Anthony McGill and AP McGill Enterprise, LLC v. GJG Productions, Inc.

Court of Appeals of Texas·Decided June 25, 2019·No. 01-17-00937-CV·Published

Opinion

Opinion issued June 25, 2018

In The

Court of Appeals

For The

First District of Texas

before the second trial setting, the trial court granted partial summary judgment for GJG on liability. The suit was then transferred to the 80th District Court for trial on damages only.

A jury awarded GJG actual damages of $16,073. The final judgment incorporated the partial summary judgment on liability and awarded GJG actual damages of $16,073 and trial and appellate attorneys’ fees.

McGill appeals only the trial court’s grant of partial summary judgment on liability. We affirm.

Background

GJG’s summary-judgment evidence, consisting of the affidavits of George Grega and Edwin Brown, reflects that GJG, a Houston-based production company that was owned and operated by Grega, provided audio, visual, and staging equipment for special events such as concerts and festivals. GJG and other companies in the industry often rented equipment from each other and hired each other as subcontractors. One of the other production companies GJG worked with over the years, including by subcontracting, was Starr Sound Systems, which was owned by Brown.

McGill planned to put on a Zydeco and Blues festival on the weekend of April 11–12, 2015 on his property in central Houston. A mutual acquaintance introduced Brown to McGill, and McGill hired Starr on February 20, 2015 to

provide audio, lighting, and staging for the festival. Starr then subcontracted the staging portion of the work to GJG. Starr received from McGill a 50% nonrefundable down payment, which is standard in the industry because once a stage is set up, the labor is done and the stage cannot be used elsewhere. GJG charged Starr a 50% nonrefundable down payment for the staging equipment.

GJG tried to set up the stage the Tuesday before the April 11–12 weekend festival to provide Starr and others sufficient time to complete their work after the stage was in place. Brown met Grega and the GJG crew at the property, and Brown then introduced Grega to McGill and explained to McGill that GJG would be handling the staging portion of the work. At the time, McGill was constructing a roof over the area where the stage would be, so he asked GJG to return the next morning. GJG returned the next day as requested and set up the stage. The 40’ by 40’ stage consisted of 50 stage decks (some that GJG owned and others that it had to rent) that measured 8’ by 4’, legs and clamps, stairs, and black stage-skirting.

After GJG’s crew had set up the stage, McGill postponed the festival until the following weekend because of rain. McGill notified Brown of the postponement and requested that GJG leave the stage in place until after the rescheduled event. Grega asked whether GJG could be paid for the extra week’s use of its equipment, especially because GJG had planned on using it for another job that week. Brown relayed the request to McGill, who became angry and

refused to pay for the extra time. Ultimately, GJG agreed to leave the stage on McGill’s property for the extra week.

The rain continued into the next week, and the following Thursday, April 16, Brown learned that McGill had cancelled the festival. That weekend, Grega called McGill to find out when he could retrieve the staging equipment. McGill told him the ground was still very wet and muddy, so GJG should wait until it dried out before trying to bring trucks in.

On Monday, Brown called McGill to ask about retrieving the equipment.

McGill became very angry and told Brown no one could get their equipment until his down payments were refunded. Brown explained to McGill that down payments “are always non-refundable because they compensate vendors for the use of their equipment (that cannot be used elsewhere) and labor that is needed to prepare for a job.” McGill hung up before Brown could finish his explanation. Grega tried calling McGill several times over the next week or so but made no progress.

On April 29, Grega called the Houston Police Department for help in getting his equipment. After speaking with an officer, Grega took a crew to McGill’s property and discovered the gate was open. They attempted to enter, but were met by McGill, who refused to let them get the staging equipment and ordered them to leave. Grega and the GJG crew parked across the street, where Grega once again

called police for help. This time, an officer was dispatched to the scene, and he spoke with McGill, who continued to refuse to let GJG get its the equipment. After speaking with the district attorney’s office, the officer said that police could not assist because it was a civil matter.

