toward [HMMH] all duties and obligations that [HMMH] owed the City under the Main Contract, and to bind all lower tier subcontractors to the obligations set forth in the Main Contract and the Subcontract. The Subcontract expressly required [AWC] to maintain automobile liability insurance coverage for “owned, hired and non-owned vehicles with a $10,000,000 combined single limit for bodily injury and property damage.”

(Punctuation omitted.) Pitts I, 312 Ga. App. at 602.

In June 2007, a truck operated by A&G Trucking, a subcontractor hired by

AWC, killed Mack Pitts, a worker at the site. After Pitts’s estate was unable to collect

the judgment of $5.57 million it obtained against A&G, the estate sued the City,

HMMH, and AW C, asserting inter alia that Pitts had been a third-party beneficiary of

the Subcontract’s provisions requiring defendants’ lower tier subcontractors, including

A&G, with $10 million of automobile liability coverage. In the course of the estate’s

4 action, HMMH asserted a cross-claim against AWC that AW C had breached its duty

under the Phase 2 subcontract to indemnify HM MH as to the estate’s claims.

In December 2010, the trial court granted the Pitts defendants’ motions for

summary judgment on the ground that Pitts had not been a third-party beneficiary of

the Phase 2 subcontracts. The estate appealed this ruling to this Court, which

concluded that Pitts had indeed been a third-party beneficiary of the Phase 2

subcontracts. See Pitts I, 312 Ga. App. at 603-604 (1) (a) (i). The City appealed this

Court’s ruling to the Supreme Court of Georgia, which vacated this Court’s decision

in Pitts I and remanded for further consideration of the third-party beneficiary

question. See Archer Western Contractors v. Estate of Mack Pitts (“Pitts II”), 292 Ga.

219, 230 (4) (735 SE2d 772) (2012). On remand, this Court once again concluded that

Pitts had been a third-party beneficiary of the Phase 2 subcontracts. Estate of Mack

Pitts v. City of Atlanta (“Pitts III”), ___ Ga. App. ___, 2013 Ga. App. LEXIS 654

(Case No. A11A1487, decided July 16, 2013), slip. op. at * 5. We therefore reversed

the trial court’s grant of summary judgment to the construction companies as well as

its denial of summary judgment to the estate. Id.

In the same December 2010 order that granted summary judgment to the Pitts

defendants and formed the basis of the Pitts I, II, and III appeals, the trial court also

5 denied HMMH’s cross-motion for summary judgment and granted AW C’s cross-

motion for the same, holding that AWC had no duty to defend or indemnify HMMH

from any losses incurred in the course of operations at the construction site under the

Phase 2 subcontract. HMMH did not appeal this portion of the December 2010 order.

In December 2011, however, HMMH notified AWC that it would not make any

additional payments to AWC under these two parties’ Phase 3 subcontract until the

conclusion of the Pitts litigation.

AWC brought this action seeking a declaration that it was owed money under

Phase 3 of the project and that the trial court’s order in the Phase 2 litigation precluded

HMMH from withholding payments due under the Phase 3 subcontract when such

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klay v. United Healthgroup, Inc.
376 F.3d 1092 (Eleventh Circuit, 2004)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Continental Insurance v. Equity Residential Properties Trust
565 S.E.2d 603 (Court of Appeals of Georgia, 2002)
Bryan County v. Yates Paving & Grading Co.
638 S.E.2d 302 (Supreme Court of Georgia, 2006)
Simmons Co. v. Deutsche Financial Services Corp.
532 S.E.2d 436 (Court of Appeals of Georgia, 2000)
Hopkins v. WORLD ACCEPTANCE CORP.
798 F. Supp. 2d 1339 (N.D. Georgia, 2011)
American General Financial Services v. Jape
732 S.E.2d 746 (Supreme Court of Georgia, 2012)
Archer Western Contractors, Ltd. v. Estate of Pitts
735 S.E.2d 772 (Supreme Court of Georgia, 2012)
North Augusta Associates Ltd. Partnership v. 1815 Exchange, Inc.
469 S.E.2d 759 (Court of Appeals of Georgia, 1996)
Estate of Pitts v. City of Atlanta
719 S.E.2d 7 (Court of Appeals of Georgia, 2011)
Estate of Pitts v. City of Atlanta
746 S.E.2d 698 (Court of Appeals of Georgia, 2013)
Miller v. GGNSC Atlanta, LLC
746 S.E.2d 680 (Court of Appeals of Georgia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Archer Western Contractors, LLC v. Holder Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/archer-western-contractors-llc-v-holder-construction-company-gactapp-2013.