Applied Companies v. Secretary of the Army

CourtCourt of Appeals for the Federal Circuit
DecidedJuly 14, 2006
Docket2005-1511
StatusPublished

This text of Applied Companies v. Secretary of the Army (Applied Companies v. Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Applied Companies v. Secretary of the Army, (Fed. Cir. 2006).

Opinion

Error: Bad annotation destination United States Court of Appeals for the Federal Circuit

05-1511

APPLIED COMPANIES,

Appellant,

v.

Francis J. Harvey, SECRETARY OF THE ARMY,

Appellee.

Peter B. Jones, Jones & Donovan, of Newport Beach, California, argued for appellant.

James W. Poirier, Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, of Washington, DC, argued for appellee. With him on the brief were Peter D. Keisler, Assistant Attorney General, David M. Cohen, Director, and Donald E. Kinner, Assistant Director.

Appealed from: Armed Services Board of Contract Appeals United States Court of Appeals for the Federal Circuit

_________________________

DECIDED: July 14, 2006 _________________________

Before MICHEL, Chief Judge, NEWMAN and RADER, Circuit Judges.

MICHEL, Chief Judge.

Applied Companies (“Applied”) appeals the decision of the Armed Services

Board of Contract Appeals (“Board”) denying the majority of its claim under the Value

Engineering clause of its contract with the United States Army. Applied Co., ASBCA

No. 50593, 04-2 BCA P32,786 (Nov. 2, 2004). Because the Board correctly concluded

that Applied was not entitled to share in future savings on air conditioner (“AC”) models

not covered by Applied’s contract with the Army, we affirm.

I

In 1985, Applied entered into a contract with the United States Army Troop

Support Command (“TROSCOM”) to supply 36,000 (“36k”) BTU/HR horizontal ACs

(“Applied ACs”). The contract incorporated by reference the 1984 version of FAR 52.248-1, entitled “Value Engineering” (“VE clause”), which provides that “[t]he

Contractor is encouraged to develop, prepare, and submit value engineering change

proposals (VECP’s) voluntarily. The Contractor shall share in any net acquisition

savings realized from accepted VECP’s, in accordance with the incentive sharing rates

in paragraph (f) below.” For a fixed-price contract such as Applied’s, paragraph (f)

provides that the contractor shall be entitled to fifty percent of the net acquisition

savings under the instant contract and future contracts.

In 1989, Applied’s CEO, Barney Klinger, suggested to Col. Clarence Mills, then

the Deputy Commander for Procurement and Readiness at TROSCOM, and to a Mr.

Mabrey, TROSCOM’s Director of Procurement and Production, that certain parts in the

Applied AC could be replaced with commercial parts at significant savings. A few

months later, Col. Mills met with Mr. Klinger at a trade conference and suggested that

Applied submit a VECP. Following several additional meetings with TROSCOM,

Applied submitted a VECP on July 7, 1989, which contained a list of specific

commercial part substitutions for the Applied AC. The Army Contracting Officer (“CO”)

conditionally accepted the VECP on July 25, 1989, pending successful testing of the

“commercialized” ACs. The CO unconditionally accepted Applied’s VECP on October

15, 1990, and calculated the “Contractor Share of Net Instant Acquisition Savings” to be

$1,540,181.

On January 9, 1995, Applied submitted a claim to the Army for “one half

anticipated savings of the total of $81 million to be realized by the Army” owing to the

Army’s “abandonment of ‘specified source control’ vendors” in favor of commercially

available parts for all twenty-three air conditioning models covered by military

05-1511 2 specification MIL-A-52767.1 Applied conceded that its VECP was limited to the Applied

AC, and that the VECP “effectively excluded the collateralized savings expected” from

the application of commercialization to the entire family of ACs, yet argued that it was

entitled to share in cost savings for “the concept proposed by Applied in the VECP.” In

a follow-up letter, Applied reiterated that, in its VECP, it had “agreed to forego

collateralized savings on other Army contracts wherein commercial components would

be substituted.” Nonetheless, Applied argued that it was entitled to VE savings for all

AC models to which the Army had applied the commercialization concept included in

Applied’s VECP.

On November 27, 1996, the CO denied Applied’s claim for lack of proof of

entitlement. In October 2001, the parties settled the matter of instant savings, leaving in

dispute only future savings, for which Applied sought $19,806,796.2 The Board held an

evidentiary hearing on November 11, 2001, at which Col. Mills, Mr. Mabrey, and Mr.

Klinger testified. Three years later, the Board issued a plurality opinion awarding

Applied nearly $1 million, representing fifty percent of the savings on future purchases

of 36k BTU/HR horizontal ACs. The plurality denied the remainder of Applied’s claim

1 Military specification MIL-A-52767 covered a total of twenty-three air conditioning models in five sizes (6k, 9k, 18k, 36k, and 60k BTU/HR), vertical and horizontal configurations, and various electric power classes. Each of the twenty-three models had its own detailed design drawing package. The components of each model were basically the same, but varied in size, capacity, and shape. 2 The Board quantified Applied’s claim by taking fifty percent of Applied’s initial demand for a share of the Army’s $81 million cost savings, or $40.5 million, and splitting that amount equally between the two Applied VECP claims appealed to the Board. (The second claim related to another VECP, submitted under a separate contract for 36k BTU/HR vertical ACs, and was settled in October 2001.) Accordingly, Applied originally sought $20.25 million in this suit. Following the October 2001 partial settlement, that claim was reduced to the present figure.

05-1511 3 because Applied failed to prove the “future unit cost savings” for ACs other than the 36k

BTU/HR horizontal model. Thus, the plurality held that the VE savings was applicable

only to future purchases of 36k BTU/HR horizontal ACs, and not to ACs of any other

size or configuration.

Applied filed a motion for reconsideration, arguing that the Board committed legal

error in placing upon it the burden of proving future unit cost reduction. On June 13,

2005, the Board issued a reconsideration opinion affirming its original decision. Applied

Co., ASBCA No. 50593, 05-2 BCA P32,986 (June 13, 2005) (“Reconsideration”). This

appeal followed. We have jurisdiction under 28 U.S.C. § 1295(a)(10).

II

The dispositive issue on appeal is to which AC models the VECP applies; this

inquiry involves both the regulatory language of the VE clause and the language of

Applied’s agreement with the Army. Interpretation of regulations and contracts are

questions of law that we review de novo. Lane v. Principi, 339 F.3d 1331, 1339 (Fed.

Cir. 2003) (regulatory interpretation); Lockheed Martin IR Imaging Sys. v. West, 108

F.3d 319, 322 (Fed. Cir. 1997) (contract interpretation).

A

Part (b) of the VE clause defines “Acquisition savings” as “savings resulting from

the application of a VECP to contracts awarded by the same contracting office or its

successor . . . for essentially the same unit.” It defines “Unit” as “the item or task to

which the Contracting Officer and the Contractor agree the VECP applies.” Part (c) of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Applied Companies v. Secretary of the Army, Counsel Stack Legal Research, https://law.counselstack.com/opinion/applied-companies-v-secretary-of-the-army-cafc-2006.