Aquafortis Associates, LLC v. Maine Department of Environmental Protection

Superior Court of Maine·Decided February 26, 2018·No. LINap-14-01·Unpublished

Opinion

STATE OF MAINE SUPERIOR COURT LINCOLN,SS CIVIL ACTION DOCKET NO. AP-14-01

AQUAFORTIS ASSOCIATES, LLC )

)

Appellant, )

V. ) DECISION AND ORDER )

MAINE DEPARTMENT OF )

ENVIR0Nlv1ENTAL PROTECTION )

)

Respondent. )

INTRODUCTION

This matter is before the Court on an appeal by AquaFortis Associates, LLC, Appellant, from a Water Level Order in Matter #L-22585-36-B-N issued by the Maine Department of Environmental Protection ("DEP''), Respondent, regarding the Clary Lake Dam. This appeal has been brought in accordance with 38 M.R.S. § 346(1), 5 M.R.S.

§§ 1101-1108, and M.R. Civ. P. 80C.

FACTS

The Clary Mill was constructed as a lumber mill in Whitefield, 1 foine in the 1890's

1

over what was then Pleasant Pond Brook by Henry Clary. (Certified Record "C.R." 98;

264 at 6). The Clary Mill site included the mill, a millpond, the mill dam, and other property adjacent to the brook (C.R. 98). Henry Clary built the Clary Lake Darn ("the Dam") in 1903 and purchased some of the land under the newly formed Clary Lake ("the Lake"), created by impounded water from the Dam. (C.R. 98; 264 at 6). To the extent possible, the Dam controls the water levels of the Lake. (C.R. 106 at 1231; 264 at 6).

1 In citations to the Certified Record, page numbers gencra11y refer to the number of the document except for citations to C.R. 106. In citations to C.R. 106, which is a transcript of the public hearing held on Aug. 12, 2012, the page numbers refer to the transcript page numbers, not the document page numbers.

Around 1980, Chester Chase owned the Clary Mill site and converted the hydro-

mechanical usage of the Dam into hydro-electrical by installing a generator. (C.R. 106 at 73 and 80). Around this time, he also filled the Dam's large aperture discharge outlet with a concrete plug. (C.R. 106 at 69; 264 at 6). In 1995, he partitioned the Mill site into multiple parcels which no longer operated in an integrated way, and sold the Dam to the then-president to the Clary Lake Association ("CLA"). (C.R. 108 Ex. R).

Pleasant Pond Mill ("PPM") bought the Clary Mill, milldam, and millpond, including flowage rights, in 2003. (C.R. 1; 108 Ex. R). It purchased the millhouse and the Dam in 2006, placing the entire Mill site under single ownership again. (C.R. 1; 108 Ex. R). In 2010, PPM transferred the land and flowage rights it bought in 2003 to AquaFortis. (C.R. 1; 108 Ex. R). The Dam has not been operated for either hydro-mechanical or hydro- electrical use since at least 2003. (C.R. 106 at 21, 72-73, and 105-106). The Dam currently has a narrow vertical crack in the concrete plug that was installed by Chester Chase. (See C.R. 40 at 7 and 8). However, it is still capable of impounding water and meets the statutory definition of dam. (C.R. 264 at 6).

On Jan. 3, 2012, a group of Clary Lake littoral owners ("Petitioners") filed a Petition to Set Water Levels/Minimum Flows ("the Petition") pursuant to the Water Level Act, 38 M.R.S. § 840 et seq. (See Petition at C.R. 1). The Petition contains the appropriate number of signatures to require the DEP to hold a hearing. (C.R. 1; 38 M.R.S. § 840(1)). The DEP processed the Petition and notified PPM on Feb. 8, 2012. (C.R. 5; 7; 8). The DEP later determined that AquaFortis was a party to the proceedings and granted it full party status over its objections. (C.R. 72; 84; 94; 98; 101; 102). The DEP also granted the CLA intervenor status. (C.R. 92). At this time, the DEP had recently lost one of its most experienced employees in dam-related matters and the Petition would be the DEP's first adjudicatory hearing on a water level petition. (C.R. 4; 106 at 84; 208). Ms. Beth

Callahan, the DEP's Project Manager, was tasked with gathering evidence related to the Dam. (C.R. 134). She exchanged multiple emails with Mr. George Fergusson, Spokesperson for the Petitioners, as well as with PPM and AquaFortis's attorney. (See e.g., C.R 4-7; 29; 39-41; 46-54 and C.R. 30; 54; 56). There was also an email from Mr. Earle Townsend, another DEP employee, to PPM's manager Paul Kelley, Jr. (C.R. 108 Ex. L).

A public hearing on the Petition was held on Aug. 12, 2012 ("the Hearing"t with Ms. Heather Parent presiding as Hearing Officer. (See transcript at CR. 106 and exhibits at C.R. 108). PPM and AquaFortis were represented by the same counsel. (C.R. 106 at 6). At the hearing, Ms. Callahan gave brief background testimony regarding the Petition and her fact-gathering. (CR. 106 at 122-124). Mr. Dave Courtemach, an employee of the DEP's Division of Environmental Assessment, also testified as to the range of recommended water levels, and how he arrived at those figures. (C.R. 106 at 124-137). The record closed after the Hearing on that date, but would remain open for a report provided by PPM to the DEP. (C.R. 84; 106 at 110).

