Appalachian Power co. v. State Corp. Comm'n

CourtSupreme Court of Virginia
DecidedNovember 1, 2012
Docket120394
StatusPublished

This text of Appalachian Power co. v. State Corp. Comm'n (Appalachian Power co. v. State Corp. Comm'n) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appalachian Power co. v. State Corp. Comm'n, (Va. 2012).

Opinion

Present: Kinser, C.J., Lemons, Millette, McClanahan and Powell, JJ., and Russell and Lacy, S.JJ.

APPALACHIAN POWER COMPANY

v. Record No. 120394 OPINION BY SENIOR JUSTICE ELIZABETH B. LACY STATE CORPORATION COMMISSION, November 1, 2012 ET AL.

FROM THE STATE CORPORATION COMMISSION

In this appeal, we consider whether the State Corporation

Commission properly construed and applied Code § 56-

585.1(A)(5)(e) to deny rate adjustment clause recovery for

certain costs incurred by Appalachian Power Company (“APCO” or

“the Company”).

Background

Prior to 1999, the State Corporation Commission (“the

Commission”) determined the rates electric utility companies

charged consumers pursuant to Chapter 10, Article 2 of Title 56,

Code §§ 56-234 through -245.1:1. Under that regulatory regime,

the rates could be changed following a review initiated by the

Commission or upon an application filed by an electric utility.

The Commission had broad discretion in selecting the methodology

for determining rates including the rate of return on equity

guided by the principle that the rates were to be just and

reasonable, allowing the utility a reasonable return and

imposing just rates on the consumer. Code § 56-235.2. In 1999, the General Assembly enacted the Virginia Electric

Utility Restructuring Act, former Code §§ 56-576 et seq., which

was designed to deregulate parts of the electric utility

industry and introduce competition among the providers of

electric generation. 1999 Acts ch. 411; Potomac Edison Co. v.

State Corp. Comm’n, 276 Va. 577, 580, 667 S.E.2d 772, 773

(2008). The legislation established a transition period, during

which the base rates of electric utilities were held constant or

“capped.” 1 However, utilities were allowed to file annual rate

applications to recover incremental costs incurred for system

reliability and for compliance with governmental environmental

laws or regulations. Code § 56-582(B)(vi); 2004 Acts ch. 827.

In 2007, the General Assembly ended its program of

deregulation and enacted Code § 56-585.1 which prescribed a new

regulation regime. 2007 Acts chs. 888, 933. The new

legislation reaffirmed the Commission’s authority to regulate

electric utility rates but prescribed certain procedures and

methodologies which the Commission must follow in establishing

such rates.

1 The initial transition period extended from January 1, 2001 to July 1, 2007, but was extended to December 31, 2008, “unless sooner terminated by the Commission pursuant to the provisions of subsection C; however, rates after the expiration or termination of capped rates shall equal capped rates until such rates are changed pursuant to other provisions of this title.” Code § 56-582(F); 2007 Acts chs. 888, 933. 2 Under the 2007 regulatory regime each utility was required

to undergo an initial review by the Commission in 2009. In this

proceeding, the Commission conducted a review of each company’s

2008 performance, set a rate of return and determined the rates

to be charged going forward “until such rates are adjusted.”

Code § 56-585.1(A). The methodology for adjusting rates in this

initial proceeding was set out in the statute. Id.

The legislation requires that, after the initial review

proceeding, the performance of electric utility companies is

reviewed every two years. In the biennial review, the

Commission considers the company’s rates, terms, and conditions

for the provision of generation, distribution and transmission

services for the preceding two years. Id. While the biennial

review has some characteristics of the Chapter 10 base rate

proceeding, the statute imposes significant limitations on the

Commission’s discretion in adjusting rates. Id.

If the utility earned more than 50 basis points below the

authorized fair combined rate of return, the Commission “shall

order increases to the utility’s rates necessary to provide the

opportunity to fully recover the costs of providing the

utility’s services and to earn not less than such fair combined

rate of return . . . .” Code § 56-585.1(A)(8)(i). If the

utility earned more than 50 basis points above the fair combined

rate of return established by the Commission, 60 percent of the

3 amount of the earnings above the fair rate of return must be

credited to customers’ bills and the electric utility may retain

the remaining 40 percent of the excess earnings. Code § 56-

585.1(A)(8)(ii). The Commission may not order a rate reduction

unless it finds that the electric utility earned more than 50

basis points above the fair rate of return in two consecutive

biennial reviews. Code § 56-585.1(A)(8)(iii).

