ARC Designs, Inc. v. Nabors Industrial, Inc.

Court of Appeals of Texas·Decided April 21, 2020·No. 01-18-00992-CV·Published

Opinion

Opinion issued April 21, 2020

In The

Court of Appeals

For The

First District of Texas

the Contract and sued ADI for breach of contract. ADI brought a counterclaim, asserting that Nabors breached the Contract by failing to pay as agreed. The trial court rendered summary judgment in favor of Nabors on its claim and awarded it damages. The trial court denied ADI’s motion for summary judgment on its counterclaim. After a trial to the court on the limited issue of attorney’s fees, the trial court awarded Nabors its fees.

On appeal, ADI presents four issues. In its first issue, ADI contends that the trial court erred in granting summary judgment for Nabors because ADI presented evidence raising a fact issue regarding the applicable termination and damages provisions in the Contract. In its second and third issues, ADI contends that the trial court erred in granting Nabors’s summary-judgment motion, and denying that of ADI, because the trial court misconstrued the Contract terms as providing a right of reimbursement and failed to award ADI certain sums due. In its fourth issue, ADI contends that the trial court erred in awarding attorney’s fees.

We affirm.

Background

Nabors owns and operates land-based drilling rigs and provides oilfield services. ADI is a drilling-structure manufacturing facility and metal fabricator. On February 12, 2014, Nabors retained ADI to fabricate and construct five sets (“Sets”) of drilling rig components. Each Set was comprised of a mast and a substructure.

The Contract Price was $651,248.00 for each mast and $1,276,667.00 for each substructure, or a total of $1,927,915.00 for each Set. The parties agreed, as provided in Article 2.2 of the Contract, that Nabors was to pay the Contract Price for each Set in installments, based on the completion of certain “milestones” in the fabrication and construction process, as follows:

20% of Contract Price within 10 days of execution of [the] Contract by both parties.

25% of Contract Price upon [ADI’s] receipt of all structural steel in [ADI’s] fabrication facility complete with MTR’s that meet contract requirements.

45% of Contract Price upon completing of all Work, including electronic delivery of the Equipment’s data book and all API nameplates affixed to the Equipment.

10% of Contract Price for final payment pursuant to the delivery dates set forth on [the Schedule of Delivery].

Pursuant to the terms of Contract, ADI was to deliver one Set per month for five consecutive months, beginning in October 2014 and ending in February 2015. According to the Schedule of Delivery, Set 1 was to be delivered on October 31, 2014; Set 2 on November 30, 2014; Set 3 on December 31, 2014; Set 4 on January 31, 2015; and, Set 5 on February 28, 2015. The Schedule of Delivery included a “penalty date” occurring 30 days after each due date. And, Article III of the Contract, governing delivery, provided:

3.1 [ADI] shall complete the Work as set forth in [Schedule of Delivery]. . . . [I]f any of the Equipment is delivered after the Penalty Date . . . , then [ADI] shall be liable to [Nabors] for liquidated damages in an amount equal to one (1%) of the

Contract Price for each day that delivery is delayed, provided that in no event shall [ADI] be liable to [Nabors] for more than ten percent (10%) of the Contract Price.

3.2 Time is of the essence with respect to the performance of the Work and there shall be no extension or postponement of the Delivery Date. The Parties agree that this Article is a material term of this Contract for all purposes.

3.3 . . . . Any change to [the Schedule of Delivery] will only be made in writing by agreement of the Parties. . . .

In the event that ADI failed to “conduct its operations” under the Contract with diligence or “otherwise breached its obligations,” Article IX, “Unsatisfactory Performance,” authorized Nabors to elect whether to cover or to pursue other remedies under the law or in equity:

9.1 If [ADI] has failed to conduct its operations under this Contract in a diligent, skillful or workmanlike manner . . . , or if the [ADI]

has otherwise breached its obligations hereunder, [Nabors] may give [ADI] written notice in which the cause of the dissatisfaction shall be specified. Should [ADI] fail to remedy the dissatisfaction within five (5) days after the receipt of the written notice, [Nabors] may, at its discretion take one of the following courses of action:

9.1.1 [Nabors] may retain another Contractor (’’Substitute Contractor”) to complete the remaining Work. In such event [Nabors] shall have no obligation to pay [ADI] any additional sums whatsoever and [ADI] shall be responsible to pay to [Nabors] the difference between the outstanding relevant Purchase Order and the actual cost of completing the Work with the Substitute Contractor.

9.1.2 [Nabors] may take over and complete the Work using [ADI’s] facilities, equipment and personnel. If [Nabors]

takes over the Work, [Nabor’s] cost in completing the Work with no allowance for use of [ADI’s] facilities,

equipment and personnel shall be deducted from the Contract Price . . . .

