Appeal of Milford Water Works

489 A.2d 627, 126 N.H. 127, 1985 N.H. LEXIS 258
CourtSupreme Court of New Hampshire
DecidedFebruary 21, 1985
DocketNo. 84-048
StatusPublished

This text of 489 A.2d 627 (Appeal of Milford Water Works) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Milford Water Works, 489 A.2d 627, 126 N.H. 127, 1985 N.H. LEXIS 258 (N.H. 1985).

Opinion

DOUGLAS, J.

This is an appeal by the Milford Water Works (utility) for relief from two conditions contained in an order by the New Hampshire Public Utilities Commission (PUC) granting the petition of that utility to exempt it from the zoning ordinances of the town of Amherst with regard to the laying of pipes from a well owned by the utility and located in Amherst to the utility’s customers in Milford. We hold that the PUC had the authority to impose the contested conditions and that they are not unreasonable.

The Milford Water Works has been owned and operated by the town of Milford since 1890. It became a public utility in 1960 pursuant to RSA 38:12 and RSA 374:22 when it extended its lines and service into a limited area of the town of Amherst, separate and distinct from the location involved here.

Until February 1983, Milford drew its water from three wells, all located in the town of Milford, with a total pumping capacity of 1,100 gallons per minute. In anticipation of future demand, Milford planned to construct a fourth well, which was projected to supply an additional 500 gallons per minute.

In February 1983, the New Hampshire Water Supply and Pollution Control Commission (WSPCC) discovered, through routine sampling, that one of Milford’s three wells had unsafe concentrations of volatile organic chemicals and ordered that well closed. The WSPCC further ordered the utility to abandon its plan to construct the proposed fourth well because of possible contamination. This order caused Milford to lose 500 gallons per minute, or between 40 and 45 percent of its current water supply, in addition to losing the projected 500 gallons per minute from the proposed well. Milford [129]*129implemented emergency water rationing and began an immediate search for an additional water supply.

Studies conducted by the WSPCC and by a consulting firm hired by Milford indicated that there were no potential well sites within the town of Milford which would likely be free of pollutants. Both the WSPCC and Milford’s consultants advised that the only adequate and safe site for a new well would be on land in Amherst, owned by the town of Milford, known as the Curtis Farm.

The Curtis Farm fronts on the Souhegan River, which at that point forms the boundary between Milford and Amherst. Tests indicated that the projected well field could support two gravel-packed wells that would pump 1,100 gallons per minute.

The utility obtained the necessary permits from the WSPCC, pursuant to RSA 149:8-a, and from the State Wetlands Board, pursuant to RSA 483-A:l (Supp. 1983). Construction began immediately on both wells. The utility did not, however, seek the PUC’s approval to begin construction in Amherst before construction commenced, as required by RSA 374:22.

The first well came “on-line” on July 16, 1983, although the second was still under construction at the time of the PUC hearing. The pipeline connecting the wells to the utility’s customers extends approximately 400 feet to the Souhegan River and then about another 100 feet across the river to a pumping station on the Milford side.

In compliance with a condition of WSPCC approval of the project, the utility dug seven monitoring wells, the purpose of which was to observe the water table and measure the impact of the Curtis Farm wells on the surrounding aquifer.

Prompted by concern about the effects of the Curtis Farm wells upon their own water supplies, seventy-nine neighboring Amherst residents formed a group called United Souls Urging Responsible Precaution with the catchy acronym USURP and, in typical American fashion, filed an equity petition in Hillsborough County Superior Court naming the Town of Milford as respondent. As a result of that petition, a settlement agreement was reached on July 18,1983, wherein Milford agreed to apply to the PUC pursuant to RSA 31:62 for an exemption from the zoning ordinances of Amherst for the laying of pipes. The Town of Milford further agreed to install two additional monitoring wells and to limit the draw from the Curtis Farm well to 600,000 gallons per day until the PUC rendered its decision.

On July 25, 1983, after the project had been substantially completed, the Town of Milford, on behalf of the utility, petitioned the PUC for a ruling pursuant to RSA 31:62 that the construction of certain structures, including pipelines, wells, well houses and pump[130]*130ing equipment over an expanse of approximately 400 feet within the confines of the town of Amherst, was reasonably necessary for the convenience and welfare of the public and that, accordingly, the above described structures were exempt from the zoning ordinances of Amherst.

On September 6, 1983, a hearing was held in each of the two affected towns. Both Amherst and Milford presented expert testimony, and members of the public voiced their concerns regarding the possible adverse effects of the Curtis Farm wells on the ground water supplies affecting neighboring wells. Although expert testimony indicated that such effects would be “minimal,” testimony by numerous residents living within 2,500 feet of the Curtis Farm wells indicated a possible causal relationship between pumping from the Curtis Farm well then in operation and substantial drops in water levels experienced in their Wells, ponds and streams.

On October 28, 1983, the PUC, by Order No. 16,737, granted the town’s petition for exemption from the Amherst zoning ordinances under RSA 31:62, but attached certain conditions. The utility was required to: 1) maintain and monitor twice weekly nine test wells and make the results from such monitoring available to the selectmen of Amherst; 2) establish an emergency water supply within twenty-four hours to any person residing within 2,500 feet of the Curtis Farm wells whose water supply should fail, pending either construction of a permanent service connection or a determination by the PUC that the utility did not cause such failure; and 3) provide a permanent pipeline and hookup to any such person free of charge unless the utility could demonstrate that some factor other than the Curtis Farm well pumping caused the failure.

The utility did not contest its obligations regarding the test wells, but requested a rehearing on the other two conditions. The utility’s motion for rehearing was denied by the PUC on December 30,1983, by Supplemental Order No. 16,834.

The utility appealed to this court pursuant to RSA 541:6. It argues that the conditions relating to its obligations to provide emergency service to neighboring residents whose water supplies may fail, and to provide permanent hookup free of charge unless it can demonstrate that such failure was not related to the Curtis Farm wells, are unlawful and unreasonable.

The utility contends that the PUC exceeded its authority in imposing these conditions because RSA 31:62 gives the PUC power only to grant or deny an exemption from local zoning ordinances and contains no provision for the imposition of accompanying conditions. It further argues that the PUC had no authority under its general supervisory powers to attach such conditions.

[131]*131The pertinent part of RSA 31:62 states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. City of Nashua
308 A.2d 847 (Supreme Court of New Hampshire, 1973)
Pereira v. New England LNG Co., Inc.
301 N.E.2d 441 (Massachusetts Supreme Judicial Court, 1973)
In Re Petition of Monmouth Consolidated Water Co.
220 A.2d 189 (Supreme Court of New Jersey, 1966)
In Re Public Service Electric & Gas Co.
241 A.2d 15 (New Jersey Superior Court App Division, 1968)
Petition of Boston & Maine Corp.
251 A.2d 332 (Supreme Court of New Hampshire, 1969)
Parker-Young Co. v. State
145 A. 786 (Supreme Court of New Hampshire, 1929)
Opinion of the Justices
179 A. 344 (Supreme Court of New Hampshire, 1935)
Appeal of Granite State Electric Co.
435 A.2d 119 (Supreme Court of New Hampshire, 1981)
Appeal of Public Service Co.
454 A.2d 435 (Supreme Court of New Hampshire, 1982)
Sklar Realty, Inc. v. Town of Merrimack
480 A.2d 149 (Supreme Court of New Hampshire, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
489 A.2d 627, 126 N.H. 127, 1985 N.H. LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-milford-water-works-nh-1985.