Anna Thomas v. Travelers Casualty and Surety Company of America

636 F. App'x 992
CourtCourt of Appeals for the Eleventh Circuit
DecidedJanuary 13, 2016
Docket14-15408
StatusUnpublished

This text of 636 F. App'x 992 (Anna Thomas v. Travelers Casualty and Surety Company of America) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anna Thomas v. Travelers Casualty and Surety Company of America, 636 F. App'x 992 (11th Cir. 2016).

Opinion

PER CURIAM:

Anna Thomas, proceeding pro se and as substitute appellant for Alvin Thomas (“Thomas”) 1 , appeals the dismissal with prejudice of Thomas’s civil complaint alleging breach of contract and seeking specific performance against Travelers Casualty and Surety Company of America (“Travelers”). This case concerns Thomas’s work as a subcontractor on a federal project, for which he was not fully paid by the contractor. He obtained a judgment against the contractor in state court and, unable to collect on the judgment, filed a claim with Travelers, which had issued bonds at the request of the contractor to ensure payment of those who furnished materials and labor for the project.

Travelers denied the claim on the basis that it was untimely under the Miller Act, 40 U.S.C. §§ 3131-3134. Thomas then filed suit in federal court against Travelers. The district court granted summary *994 judgment to Travelers, concluding that Thomas’s claim was time barred.

On appeal, Thomas argues that the district court erred in granting summary-judgment to Travelers because the Full Faith and Credit Clause imposed a duty on the district court to give effect to the state-court judgment. Thomas also argues that the principals of res judicata and collateral estoppel preclude Travelers from raising a statute-of-limitations defense because a judgment against a principal (the contractor) establishes a surety’s (Travelers’s) liability as long as the surety had notice of the action against its principal. Thomas maintains that Travelers had notice and an opportunity to contest the contractor’s liability in the state-court action. After careful review, we affirm.

I.

Thomas was hired by Thorington Electrical and Construction Company (“TECC”) as a subcontractor to perform drainage work for a project at Maxwell Air Force Base in Montgomery, Alabama. Thomas completed work on the project in March 2006. 2 For this work, TECC paid Thomas $90,696.47, about half of what he was owed. Thomas brought suit against TECC in Alabama state court in January 2008 to collect the remaining amount due. In October 2008, the state court entered judgment in favor of Thomas and ordered TECC to pay Thomas the remaining $99,172.77 owed under the subcontract.

In September 2008, Thomas notified Travelers that he intended to file a claim on payment bonds Travelers had issued for the construction projects. In accordance with federal law, TECC had engaged Travelers to execute a series of performance and payment bonds in favor of the United States for the project at Maxwell Air Force Base.

Thomas submitted a claim form, along with the October 2008 state judgment, to Travelers in February 2009. After some additional communications between Travelers and Thomas, Travelers notified Thomas in August 2009 that it was denying his claim primarily because it was not timely filed under the terms of the Miller Act. Believing that his claim was wrongfully denied, Thomas filed suit in federal court against Travelers in December 2012, seeking to recover the amount of the state-court judgment he obtained against TECC.

The district court granted summary judgment to Travelers, concluding that Thomas’s action was time-barred under the Miller Act because he had not brought the action within one year of the date on which he last performed labor under the contract. Consequently, the court dismissed Thomas’s complaint with prejudice as time barred. After unsuccessfully moving for reconsideration of the judgment, Thomas now brings this appeal.

II.

We review a district court’s grant of summary judgment de novo, viewing the evidence and drawing all reasonable inference in favor of the non-moving party. Burger King Corp. v. E-Z Eating, 41 Corp., 572 F.3d 1306, 1313 (11th Cir.2009). Under Federal Rule of Civil Procedure 56(a), summary judgment should be granted “if the movant shows that there is no *995 genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56.

III.

Here, the contract the parties entered into was for construction of a federal project and therefore properly governed by the Miller Act. 3 The Miller Act requires a contractor to furnish performance and payment bonds to the United States “[b]e-fore any contract of more than $100,000 is awarded for the construction, alteration, or repair of any public building or public work of the Federal Government.” 40 U.S.C. § 3131(b). The purpose of the Miller Act is to ensure that those who furnish labor and materials for public construction projects will be paid. Graybar Elec. Co. v. John A. Volpe Constr. Co., 387 F.2d 55, 58 (5th Cir.1967). 4 Because the Miller Act is “highly remedial in nature,” it is to be liberally construed “to effectuate the congressional intent to protect those whose labor and materials go into public projects.” Id. (quotation omitted).

The act provides that every person who has furnished labor or materials under a contract for which a payment bond under 40 U.S.C. § 3131(b)(2) was issued, but who has not been paid within ninety days of the last day of performance, “may bring a civil action on the payment bond for the amount unpaid at the time the civil action is brought and may prosecute the action to final execution and judgment for the amount due.” 40 U.S.C. § 3133(b)(1). However, any such action “must be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the action.” 40 U.S.C. § 3133(b)(4).

The last date that Thomas worked for or provided materials for the project was in March 2006. Thomas did not file suit against Travelers until December 12, 2012, more than six years after he last performed under the contract. Even assuming Thomas could rely on the date he filed suit against TECC in state court in January 2008, the action still was not timely brought within the one-year limitation period. As a result, the district court correctly concluded that Thomas’s suit against Travelers was not timely filed under the Miller Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Timson v. Sampson
518 F.3d 870 (Eleventh Circuit, 2008)
Burger King Corp. v. E-Z Eating, 41 Corp.
572 F.3d 1306 (Eleventh Circuit, 2009)
Baker v. General Motors Corp.
522 U.S. 222 (Supreme Court, 1998)
Wallace G. Frederick v. United States
386 F.2d 481 (Fifth Circuit, 1967)
Larry Bonner v. City of Prichard, Alabama
661 F.2d 1206 (Eleventh Circuit, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
636 F. App'x 992, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anna-thomas-v-travelers-casualty-and-surety-company-of-america-ca11-2016.