9.1.3 Upon [Nabors’s] request and pursuant to [Article XI], [ADI] shall allow [Nabors] to remove any and all Equipment in whatever stages of completion as well as other manufactured products related to the Equipment.

9.2 The remedies set forth in this Article are in addition to, and not in lieu of any and all other remedies available to [Nabors] in law or equity.

And, Article 24.4 provided that the “prevailing party in any lawsuit shall be entitled to recover reasonable and necessary attorneys’ fees.”

Article XI, “Termination of the Contract,” provided that Nabors could also terminate the Contract, either at will or for unsatisfactory performance under Article IX above, as follows:

11.1 This Contract may be terminated 11.1.1 By [Nabors] upon 10 days’ notice.

....

11.1.3 By [Nabors] for unsatisfactory performance as set forth in Article IX above.

In the event that Nabors terminated the Contract pursuant to Article 11.1.1, i.e., at will, Article 11.2 governed the amounts owed to ADI as follows:

[Nabors] shall pay to [ADI] all amounts due and owing at the date of termination together with reasonable additional costs incurred by [ADI]

in terminating the Work including if applicable, costs of shipping and the costs of cancellation of subcontracts or purchase orders for materials, equipment and supplies. In no event shall [Nabors] be entitled to payment for any loss of any profit as a result of such termination.

In the event that Nabors terminated the Contract pursuant to Article 11.1.3, i.e., for cause based on ADI’s “unsatisfactory performance as set forth in Article IX above,” Article 11.4 provided that ADI “shall not be entitled to any compensation whatever [sic].”

It is undisputed that ADI did not deliver Set 1 by the date specified in the Schedule of Delivery, that of October 31, 2014. Rather, ADI delivered a portion of Set 1, the substructure, on December 15, 2014. Nabors asserts that, not only was the substructure almost two months late, but it was defective, causing Nabors to incur $175,000.00 to remedy defects. ADI did not complete the mast component of Set 1 until January 2015. On February 3, 2014, after Sets 2, 3, and 4, which the Schedule of Delivery stated were due by November 30, 2014, December 31, 2014, and January 31, 2015, respectively, were not delivered, Nabors issued a change order to reduce the scope of the Contract to Set 1 and the mast component of Set 2. Nabors demanded reimbursement of its milestone payments but stated that it was willing to reduce this sum by a mutually agreed upon amount for ADI’s expenses on the three masts and four substructures being reduced.

Free access — add to your briefcase to read the full text and ask questions with AI

ARC Designs, Inc. v. Nabors Industrial, Inc., (Tex. Ct. App. 2020).

ARC Designs, Inc. v. Nabors Industrial, Inc. (ARC Designs, Inc. v. Nabors Industrial, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Frost National Bank v. L & F Distributors, Ltd.
165 S.W.3d 310 (Texas Supreme Court, 2005)
Seagull Energy E & P, Inc. v. Eland Energy, Inc.
207 S.W.3d 342 (Texas Supreme Court, 2006)
Goodyear Tire and Rubber Co. v. Mayes
236 S.W.3d 754 (Texas Supreme Court, 2007)
Centeq Realty, Inc. v. Siegler
899 S.W.2d 195 (Texas Supreme Court, 1995)
Strange v. Continental Casualty Co.
126 S.W.3d 676 (Court of Appeals of Texas, 2004)
Cathey v. Booth
900 S.W.2d 339 (Texas Supreme Court, 1995)
Kennedy Ship & Repair, L.P. v. Pham
210 S.W.3d 11 (Court of Appeals of Texas, 2006)
B & W SUPPLY, INC. v. Beckman
305 S.W.3d 10 (Court of Appeals of Texas, 2009)
Henry v. Masson
333 S.W.3d 825 (Court of Appeals of Texas, 2010)
Beverick v. Koch Power, Inc.
186 S.W.3d 145 (Court of Appeals of Texas, 2006)
Rhone-Poulenc, Inc. v. Steel
997 S.W.2d 217 (Texas Supreme Court, 1999)
KPMG Peat Marwick v. Harrison County Housing Finance Corp.
988 S.W.2d 746 (Texas Supreme Court, 1999)
Reilly v. Rangers Management, Inc.
727 S.W.2d 527 (Texas Supreme Court, 1987)
MMP, Ltd. v. Jones
710 S.W.2d 59 (Texas Supreme Court, 1986)
AMS Construction Co. v. K.H.K. Scaffolding Houston, Inc.
357 S.W.3d 30 (Court of Appeals of Texas, 2011)
Whittaker v. Byard
25 S.W.3d 118 (Kentucky Supreme Court, 2000)