A.O.D. Construction Co. v. Plymouth, No. Cv 92-0449974s (Jun. 5, 1995)

1995 Conn. Super. Ct. 6790
Connecticut Superior Court·Decided June 5, 1995·No. No. CV 92-0449974S·Unpublished

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION I.

The plaintiff, A.O.D. Construction, Inc. (hereinafter, "A.O.D.") is a Connecticut corporation and the defendant, Town of Plymouth (hereinafter, "Town") is a municipal corporation.

The plaintiff's claims are set forth in a two count amended complaint dated January 3, 1995.

The first count alleges that the plaintiff and defendant entered into a contract on or about January 25, 1990 for the construction of sanitary sewers in the Plymouth Farms area CT Page 6791 identified as Phase 7, Contract #4. The contract was to be completed within 120 consecutive calendar days of the written notice to proceed.

The plaintiff alleges that it completed the work and performed and completed additional work beyond the contract price at the direction of the defendant. Also that it was delayed in completing the project as a result of conduct of the defendant, differing site conditions, being required to work out of sequence, and insufficient or inaccurate plans and specifications.

The second count asserts that the extra work done by the plaintiff was at the request of the defendant, and provided benefits to the defendant.

The defendant filed an answer to the amended complaint dated January 17, 1995. The defendant's pleading contains an answer, special defense and a counterclaim; which contains four counts.

Count one alleges costs and expenses were incurred because of delays by the plaintiff.

Count two claims that the plaintiff failed to perform its work according to specifications and performed its work in a defective manner.

Count three alleges that the plaintiff caused damage to the storm water drainage system.

Count four claims that an offer of compromise was reached and that the plaintiff failed to perform thereunder.

In substantiation of its allegations, the plaintiff first offered the testimony of Thomas S. Juros. Mr. Juros is a Consulting Civil Engineer, licensed in the State of Connecticut. He was the consulting engineer for the defendant on the project in question. His employment is based on a contract between him and the Water Pollution Control Authority (WPCA) dated December 2, 1986. Mr. Juros had reviewed several other sewer projects.

Mr. Juros did the design work and prepared plans dated September 1989 for the entire project. He determined where the sewers were to be located, their size, depth and the slope CT Page 6792 of the pipes. In connection with his responsibilities, he prepared and drafted specifications for the construction of sanitary sewers in the Plymouth Farms area, Phase 7, Contract #4, Plymouth, Connecticut. (Plaintiff's Exhibit A).

The plans prepared by Thomas Juros reflected catch basins, utility and cable TV lines. The plans also indicated "call before you dig"; this was to notify the contractor to call to verify the location of utility and cable TV wires.

The plans and specifications were available for use by those who wished to submit bids for the project. There were 19 bids submitted. The bids ranged from $396,200.00 to $680,600.00, with the plaintiff being accepted as the lowest qualified bidder with a low bid of $396,200.00. Mr. Juros had placed a construction value on the project of $465,900.00.

The plaintiff's bid was prepared and submitted by Alberto DiChello, who has been president of AOD since 1988. He is an experienced contractor who has worked on projects at Bradley International Airport, projects in Hartford and Meriden and has done work for the MDC.

By letter dated January 17, 1990, (Exhibit C), the plaintiff was notified that it had been accepted as low bidder and the contract was signed on January 25, 1990.

Time of completion and liquidated damages are contained on page 7, Article 22 of Exhibit A. Said Article states:

ARTICLE 22. TIME OF COMPLETION AND LIQUIDATED DAMAGES: The bidder must agree to commence work on or before a date to be specified in a written "Notice to Proceed" of the Owner and to substantially complete the project within 120 consecutive calendar days thereafter and to fully complete the project within 30 consecutive calendar days thereafter. Bidder must agree also to pay as liquidated damages, the sum of $500.00 for each consecutive calendar day thereafter as hereinafter provided in the Contract and General Conditions. IT IS UNDERSTOOD, TIME IS OF THE ESSENCE.

Article 2(r), page GC-4 defines substantial completion as follows: CT Page 6793

(r) Whenever the phrases "substantial completion" or "substantially complete" are used in the Contract Documents, they shall mean the essential parts of the project are completely tested and accepted and being sufficiently completed so that the project or specified part can be used for the purposes for which it is intended. For a sanitary sewer project, this means that the sanitary sewer and all house laterals are completely constructed and all sections have passed the leakage test. This does not mean that the disturbed road areas have to be repaved at this time.

Mr. Juros also referred to Article 30 of Exhibit A, entitled "Changes in Plans and Specifications". Said Article states as follows:

ARTICLE 30. CHANGES IN PLANS AND SPECIFICATIONS:

Free access — add to your briefcase to read the full text and ask questions with AI

A.O.D. Construction Co. v. Plymouth, No. Cv 92-0449974s (Jun. 5, 1995), 1995 Conn. Super. Ct. 6790 (Colo. Ct. App. 1995).

1995 Conn. Super. Ct. 6790 (A.O.D. Construction Co. v. Plymouth, No. Cv 92-0449974s (Jun. 5, 1995)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Norwalk Door Closer Co. v. Eagle Lock & Screw Co.
220 A.2d 263 (Supreme Court of Connecticut, 1966)
St. Margaret's-McTernan School, Inc. v. Thompson
627 A.2d 449 (Connecticut Appellate Court, 1993)