The 2007 legislation also creates a new proceeding allowing

a utility to petition the Commission for approval of a rate

adjustment clause for the “timely and current” recovery from

customers for costs incurred in certain identified programs.

Code §§ 56-585.1(A)(4) through (6). As relevant here, the

Commission is directed to make rate adjustments allowing a

company to recover projected and actual costs of projects which

the Commission finds necessary to comply with state or federal

environmental laws or regulations. Code § 56-585.1(A)(5)(e).

Once granted, a rate adjustment clause is combined with the

company’s costs, revenues and investments in a biennial review

proceeding if there are adjustments to the rates until the

amounts of the adjustment clause are fully recovered. Code

§ 56-585.1(A)(3).

Proceedings

Pursuant to the regulatory review regime outlined above,

APCO filed its petition for its initial review in 2009. In that

4 proceeding APCO sought a rate increase of approximately $167

million based on the Company's performance in the 2008 test

year. The Commission’s order implementing APCO’s adjusted rates

included recovery for some, but not all the amounts sought by

APCO for compliance with various state and federal environmental

laws and regulations. These rates became effective in August of

2010. In re Appalachian Power Co., Case No. PUE-2009-00030,

(July 15, 2010). 2

In March of 2011, APCO filed a petition pursuant to Code

§ 56-585.1(A)(5)(e), seeking a rate adjustment clause to recover

$77 million, which it asserted represented the 2009 and 2010

actual costs incurred by the Company, but not recovered through

base rates, to comply with state and federal environmental

requirements. 3 The recovery APCO sought was incurred either

directly by APCO for environmental projects required for

compliance or through the capacity equalization charges it paid

to its affiliates which included costs incurred by the

2 A copy of this order may be found using the Commission’s docket search website, http://docket.scc.state.va.us/CyberDocs/Libraries/Default_Librar y/Common/frameviewdsp.asp?doc=103033&lib=CASEWEBP%5FLIB&mimetype =application%2Fpdf&rendition=native (last visited September 28, 2012). 3 APCO contemporaneously made its biennial filing pursuant to Code § 56-585.1(A)(3). That proceeding is not at issue in this appeal. 5 affiliates for compliance with state or federal environmental

laws or regulations. 4

The Commission published an order calling for notice and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christian v. STATE CORP. COM'N
718 S.E.2d 767 (Supreme Court of Virginia, 2011)
Piedmont Environmental v. Virginia Elec.
684 S.E.2d 805 (Supreme Court of Virginia, 2009)
Appalachian Voices v. STATE CORP. COM'N
675 S.E.2d 458 (Supreme Court of Virginia, 2009)
Potomac Edison Co. v. STATE CORP. COM'N
667 S.E.2d 772 (Supreme Court of Virginia, 2008)
BBF, INC. v. Alstom Power, Inc.
645 S.E.2d 467 (Supreme Court of Virginia, 2007)
Davenport v. Little-Bowser
611 S.E.2d 366 (Supreme Court of Virginia, 2005)
Beck v. Shelton
593 S.E.2d 195 (Supreme Court of Virginia, 2004)
SIGNAL Corp. v. Keane Federal Systems, Inc.
574 S.E.2d 253 (Supreme Court of Virginia, 2003)
Halifax Corp. v. First Union National Bank
546 S.E.2d 696 (Supreme Court of Virginia, 2001)
Browning-Ferris, Inc. v. Commonwealth
300 S.E.2d 603 (Supreme Court of Virginia, 1983)
Brown v. Lukhard
330 S.E.2d 84 (Supreme Court of Virginia, 1985)
Commonwealth v. Appalachian Electric Power Co.
68 S.E.2d 122 (Supreme Court of Virginia, 1951)
Mutual Savings & Loan Ass'n v. Commonwealth
186 S.E.2d 13 (Supreme Court of Virginia, 1972)
Smith v. Bryan
40 S.E. 652 (Supreme Court of Virginia, 1902)
Superior Steel Corp. v. Commonwealth
136 S.E. 666 (Supreme Court of Virginia, 1927)
Hunton v. Commonwealth
183 S.E. 873 (Supreme Court of Virginia, 1936)
Commonwealth v. Stringfellow
4 S.E.2d 357 (Supreme Court of Virginia, 1939)
Miller v. Commonwealth
21 S.E.2d 721 (Supreme Court of Virginia, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
Appalachian Power co. v. State Corp. Comm'n, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appalachian-power-co-v-state-corp-commn-va-2012.