Appeal of Rehabilitation Associates of New England

556 A.2d 1183, 131 N.H. 560, 1989 N.H. LEXIS 22
CourtSupreme Court of New Hampshire
DecidedApril 7, 1989
DocketNo. 88-225
StatusPublished
Cited by8 cases

This text of 556 A.2d 1183 (Appeal of Rehabilitation Associates of New England) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Rehabilitation Associates of New England, 556 A.2d 1183, 131 N.H. 560, 1989 N.H. LEXIS 22 (N.H. 1989).

Opinions

JOHNSON, J.

In this appeal from a decision and a denial of a motion for reconsideration by the New Hampshire Health Services Planning and Review Board (the board), the plaintiff, Rehabilitation Associates of New England (RANE), raises the following issues: (1) whether RANE, as a holder of a certificate of need, may re-site its planned facility within the same service area without first obtaining board approval; and (2) whether the board abused its discretion in failing to grant RANE a six-month extension of the time period in which RANE had to commence construction of the facility. We hold that RANE’s re-siting of the facility from a site in Allenstown to the grounds of the Concord Hospital in Concord did not require prior board approval. Because we find that RANE had commenced construction of the facility by the statutorily required date, we do not reach the second issue.

In September 1984, RANE, a New Hampshire limited partnership, filed an application for a certificate of need (CON) with the New Hampshire Certificate of Need Review Board (the board), the predecessor of the New Hampshire Health Services Planning and Review Board, for a 100-bed comprehensive acute physical rehabilitation facility which would include the treatment of head injuries. Although the application stated that the facility was to be situated in the Concord region, it did not specify a particular site. During the review process which followed filing, RANE indicated that it had an option to purchase land in Allenstown and planned to build its facility there.

[562]*562The board initially denied the CON. However, following a hearing on a motion for reconsideration, the board granted RANE a CON to build its facility at a cost of $15,500,000. Following an appeal by other health care providers who claimed that they had not been provided with adequate notice of the reconsideration hearing, we affirmed the board’s decision. Appeal of Catholic Medical Center, 128 N.H. 410, 515 A.2d 1205 (1986). Because RANE was unable to commence construction of its facility pending final decision by this court, the board ruled that RANE had eighteen months from October 6, 1986, the date that this court had denied a motion for reconsideration, to commence construction of its facility. See RSA 151-C:12, 1(b)(2) (Supp. 1988). Construction thus had to begin by April 6, 1988.

In March 1987, RANE indicated to the board that it preferred to build the facility on the grounds of the Concord Hospital in Concord, rather than on the Allenstown site, some seven miles away. At a meeting of the board held on May 22, 1987, RANE informed the board that it had signed a letter of intent with the Concord Hospital and requested permission to move the facility to that site. RANE emphasized that it had no intention of changing the scope of the project or the type of services offered, or increasing the cost of development. RANE was told that its request for approval of the site change was premature. The board chairman instructed RANE to conclude its negotiations with Concord Hospital and then show the board a final “package”; at that point the board would determine whether the change constituted a “change in scope” and, if it did, whether the board would allow it. RANE submitted a detailed packet of information on March 4, 1988, which included a request for a six-month extension of the period during which it had to commence construction of its facility, as well as a discussion of the merits of locating the rehabilitation facility on the grounds of the Concord Hospital.

On March 23, 1988, RANE moved for a hearing in which to demonstrate that it had the necessary “good cause” to support its request for a six-month extension. In the memorandum of law which it submitted to support the motion, RANE contended that protracted negotiations with the Concord Hospital, which it asserted culminated in an “unprecedented” relationship of great benefit to the public, entitled RANE to such an extension. RANE also renewed its request for a ruling that the change in the site of RANE’s rehabilitation facility would not constitute a change in the “scope” or “location” of the facility. Following a hearing held on March 25, the board denied RANE’s request for the six-month [563]*563extension. It did not rule on the question of whether RANE’s proposed site change would constitute a change in scope. The board chairman informed RANE that the “CON is good to build in Allenstown until the 6th of April.” Implicit in this ruling, and the May 22, 1987 ruling, was the assumption that RANE could build on the Concord site only if the board had previously ruled either that such a site change did not constitute a change in scope or, if it did, that such a change was permissible.

On April 4, 1988, two days before the commencement period would expire, RANE began construction at the site in Concord. It then filed a motion for reconsideration with the board, to which it attached (1) a ground lease agreement between RANE and Capital Region Health Care Corporation, the parent corporation of Concord Hospital; (2) a contract between RANE and Commercial Construction, Inc. for the building of the Concord facility; (3) certification by the president of the corporate general partner of RANE that the document was a true and correct copy of the construction contract; and (4) a copy of a check payable to the order of Commercial Construction, Inc. in the amount of $18,370 for payment of the construction which had taken place. On April 7, 1988, RANE voluntarily suspended construction of its facility. On May 20, 1988, the board denied the motion for reconsideration. This appeal followed. The State, as amicus curiae, and St. Joseph Hospital & a. have filed briefs in support of the board’s decision. Capital Region Health Care Corporation filed a brief as amicus curiae in support of RANE’s appeal.

The first question we address is whether RANE could re-site the facility approved by the CON under RSA chapter 151-C (Supp. 1988), which governs the granting of CONS, without first obtaining board approval. If the answer to that question is in the affirmative, we will consider whether RANE’s activities constituted commencement in accordance with RSA 151-C: 12, 1(b)(2) (Supp. 1988).

RSA chapter 151-C (Supp. 1988) allows the State, through the board, to control the development of new institutional health services in this State in accordance with standards relative to the affordability and quality of such services. One of the policies underlying the statute is to promote the “rational allocation of health care resources in the state.” RSA 151-C:1, I (Supp. 1988). Under the statutory scheme, a new facility cannot be built, or a new service at an existing facility offered, without the provider’s first obtaining a CON from the board. RSA 151-CU4 (Supp. 1988). When the board determines that there is a need for additional health services, it must issue a request for applications for the [564]*564service. RSA 151-C:8, I (Supp. 1988). What information must be included in the application is determined by rules issued by the board. RSA 151-C:8, IV (Supp. 1988).

According to New Hampshire Administrative Rules He-Hea 301.04 and He-Hea 302.01, every application must contain, inter alia, a description of the project, its cost, and its relationship to the existing State health care system and to the applicant’s long term goals. N.H. Admin. Rules, He-Hea 301.04(a), (h), (n), (o); HeHea 302.01(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Appeal of St. Joseph Hospital
886 A.2d 1005 (Supreme Court of New Hampshire, 2005)
State v. Melcher
678 A.2d 146 (Supreme Court of New Hampshire, 1996)
Manchenton v. Auto Leasing Corp.
605 A.2d 208 (Supreme Court of New Hampshire, 1992)
Appeal of Salem Regional Medical Center
590 A.2d 602 (Supreme Court of New Hampshire, 1991)
Dionne v. City of Manchester
589 A.2d 1016 (Supreme Court of New Hampshire, 1991)
Snyder v. New Hampshire Savings Bank
592 A.2d 506 (Supreme Court of New Hampshire, 1991)
Catalano v. Town of Windham
578 A.2d 858 (Supreme Court of New Hampshire, 1990)
Chambers v. Geiger
573 A.2d 1356 (Supreme Court of New Hampshire, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
556 A.2d 1183, 131 N.H. 560, 1989 N.H. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-rehabilitation-associates-of-new-england-nh-1989.