Aquamarine Associates v. Burton Shipyard, Inc.

645 S.W.2d 477, 1982 Tex. App. LEXIS 5617
CourtCourt of Appeals of Texas
DecidedJune 17, 1982
Docket8456
StatusPublished
Cited by8 cases

This text of 645 S.W.2d 477 (Aquamarine Associates v. Burton Shipyard, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aquamarine Associates v. Burton Shipyard, Inc., 645 S.W.2d 477, 1982 Tex. App. LEXIS 5617 (Tex. Ct. App. 1982).

Opinion

KEITH, Justice.

Plaintiff below appeals from a judgment entered after the trial court had disregarded several jury answers, the result being a serious diminution in the amount of damages awarded to plaintiff.

Plaintiff was a partnership known as Aquamarine Associates 1 which sued defendant, Burton Shipyard, and its president, J.C. Garner. The record is unusually large 2 and the factual presentation of the questions, by both parties, leaves much to be desired.

Basically, the suit is one for breach of contract and the damages flowing therefrom. Plaintiff sued Burton because the latter did not fulfill its contract for the construction of four vessels. Burton, acting through Garner, contracted to build and deliver four ocean-going vessels, the prices and the delivery dates being set out in the margin. 3

Burton breached its contract and did not begin the timely construction of the last three hulls as required. Instead, in February of 1974, while in default upon the second hull, it refused to proceed with construction unless plaintiff agreed to an increase in price and a delayed delivery date.

Plaintiff then negotiated with Texas Maritime Industries (“TMI”) and contracted for the completion of the Burton contract, but at an increased cost of nearly $700,000 over the Burton contract. According to plaintiff, the negotiations were in good faith and at arms’ length. TMI was not an experienced builder and it suffered financial difficulties before it “went broke.” Two of plaintiff’s partners, Cuenod and Chadwick, then acquired the physical assets of TMI and changed its name to South Texas Shipyards (“STS”). They then contracted with their third partner, Gilbert, in a contract whereby STS agreed to act as a substitute to “cover” for the Burton de *479 fault. 4 These contract prices included a ten percent profit for the two partners of plaintiff who then owned STS.

STS did not meet either the contractual prices or delivery dates of Hulls 505 or 516. 5 It is to be noted that the initial contract between the partners did not cover the construction by STS of Hull 517. Later, an agreement was reached but STS did not finish the vessel and it was towed to Halter Marine in Mississippi for completion after Guenod and Chadwick sold out their interest in STS. Hull 517 was finally delivered in August 1978 at a cost of almost four million dollars.

This lengthy resume 0⅛ the evidence, most of which is undisputed and from the testimony of the principals, brings us to the discussion of the first series of complaints— those relating to “cover”. The core of the problem is the cost of reasonable “cover.” Stated differently, if the TMI contract was' reasonable, then no error is shown because the trial court awarded the damages resulting from the Burton breach based upon that hypothesis. Conversely, if the costs incident to the STS-Halter Marine transactions constituted reasonable cover, error has been shown.

We turn first to a consideration of plaintiff’s points four through eleven challenging the court’s actions with reference to the jury findings on this aspect of the appeal.

The rule governing review of a trial court’s actions under Tex.R.Civ.P. 301 were restated in Douglass v. Panama, Inc., 504 S.W.2d 776, 777 (Tex.1974): “[I]t must be determined that there is no evidence upon which the jury could have made the findings relied upon.” And, as said in Williams v. Bennett, 610 S.W.2d 144, 145 (Tex.1980):

“In making this determination we must review the record in the light most favorable to the jury findings considering only the evidence and inferences which support them, and rejecting the evidence and inferences contrary to the findings.” 6

We begin our discussion of the damage question with an overview of the concept of “cover” as used in Special Issues 47 and 48. These issues were derived from Tex.Bus. & Comm.Code Ann. § 2.712 (1968), quoted in the margin. 7 The jury found that plaintiff acted in good faith and without unreasonable delay in its “cover” operation, but the issues were not broken down as to the participants in the “cover” — i.e., whether the inquiry was directed to the TMI agreement, or the STS. substitute, or even Halter Marine.

The findings are summarized:

No. 49(B) Reasonable Replacement Costs 5,984,000.
[Burton’s contract price. 4,609,000.]

Special Issue No. 50 was taken from § 2.713 of the Code and the jury found the damages to be $1,991,000. This answer was properly disregarded as immaterial since § 2.713 is applicable only when the buyer has not “covered” as set out in the preceding section of the Code quoted in the footnote. See § 2.713, Comment 5. 8

*480 Defendants attack the jury finding of “reasonable cost” of the substituted vessels, as found in Special Issue No. 49(B) by pointing to the fact that the evidence supporting the increased costs incurred with STS was hearsay in nature and was stricken from the record on the trial court’s own motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
645 S.W.2d 477, 1982 Tex. App. LEXIS 5617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aquamarine-associates-v-burton-shipyard-inc-texapp-1982.