Appeal of Granite State Electric Co.

435 A.2d 119, 121 N.H. 787
CourtSupreme Court of New Hampshire
DecidedSeptember 16, 1981
DocketNo. 80-390
StatusPublished
Cited by6 cases

This text of 435 A.2d 119 (Appeal of Granite State Electric Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Granite State Electric Co., 435 A.2d 119, 121 N.H. 787 (N.H. 1981).

Opinion

Douglas, J.

Granite State Electric Company (Granite State) appeals an order of the public utilities commission (PUC) establishing a minimum rate at which it must purchase electric power from small power producers (SPP) of hydroelectric power over the life of their projects. Granite State challenges both the rate and the fact that the PUC set that rate as a minimum for the life of the power projects. We reverse and remand.

In 1978, the New Hampshire Legislature enacted the Limited Electrical Energy Producers Act (LEEPA), RSA ch. 362-A (Supp. 1979), “to provide for small scale diversified sources of supplemental electrical power to lessen the state’s dependence upon other sources which may, from time to time, be uncertain.” RSA 362-A:l (Supp. 1979). That statute requires an electric utility, in certain circumstances, to purchase the entire output of electric power produced by a limited electrical energy producer, RSA 362-A:3 (Supp. 1979), at a rate set by the PUC. RSA 362-A:4 (Supp. 1979). That same year, the United States Congress enacted the Public Utility Regulatory Policies Act of 1978, Pub. L. No. 95-617, 92 Stat. 3117 (1978) (PURPA), which contained similar provisions requiring the Federal Energy Regulatory Commission (FERC) to prescribe rules to encourage, inter alia, small power production, including rules requiring electric utilities to purchase power from small power production facilities. PURPA § 210, 16 U.S.C.A. § 824a-3 (Supp. 1981).

On October 18, 1979, the PUC, pursuant to authority of RSA 362-A:4 (Supp. 1979) and PURPA § 210(f), 16 U.S.C.A. § 824a-3(f) (Supp. 1981), initiated hearings to determine the proper rate that an electric utility would be required to pay for energy produced by an SPP. Although LEEPA, RSA 362-A:4 (Supp. 1979), does not set standards for determination of that rate, PURPA does. PURPA § 210(b), 16 U.S.C.A. § 824a-3(b) (Supp. 1981), requires that, under FERC rules, the rates for purchases by electric utilities “shall be just and reasonable to the electric consumers of the electric utility and in the public interest” and shall not exceed “the incremental cost to the electric utility of alternative electric energy.” “Incre[790]*790mental cost of alternative electric energy” is defined as “the cost to the electric utility of the electric energy which, but for the purchase from such . . . small power producer, such utility would generate or purchase from another source.” PURPA § 210(d), 16 U.S.C.A. § 824a-3(d) (Supp. 1981).

The FERC rules implementing PURPA § 210 changed the term “incremental cost” to “avoided costs,” 18 C.F.R. § 292.101(b)(6) (1980), and defined it to include “both the fixed and the running costs on an electric utility system which can be avoided by obtaining energy or capacity from qualifying facilities.” 45 Fed. Reg. 12,216 (1980). (Emphasis added.) FERC classified costs as “energy” costs and “capacity” costs. Id. “Energy costs are the variable costs associated with the production of electric energy (kilowatt-hours). They represent the cost of fuel, and some operating and maintenance expenses. Capacity costs are the costs associated with providing the capability to deliver energy; they consist primarily of the capital costs of facilities.” Id. FERC also determined that incremental costs, not average system costs, should be used to calculate avoided costs because, “[u]nder the principles of economic dispatch, utilities generally turn on last and turn off first their generating units with the highest running cost. At any given time, an economically dispatched utility can avoid operating its highest-cost units as a result of making a purchase from a qualifying facility.” Id.

After six days of hearings, the PUC issued an order dated June 18, 1980, in which it rejected the utilities’ position that avoided costs should be based solely on average fuel costs. The commission chose instead to follow the FERC concept of avoided costs. It adopted its staffs recommendation for a formula to arrive at avoided costs that included: base fuel cost; an “adder” for daily peak operation; a correction for forced outages; an inventory cost; and operation and maintenance expense; plus an added amount for capacity. Because precise data on all those costs were not available, the PUC used figures for Public Service Company of New Hampshire’s (PSNH) newest oil-fired generating unit, Newington Station, as a “proxy,” noting in its report that the parties “agreed” to the proxy. The PUC used that data to arrive at an avoided cost figure that rounded out to 8.2 cents per kilowatt-hour for all utilities except Granite State. Finding that Granite State had excess capacity, the PUC did not add the capacity component to that utility’s costs and, accordingly, found its avoided costs to be 7.7 cents per kilowatt-hour, when rounded upward. Those rates were established as a minimum for the life of qualifying facilities, but the PUC indicated that it would consider future increases.

[791]*791On July 14, 1980, Granite State filed a motion for rehearing on several grounds, including the assertions that the rate set for Granite State had no basis in the record and that the minimum rate for the lifetime of an SPP facility was unlawful. The PUC held oral argument on the motion, and Granite State advised the PUC that it had never agreed to the Newington proxy, offering to provide additional testimony to demonstrate that 7.7 cents per kilowatt-hour exceeded its avoided costs. The PUC issued a second order denying the motion for rehearing, rejecting the offer of additional testimony, and reaffirming the minimum lifetime rate on policy grounds. Granite State appealed to this court pursuant to RSA 541:6.

Granite State argues that there is insufficient evidence in the record to support the PUC’s determination of its avoided cost rate. It specifically claims that, because the rate was derived from figures for PSNH, there is no support in the record for applying those figures to Granite State. Under RSA 541:13, the PUC’s findings are presumed reasonable and its order will not be overturned unless Granite State can show by a clear preponderance of the evidence that it is unjust or unreasonable. Legislative Util. Consumers’ Council v. Public Util. Com., 117 N.H. 972, 974, 380 A.2d 1083, 1084 (1977). One way that Granite State may meet its burden is by “showing that no evidence was presented in the record to sustain the order.” N.H.-Vt. Hosp. Serv. v. Whaland, 114 N.H. 92, 96, 315 A.2d 191, 194 (1974). After reviewing the record, we conclude that Granite State has met its burden.

In its initial order setting avoided cost rates, the PUC presumed that all parties had agreed to the use of the Newington proxy, and it proceeded to arrive at a rate using Newington data. Granite State responded to that order by filing a motion for rehearing in which it informed the PUC that it had never agreed to the Newington proxy, arguing that its avoided cost rate should be based on figures for its own supplier, New England Power Company (NEPCO).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Appeal of Briand
644 A.2d 47 (Supreme Court of New Hampshire, 1994)
Appeal of Campaign for Ratepayers Rights
577 A.2d 1230 (Supreme Court of New Hampshire, 1990)
Appeal of Vicon Recovery Systems, Inc.
547 A.2d 301 (Supreme Court of New Hampshire, 1988)
Appeal of Public Service Co.
539 A.2d 275 (Supreme Court of New Hampshire, 1988)
Appeal of Milford Water Works
489 A.2d 627 (Supreme Court of New Hampshire, 1985)
Appeal of Mountain Springs Water Co.
466 A.2d 915 (Supreme Court of New Hampshire, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
435 A.2d 119, 121 N.H. 787, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-granite-state-electric-co-nh-1981.