Aquatrol Corp. v. Altoona City Authority

296 F. App'x 221
CourtCourt of Appeals for the Third Circuit
DecidedOctober 8, 2008
Docket07-3192
StatusUnpublished
Cited by3 cases

This text of 296 F. App'x 221 (Aquatrol Corp. v. Altoona City Authority) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aquatrol Corp. v. Altoona City Authority, 296 F. App'x 221 (3d Cir. 2008).

Opinion

OPINION OF THE COURT

HARDIMAN, Circuit Judge.

Aquatrol Corporation (Aquatrol) appeals an order of the District Court granting Defendants’ Rule 50 motions on Aquatrol’s breach of contract and promissory estoppel claims. The District Court had jurisdiction pursuant to 28 U.S.C. § 1332 and we have appellate jurisdiction pursuant to 28 U.S.C. § 1291. 1 We will affirm.

I.

Because we write for the parties, we recount only those facts essential to our decision.

In 1998, the Altoona City Authority (the Authority) contracted with G.M. McCrossin (McCrossin) to manage the computer upgrade of the Horseshoe Curve Water Treatment Facility Project (the Project). The scope of the work included updating the software utilized by the Authority to make the computer systems at five water treatment plants Y2K-compliant. The contract (Contract) specified that McCrossin hire Aquatrol to complete the upgrade. Aquatrol had installed the previous software manufactured by Wonderware.

In March 1999, McCrossin executed a Purchase Agreement (Agreement) with Aquatrol for the installation and configuration of Y2K-compliant software. The purchase order incorporated specifications for the software upgrade and required that the work be completed by September 1, 1999. The specifications were created by Gwin, Dobson & Foreman, Inc. (GD & F), *223 the Authority’s consulting engineers. MeCrossin agreed to pay Aquatrol $140,849.00 if the upgrade was completed satisfactorily. MeCrossin also reserved the right to cancel the order if it was not completed as specified.

The software installation was not completed as specified. The first attempt by Aquatrol to install updated software was not made until December 1999 — three months after the initial project deadline. Moreover, neither GD & F nor the Authority was satisfied with the update because, inter alia, the software was still not Y2K-compliant. In order to prevent the loss of essential data, the water treatment plant computers needed to be set to a date prior to 2000, but all post-1999 dates could only be entered manually. On January 7, 2000, ,Aquatrol received a memo identifying the continuing failures in the software upgrade. Aquatrol responded to GD & F that the problems were caused by the Wonderware software that was used for the upgrade. On March 16, 2000, GD & F sent Aquatrol a letter informing it that the Authority remained displeased with the software upgrade and stated that payment would not be made until Aquatrol completed the upgrade as specified.

Problems with the upgrade continued. On December 12, 2000, Aquatrol sent the Authority a letter requesting that it agree to equipment upgrades to make the Wonderware software work properly. Aquatrol informed the Authority that the upgrades would add $53,000.00 to the price of the contract. The Authority responded that it would agree to Aquatrol’s proposal but would not pay for the labor and expenses associated with the new installations. Aquatrol rejected this counterproposal.

On April 24, 2001, MeCrossin sent Aquatrol a letter informing it that the Authority issued a “deduct change” for the Aquatrol contract. Accordingly, MeCrossin requested that Aquatrol retrieve any equipment from the Project site. MeCrossin sent Aquatrol a final order cancelling the Agreement in its entirety on May 23, 2001.

Four months later, Aquatrol contacted the Authority with a new offer. Based on its understanding of the Wonderware software settings, Aquatrol offered to complete the Project for the original contract price of $140,849.00. The Authority rejected this offer and eventually contracted with U.S. Filter Control Systems to complete the upgrade.

II.

Aquatrol brought a breach of contract claim against MeCrossin and unjust enrichment and promissory estoppel claims against the Authority. Following Aquatrol’s case in chief, the District Court granted Defendants’ motions for judgment as a matter of law pursuant to Rule 50 of the Federal Rules of Civil Procedure.

We exercise plenary review over a district court’s decision to grant a motion for judgment as a matter of law pursuant to Rule 50(a) of the Federal Rules of Civil Procedure. Northview Motors, Inc. v. Chrysler Motors Corp., 227 F.3d 78, 88 (3d Cir.2000). “[A] directed verdict is mandated where the facts and the law will reasonably support only one conclusion.” Id. (quoting McDermott Int’l, Inc. v. Wilander, 498 U.S. 337, 356, 111 S.Ct. 807, 112 L.Ed.2d 866 (1991)). In our review, we “must draw all reasonable inferences in favor of the nonmoving party.” Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133, 150, 120 S.Ct. 2097, 147 L.Ed.2d 105 (2000).

III.

Aquatrol first argues that the District Court erred in granting McCrossin *224 judgment as a matter of law on Aquatrol’s breach of contract claim. Aquatrol asserts that McCrossin breached the Agreement when it failed to pay after Aquatrol performed the software upgrade in conformity with all applicable specifications.

Although Aquatrol admits that the Wonderware software was not working properly at the time that the contract was cancelled in 2001, 2 it asserts that the “problems were due to bugs in the Wonderware software selected by GD & F.” Aquatrol claims that it satisfied its obligations under the Agreement because it “supplied and installed the Wonderware software as specified in the purchase order (incorporating the specification).” We disagree.

Pennsylvania law states that a contractor or subcontractor, such as Aquatrol, is not responsible for defects caused by problems in a design specification. See A.G. Cullen Constr. Inc. v. State Sys. of Higher Ed., 898 A.2d 1145, 1156 (Pa. Commw.Ct.2006); Rhone Poulenc Rorer Pharms., Inc. v. Newman Glass Works, 112 F.3d 695 (3d Cir.1997). See generally United States v. Spearin, 248 U.S. 132, 54 Ct.Cl. 187, 39 S.Ct. 59, 63 L.Ed. 166 (1918) (providing guidance on the doctrine of implied warranty of design). Design specifications “describe in precise detail the materials to be employed and the manner in which the work is to be performed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
296 F. App'x 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aquatrol-corp-v-altoona-city-authority-ca3-2008.