Anne Arundel County v. Nes

881 A.2d 1161, 163 Md. App. 515
CourtCourt of Special Appeals of Maryland
DecidedSeptember 1, 2005
Docket1687, September Term, 2004
StatusPublished
Cited by1 cases

This text of 881 A.2d 1161 (Anne Arundel County v. Nes) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anne Arundel County v. Nes, 881 A.2d 1161, 163 Md. App. 515 (Md. Ct. App. 2005).

Opinion

DAVIS, Judge.

Appellees, Jane P. Nes and Tanyard Springs Limited Partnership, sought to subdivide a large tract of land in Anne Arundel County. They applied to the County’s Director of Planning and Code Enforcement (PACE) for a waiver of school capacity requirements imposed by County ordinances. PACE denied the waiver request. Appellees then appealed the denial to the County’s Board of Appeals, which affirmed PACE’s decision. Appellees sought judicial review in the Circuit Court for Anne Arundel County. The circuit court granted appellees’ requested relief, remanding the matter to the Board of Appeals for further proceedings on the threshold issue of whether school capacity was in fact inadequate.

Appellant, Anne Arundel County, appealed the circuit court’s judgment, presenting three questions for our review:

I. Was the Board of Appeals’ decision that Nes did not meet the criteria for a waiver of school adequacy requirements under Article 26 § 2-411 of the Anne Arundel County Code supported by substantial evidence, and did the Board correctly conclude as a matter of law that the issue of whether schools were adequate under former Article 26 § 2-416 of the Anne Arundel County Code was not properly before the Board?
II. Did the circuit court correctly remand for the Board of Appeals to decide the issue of whether schools are adequate, in light of the intervening change of law that has resulted in school adequacy now being determined legislatively and not administratively, and that has made moot any review of that issue by the Board of Appeals?
III. Assuming, arguendo, that the Board of Appeals should now decide the issue of whether schools are adequate, did the circuit court correctly rule that it may *518 consider the 1998 APF Agreement on the question of whether schools are adequate?

We conclude that the adequacy of the schools’ capacity was not an issue properly before the Board of Appeals for decision. Therefore, we shall reverse the judgment of the circuit court, and, in effect, affirm the Board of Appeals’ decision that the issue of school adequacy was not properly before it and that appellees had abandoned their quest for a waiver.

BACKGROUND

Appellees own a 277-acre tract of land in Anne Arundel County, which they seek to subdivide for industrial, commercial, and residential uses. Before subdivision can occur, the County’s ordinances require that there be in place adequate public facilities (e.g., roads, water supply) to serve the new subdivision. This appeal concerns the requirement for adequate capacity at nearby schools as a precondition to the County’s approval of residential subdivisions. See Article 26 § 2-416 of the Anne Arundel County Code. 1

*519 In routine subdivision cases, the County’s ordinances provide a seamless process for subdivision applications and agency review for adequate public facilities. Appellees pursued an alternative, two-step subdivision process, not expressly spelled out in the applicable local ordinances, but utilized in Anne Arundel County for complex subdivisions.

The first step in this alternative procedure begins with a landowner’s application for infrastructure plan approval. Appellees explain the rationale for the process in their brief:

Typically, an infrastructure plat would be accompanied by a thoroughly negotiated agreement [between the landowner and the County] addressing all of the adequate public facilities issues.... Use of this process facilitated the longer-range planning and development process necessary for larger developments, allowing developers of large projects to have the assurance that the substantial up-front capital investment in major infrastructure, including public facilities and project engineering, could be recovered through the unimpeded completion of the project.
An infrastructure plat ... typically showed large reserve or bulk parcels which could later be re-subdivided into buildable lots, and allowed County planners to evaluate and approve the hard engineering aspects of a development, including the main utilities, the main stem roads, and major facilities for water, sewer, roads, and schools.

In deposition testimony taken in a judicial review action related to this case, counsel who had represented appellees also explained that, although this infrastructure plat phase was concerned with “iron[ing] out those details so as to make subsequent ultimate development of the project easier,” a developer still “had to have a pretty good idea of what [the *520 developer] was planning for, because your infrastructure improvements had to accommodate it.” Thus, in some cases, the issue of adequate school capacity has been decided in the infrastructure plat phase, as opposed to when further subdivisions are made to create individual, “buildable” lots.

In 1998, appellees were negotiating for an adequate public facilities (APF) agreement with the County so that it could obtain approval of its infrastructure plat to subdivide the tract at issue here. PACE agreed to negotiate all public facilities issues except the adequacy of schools. As to schools, the appellees were instructed to apply for a waiver, under Article 26 § 2-411, 2 from the adequacy of schools requirement then *521 codified at Article 26 § 2-416. 3

Appellees submitted a waiver request to PACE on June 27, 1998. In the request, appellee Jane Nes (individually, apparently, and pro sé) conceded the inadequacy of nearby school capacity, writing, “Solley Elementary School, which borders Tanyard Springs, presently does not have sufficient capacity for the ... subdivision, whose initial plan requires space for 555 [townhouse] units.” She then explained the reasons she thought a waiver should be granted.

PACE denied the waiver on July 20, 1998. The decision issued by PACE was illogical in that it simply recited that the County’s Board of Education advised PACE that appellees’ proposed development would cause the local elementary and middle school to exceed their capacity, and, for that reason — a reason which would require a denial in every case — the waiver was denied. On that same date, appellees noted their appeal to the County’s Board of Appeals.

While appellees’ appeal was pending before the Board of Appeals, they and the County were finalizing the terms of their APF agreement for the infrastructure plan, regarding public facilities other than schools. The parties reached a compromise regarding other public facilities, and executed the APF agreement shortly before the Board of Appeals hearing, but that fact was not disclosed to the Board of Appeals because of a “secrecy clause” in the agreement. The clause stated:

F.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cremins v. COMMISSIONERS OF WASHINGTON COUNTY
883 A.2d 966 (Court of Special Appeals of Maryland, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
881 A.2d 1161, 163 Md. App. 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anne-arundel-county-v-nes-mdctspecapp-2005.