Appollo v. Reynolds

364 N.W.2d 422, 1985 Minn. App. LEXIS 3910
CourtCourt of Appeals of Minnesota
DecidedMarch 5, 1985
DocketC5-84-1637
StatusPublished
Cited by10 cases

This text of 364 N.W.2d 422 (Appollo v. Reynolds) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appollo v. Reynolds, 364 N.W.2d 422, 1985 Minn. App. LEXIS 3910 (Mich. Ct. App. 1985).

Opinion

OPINION

LESLIE, Judge.

The buyers of several townhouses sued the sellers when they were unable to close on the dates specified in their respective purchase agreements, due to delays in construction. The .trial court awarded the buyers damages caused by the increase in interest rates between the time of the originally scheduled closings and the actual closing dates. The sellers have appealed. We affirm.

FACTS

In 1983 the respondents (“buyers”) each signed purchase agreements for townhouses built and sold by the appellants (“sellers”). The closing dates were specified in the agreements, and the sellers promised to complete and convey the homes on those dates. However, heavy rainfall caused a substantial delay in the completion of the townhouses, and the closings therefore did not take place on the dates indicated in the purchase agreements. The sellers scheduled later closings for September and October 1983, but the buyers refused to close on those dates, claiming that the interest rates had gone up since the originally scheduled closing dates. The loan application agreements signed by the buyers stated that their mortgages could be closed at the interest rate permitted by FHA regulations as of the dates of closing. On the dates originally scheduled for closing the FHA interest rate was 12%, whereas on the actual closing dates the FHA interest rate was 12.5%.

The buyers did eventually agree to close in November 1983, although the interest rates remained high. Because the sellers refused to pay the difference between the interest rate on the originally scheduled closing dates and the interest rate on the actual dates of closing, the buyers sued.

The sellers answered claiming that they could not have closed on the originally scheduled dates anyway because the points were too high. The purchase agreement contained language indicating that the sellers would pay no more than five points. Because the points on the original closing dates were more than five, the sellers argued that performance of the contract was suspended.

The trial court indicated in its memorandum that it was “not impressed” by the sellers’ argument that since the points on the contract closing dates were more than five, the sellers would not have had to close on those dates anyway. The court therefore awarded the buyers the interest rate differential, and the sellers appealed.

ISSUES

1. Did the fact that the points were more than five temporarily suspend the sellers’ obligation to close on the originally scheduled dates?

*424 2. Did the trial court properly award as damages the difference between the rate of interest at the time of the originally scheduled dates of closing and the rate at the time of the actual closings?

ANALYSIS

I.

The sellers argue that their agreement to pay up to five points was a condition precedent to performance of the contract. They claim, therefore, that because the points were more than five on the dates of the originally scheduled closings, this non-occurrence of the condition precedent temporarily suspended their duty to close on the agreed-upon dates.

As noted above, the court rejected this argument, stating:

The court is not impressed by [sellers’] argument that since the points on the contract closing dates were more than 5, the [sellers] would not have had to close anyway on those dates. In that event, their option would have been to return the purchase money. No such offer was ever made to the [buyers]. In fact, the [sellers] had always demanded performance of the contractual agreement except in attempting to cancel the agreements for the alleged [buyers’] non-performance; and then the [sellers] claimed forfeiture of the earnest money.

As the sellers themselves concede, if the townhouses had been ready at the time of the originally-scheduled dates, the closings could still have taken place. The sellers could have paid more points or the buyers could have increased their down payments or obtained alternative financing. The court found that the sellers had always demanded performance of the contract and that the buyers were ready and willing to complete the purchases on their respective closing dates. These are factual determinations, which should be disturbed only if there is no evidence to reasonably support them. Gaertner v. Rees, 259 Minn. 299, 305, 107 N.W.2d 365, 369 (1961). Because the sellers have provided no transcript, these findings will be upheld.

By determining that the sellers continued to demand performance of the agreement, the court implicitly found that the sellers had waived the condition that the points be below five. A party to a contract may waive a condition precedent which exists for his own benefit. Dolder v. Griffin, 323 N.W.2d 773, 778 (Minn.1982), Ignoring a provision in a contract will constitute waiver, Edelstein v. Duluth, M. & I.R. Ry. Co., 225 Minn. 508, 31 N.W.2d 465 (1948), and waiver may be found where a party continues to exercise rights under a contract even though he knows a condition has not occurred or cannot be performed. Kennedy v. Hasse, 262 Minn. 155, 114 N.W.2d 82 (1962). Thus, when the sellers continued to demand performance of the purchase agreement even though the condition concerning points had not been met, the sellers waived that condition.

The trial court determined that if the sellers had wished to be excused from performing on the originally scheduled dates due to the increased number of points, they should have rescinded the contract and returned the buyers’ earnest money. The sellers, however, argue that the increase in points did not extinguish the contract, but merely suspended their duty to perform until the points went down. As authority for this claim, the sellers cite the Restatement of Contracts 2d, which states in relevant part:

§ 225. Effects of the Non-Occurrence of a Condition
(1) Performance of a duty subject to a condition cannot become due unless the condition occurs or its non-occurrence is excused.
(2) Unless it has been excused, the non-occurrence of a condition discharges the duty when the condition can no longer occur.
(3) Non-occurrence of a condition is not a breach by a party unless he is under a duty that the condition occur.

Restatement (Second) of Contracts § 225 (1981). The sellers argue that under the *425 above provision and the comments thereto their duty to close was suspended for a reasonable time until the points fell below five.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Food Market Merchandising, Inc. v. Scottsdale Indemnity Co.
196 F. Supp. 3d 1004 (D. Minnesota, 2016)
Dunn v. National Beverage Corp.
729 N.W.2d 637 (Court of Appeals of Minnesota, 2007)
Steinhilber v. Prairie Pine Mutual Insurance Co.
533 N.W.2d 92 (Court of Appeals of Minnesota, 1995)
National Union Fire Insurance v. Schwing America, Inc.
446 N.W.2d 410 (Court of Appeals of Minnesota, 1989)
Sullivan v. Eginton
406 N.W.2d 599 (Court of Appeals of Minnesota, 1987)
Patterson v. Stover
400 N.W.2d 398 (Court of Appeals of Minnesota, 1987)
Hanson v. Moeller
376 N.W.2d 220 (Court of Appeals of Minnesota, 1985)
Marriage of Cronin v. Cronin
372 N.W.2d 778 (Court of Appeals of Minnesota, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
364 N.W.2d 422, 1985 Minn. App. LEXIS 3910, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appollo-v-reynolds-minnctapp-1985.