Applied Companies v. Francis J. Harvey, Secretary of the Army

456 F.3d 1380
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 12, 2006
Docket05-1511
StatusPublished
Cited by1 cases

This text of 456 F.3d 1380 (Applied Companies v. Francis J. Harvey, Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Applied Companies v. Francis J. Harvey, Secretary of the Army, 456 F.3d 1380 (Fed. Cir. 2006).

Opinion

MICHEL, Chief Judge.

Applied Companies (“Applied”) appeals the decision of the Armed Services Board of Contract Appeals (“Board”) denying the majority of its claim under the Value Engineering clause of its contract with the United States Army. Applied Co., ASBCA No. 50593, 04-2 BCA P32,786 (Nov. 2, 2004). Because the Board correctly concluded that Applied was not entitled to share in future savings on air conditioner (“AC”) models not covered by Applied’s contract with the Army, we affirm.

I

In 1985, Applied entered into a contract with the United States Army Troop Support Command (“TROSCOM”) to supply 36,000 (“36k”) BTU/HR horizontal ACs (“Applied ACs”). The contract incorporated by reference the 1984 version of FAR 52.248-1, entitled ‘Value Engineering” (“VE clause”), which provides that “[t]he Contractor is encouraged to develop, prepare, and submit value engineering change proposals (VECP’s) voluntarily. The Contractor shall share in any net acquisition savings realized from accepted VECP’s, in accordance with the incentive sharing rates in paragraph (f) below.” For a fixed-price contract such as Applied’s, paragraph (f) provides that the contractor shall be entitled to fifty percent of the net acquisition savings under the instant contract and future contracts.

In 1989, Applied’s CEO, Barney Klinger, suggested to Col. Clarence Mills, then the Deputy Commander for Procurement and Readiness at TROSCOM, and to a Mr. Mabrey, TROSCOM’s Director of Procurement and Production, that certain parts in the Applied AC could be replaced with commercial parts at significant savings. A few months later, Col. Mills met with Mr. Klinger at a trade conference and suggested that Applied submit a VECP. Following several additional meetings with TROS-COM, Applied submitted a VECP on July 7, 1989, which contained a list of specific commercial part substitutions for the Applied AC. The Army Contracting Officer (“CO”) conditionally accepted the VECP on July 25, 1989, pending successful testing of the “commercialized” ACs. The CO defínitized VECP savings on October 15, 1990, and calculated the “Contractor Share of Net Instant Acquisition Savings” to be $1,540,181.

On January 9, 1995, Applied submitted a claim to the Army for “one half anticipated savings of the total of $81 million to be realized by the Army” owing to the Army’s “abandonment of ‘specified source control’ vendors” in favor of commercially available parts for all twenty-three air conditioning models covered by military specification *1382 MIL-A-52767. 1 Applied conceded that its VECP was limited to the Applied AC, and that the VECP “effectively excluded the collateralized savings expected” from the application of commercialization to the entire family of ACs, yet argued that it was entitled to share in cost savings for “the concept proposed by Applied in the VECP.” In a follow-up letter, Applied reiterated that, in its VECP, it had “agreed to forego collateralized savings on other Army contracts wherein commercial components would be substituted.” Nonetheless, Applied argued that it was entitled to VE savings for all AC models to which the Army had applied the commercialization concept included in Applied’s VECP.

On November 27, 1996, the CO denied Applied’s claim for lack of proof of entitlement. In October 2001, the parties settled the matter of instant savings, leaving in dispute only future savings, for which Applied sought $19,806,796. 2 The Board held an evidentiary hearing on November 11, 2001, at which Col. Mills, Mr. Mabrey, and Mr. Klinger testified. Three years later, the Board issued a plurality opinion awarding Applied nearly $1 million, representing fifty percent of the savings on future purchases of 36k BTU/HR horizontal ACs. The plurality denied the remainder of Applied’s claim because Applied failed to prove the “future unit cost savings” for ACs other than the 36k BTU/HR horizontal model. Thus, the plurality held that the VE savings was applicable only to future purchases of 36k BTU/HR horizontal ACs, and not to ACs of any other size or configuration.

Applied filed a motion for reconsideration, arguing that the Board committed legal error in placing upon it the burden of proving future unit cost reduction. On June 13, 2005, the Board issued a reconsideration opinion affirming its original decision. Applied Co., ASBCA No. 50593, 05-2 BCA P32,986 (June 13, 2005) (“Reconsideration ”). This appeal followed. We have jurisdiction under 28 U.S.C. § 1295(a)(10).

II

The dispositive issue on appeal is to which AC models the VECP applies; this inquiry involves both the regulatory language of the VE clause and the language of Applied’s agreement with the Army. Interpretation of regulations and contracts are questions of law that we review de novo. Lane v. Pricipi, 339 F.3d 1331, 1339 (Fed.Cir.2003) (regulatory interpretation); Lockheed Martin IR Imaging Sys. v. West, 108 F.3d 319, 322 (Fed.Cir.1997) (contract interpretation).

A

Part (b) of the VE clause defines “Acquisition savings” as “savings resulting from the application of a VECP to contracts awarded by the same contracting office or its successor ... for essentially *1383 the same unit.” It defines “Unit” as “the item or task to which the Contracting Officer and the Contractor agree the VECP applies.” Part (c) of the VE clause, which discusses VECP preparation, instructs that the Contractor “shall include in each VECP ... (3) Identification of the unit to which the VECP applies.” The language of the regulation is unambiguous. It is incumbent upon the contractor to propose a definition of “unit”, and thus to propose any additional models for which it seeks to share in cost savings, in its VECP. As with any other contract term, the parties may then negotiate from the contractor’s proposal until a final agreement is reached.

To determine the scope of VE savings, the proper focus of the analysis is the agreement between the CO and the contractor. Here, that “agreement” consists of: Applied’s VECP; mod P9, which conditionally accepted the VECP; and mod P15, which definitized mutually agreed upon cost savings data in accordance with Applied Companies’ fax of December 20, 1991.

The language of the VECP is unambiguous. It names only the contract for the Applied AC, and indeed specifies only the Applied AC’s unique drawing set. After submitting its VECP, Applied sent three subsequent letters of correction and clarification, none of which purported to alter the scope of the VECP, and two of which referred specifically to “the commercialization of the 36k Horizontal [AC].” As AJ Kienlen rightly noted in his opinion concurring with the Board’s reconsideration decision, the VE clause “clearly allowfs] the parties to agree that the VECP applies to the entire family [of ACs].” Reconsideration, slip op.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
456 F.3d 1380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/applied-companies-v-francis-j-harvey-secretary-of-the-army-cafc-2006.