After the Hearing, there were communications between Mr. Fergusson and Ms.

Callahan regarding a bathymetric study of the Lake. (C.R. 116}. The study was conducted on Sept. 21, 2012. (C.R. 118). There is no dispute that PPM and AquaFortis were not given notice of the study until after it was conducted, that neither gave consent for the DEP to enter the property to conduct the study, and that the DEP did not have an administrative search warrant. After the study was completed and its results issued, all parties had the right to request re-opening of the record or to submit comments on the bathymetric study in lieu of cross-examination. (C.R. 146). The Petitioners and PPM provided comments, AquaFortis did not. (C.R. 170). There were no written requests by either party to re-open the record, and it was never reopened.

A draft Water Level Order ("WLO") was issued on Dec. 19, 2013, on which PPM and the Petitioners commented. (C.R. 227; 251; 253; 264 at 3). The final WLO was issued on Jan. 27, 2014. (See WLO at C.R. 264}. It set forth the evidence presented, made findings according to criteria for evidence found in 38 M.R.S. § 840(4), and set Special Conditions with which the dam owner was required to comply. (C.R. 264).

Special Condition 3 requires the dam owner to repair or modify the Dam to an operational state such that it is capable of complying with the WLO. (C.R. 264 at 12). Special Condition 4 requires the dam owner to hire a professional land surveyor to determine the historical normal high water line using certain criteria and parameters and submit a surveyed plan for DEP approval. (C.R. 264 at 13). Special Condition 5 requires the dam owner to submit a water level management plan setting out the Dam's policies and procedures. (C.R. 264 at 13). Special Condition 6 requires the dam owner to permanently mount a gauge on the Dam to measure the water levels, and hire a USGS employee or other professional to inspect it. (C.R. 264 at 14). And Special Condition 7 requires the lake to be maintained at a level within 2.0 foot fluctuation of the normal high water level as determined by the survey in Special Condition 4. (C.R. 264 at 14). The DEP ordered PPM, as the owner of the dam, to comply with these conditions. (C.R. 264 at 12). It found that AquaFortis owns the mill complex, property abutting the Dam, and a structure sitting on top of the Darn, but the DEP did not make an explicit finding of whether Aquafortis is in control of any water flowage rights. (C.R. 264 at 7). Instead, it states that if AquaFortis controls any or all of the flowage rights, it is bound by the WLO along with PPM. (C.R. 264 at 7).

AquaFortis now appeals the WLO, pursuant to l\/1.R. Civ. P. 80C. 2

2 PPM was originally also a party to this appeal. However, it was dismissed on Jan. 25, 2016 after this Court found that it waived or abandoned its rights and lost its standing.

STANDARD OF REVIEW

Free access — add to your briefcase to read the full text and ask questions with AI

Aquafortis Associates, LLC v. Maine Department of Environmental Protection, (Me. Super. Ct. 2018).

Aquafortis Associates, LLC v. Maine Department of Environmental Protection (Aquafortis Associates, LLC v. Maine Department of Environmental Protection) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Poe v. Ullman
367 U.S. 497 (Supreme Court, 1961)
In Re Maine Clean Fuels, Inc.
310 A.2d 736 (Supreme Judicial Court of Maine, 1973)
Molasses Pond Lake Ass'n v. Soil & Water Conservation Commission
534 A.2d 679 (Supreme Judicial Court of Maine, 1987)
Marandino v. Prometheus Pharmacy
986 A.2d 1023 (Supreme Court of Connecticut, 2010)
Sevigny v. City of Biddeford
344 A.2d 34 (Supreme Judicial Court of Maine, 1975)
New England Telephone & Telegraph Co. v. Public Utilities Commission
448 A.2d 272 (Supreme Judicial Court of Maine, 1982)
Friends of Lincoln Lakes v. Board of Environmental Protection
2010 ME 18 (Supreme Judicial Court of Maine, 2010)
Anderson v. Maine Public Employees Retirement System
2009 ME 134 (Supreme Judicial Court of Maine, 2009)
Whitney v. Wal-Mart Stores, Inc.
2006 ME 37 (Supreme Judicial Court of Maine, 2006)
Kroeger v. Department of Environmental Protection
2005 ME 50 (Supreme Judicial Court of Maine, 2005)
Friends of the Boundary Mountains v. Land Use Regulation Commission
2012 ME 53 (Supreme Judicial Court of Maine, 2012)
Bayview Loan Servicing, LLC v. John H. Bartlett
2014 ME 37 (Supreme Judicial Court of Maine, 2014)
John Doe I v. Robert Williams
2013 ME 24 (Supreme Judicial Court of Maine, 2013)
Passadumkeag Mountain Friends v. Board of Environmental Protection
2014 ME 116 (Supreme Judicial Court of Maine, 2014)
Champlain Wind, LLC v. Board of Environmental Protection
2015 ME 156 (Supreme Judicial Court of Maine, 2015)
Lorraine Scamman v. Shaw's Supermarkets, Inc.
2017 ME 41 (Supreme Judicial Court of Maine, 2017)
Department of Corrections v. Public Utilities Commission
2009 ME 40 (Supreme Judicial Court of Maine, 2009)
Stein v. Maine Criminal Justice Academy
2014 ME 82 (Supreme Judicial Court of Maine, 2014)