Before filing suit, GJG sent a demand letter to McGill, requesting the release of the staging equipment and the cost of replacing the stage decks it had rented. McGill received the letter but never responded. GJG then filed suit, alleging causes of action for conversion and civil theft under the Theft Liability Act (TLA). It also sought and obtained a temporary restraining order that prevented McGill from denying GJG access to its equipment. In support of its request for injunctive relief, GJG submitted an affidavit from Brown.

An hour before a temporary injunction hearing, McGill filed an answer and a petition in interpleader in which he asserted that he had contracted with Starr, not with GJG, and claimed that he “does not know to whom the stage equipment belongs.” Brown attended the hearing and reaffirmed the statement in his affidavit that GJG, not Starr, owned the equipment. McGill, through his counsel, agreed to let GJG onto his property to get its staging equipment, but only if GJG paid McGill a “storage fee” of $750. GJG reluctantly agreed to pay because it needed the equipment but maintained its position that McGill had been holding the equipment—not storing it—to get his down payment returned.

Thereafter, GJG served McGill with requests for admissions, but McGill did not timely respond. See TEX. R. CIV. P. 198.2(c) (“If a response is not timely served, the request is considered admitted without the necessity of a court order.”); id. R. 198.3 (“A matter admitted under this rule is conclusively established as to the party making the admission unless the court permits the party to withdraw or amend the admission.”). GJG moved for partial summary judgment on liability only for its conversion and TLA claims. GJG did not rely on McGill’s deemed admissions in support of its motion.

In his summary-judgment response, McGill submitted his own affidavit and emails that he had allegedly sent to Brown. With its reply to McGill’s response, GJG objected to McGill’s affidavit to the extent that it contradicted his deemed admissions. A party may not controvert a deemed admission. See Marshall v. Vise, 767 S.W.2d 699, 700 (Tex. 1989). But GJG also explained that, irrespective of the deemed admissions, McGill’s affidavit did not raise a material fact issue.

A week before the case was set for trial, GJG’s summary-judgment motion was heard. After the hearing, McGill filed a motion to strike his deemed admissions, claiming that he failed to timely answer because of confusion between his substituting attorney and his withdrawing attorney. He also answered the requests for admissions—over fourteen months late.

Grega died before trial, and the parties agreed to a trial continuance. The trial court then granted GJG’s motion for partial summary judgment and sustained GJG’s objections to McGill’s affidavit.

Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Anthony McGill and AP McGill Enterprise, LLC v. GJG Productions, Inc., (Tex. Ct. App. 2019).

Anthony McGill and AP McGill Enterprise, LLC v. GJG Productions, Inc. (Anthony McGill and AP McGill Enterprise, LLC v. GJG Productions, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Goodyear Tire and Rubber Co. v. Mayes
236 S.W.3d 754 (Texas Supreme Court, 2007)
Medeles v. Nunez
923 S.W.2d 659 (Court of Appeals of Texas, 1996)
Winkle Chevy-Olds-Pontiac, Inc. v. Condon
830 S.W.2d 740 (Court of Appeals of Texas, 1992)
Nixon v. Mr. Property Management Co.
690 S.W.2d 546 (Texas Supreme Court, 1985)
Broesche v. Jacobson
218 S.W.3d 267 (Court of Appeals of Texas, 2007)
MMP, Ltd. v. Jones
710 S.W.2d 59 (Texas Supreme Court, 1986)
Marshall v. Vise
767 S.W.2d 699 (Texas Supreme Court, 1989)
Barker CATV Construction, Inc. v. Ampro, Inc.
989 S.W.2d 789 (Court of Appeals of Texas, 1999)
Castillo Information Technology Services, LLC v. Dyonyx, L.P.
554 S.W.3d 41 (Court of Appeals of Texas, 2017)
Weeks Marine, Inc. v. Garza
371 S.W.3d 157 (Texas Supreme Court, 2012)
Stroud Production, L.L.C. v. Hosford
405 S.W.3d 794 (Court of Appeals of Texas, 2013)
Ginn v. NCI Building Systems, Inc.
472 S.W.3d 802 (Court of Appeals of Texas, 2015)