Androscoggin Valley Regional Refuse Disposal District v. R.H. White Construction Co., Inc.

2017 DNH 093
CourtDistrict Court, D. New Hampshire
DecidedMay 8, 2017
Docket15-cv-434-LM
StatusPublished
Cited by1 cases

This text of 2017 DNH 093 (Androscoggin Valley Regional Refuse Disposal District v. R.H. White Construction Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Androscoggin Valley Regional Refuse Disposal District v. R.H. White Construction Co., Inc., 2017 DNH 093 (D.N.H. 2017).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Androscoggin Valley Regional Refuse Disposal District

v.

R.H. White Construction Co., Inc.

Civil No. 15-cv-434-LM Opinion No. 2017 DNH 093

Sanborn, Head & Associates, Inc. et al.

O R D E R

Androscoggin Valley Regional Refuse Disposal District (the

“District”) brings suit against R.H. White Construction Co.,

Inc. (“R.H. White”) alleging claims arising out of an agreement

between the parties that provided for R.H. White to design and

build a landfill gas processing facility. R.H. White filed a

third-party complaint (doc. no. 4) against nine entities that

were also involved in the building and design of the facility,

including Sanborn, Head & Associates, Inc. (“SHA”). SHA

answered the third-party complaint and asserted three third-

party counterclaims against R.H. White. See doc. no. 42. R.H. White moves to dismiss three claims asserted by the

District, arguing that they fail to adequately state a claim for

relief. See doc. no. 91. R.H. White also moves to dismiss two

of the third-party counterclaims asserted by SHA on the same

ground. See doc. no. 92.

Standard of Review

Under Rule 12(b)(6), the court must accept the factual

allegations in the complaint as true, construe reasonable

inferences in the plaintiff’s favor, and “determine whether the

factual allegations in the plaintiff’s complaint set forth a

plausible claim upon which relief may be granted.” Foley v.

Wells Fargo Bank, N.A., 772 F.3d 63, 71 (1st Cir. 2014)

(citation omitted). A claim is facially plausible “when the

plaintiff pleads factual content that allows the court to draw

the reasonable inference that the defendant is liable for the

misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678

(2009).

Background1

The District owns and operates the Mount Carberry Landfill

in Success, New Hampshire. On September 12, 2011, the District

1 These facts are drawn from the allegations in the District’s amended complaint (doc. no. 77) and R.H. White’s third-party complaint (doc. no. 4).

2 and R.H. White entered into an agreement (the “Agreement”) in

which R.H. White agreed to design and build a landfill gas

compression and treatment facility (the “LFG Facility”) at the

Mount Carberry Landfill. The purpose of the LFG Facility was to

treat and transport the landfill gas through a pipeline to the

Gorham Paper and Tissue Mill, which would purchase the gas from

the District.

In order to induce the District to enter into the

Agreement, R.H. White made several representations in its

response to the District’s Request for Proposal (“RFP”) and in

the Agreement itself. Those representations included statements

about R.H. White’s expertise and ability to build and design the

LFG Facility in accordance with the District’s needs.

In 2012, R.H. White contracted with several companies to

provide design and/or engineering services in connection with

the construction of the LFG Facility. On July 5, 2012, R.H.

White entered into an agreement with SHA (the “subcontract”),

pursuant to which SHA was responsible for much of the overall

engineering and design of the LFG Facility.

Under the terms of the Agreement and after several agreed-

upon extensions, R.H. White was obligated to substantially

complete its work on or before October 22, 2012. On November 5,

3 2012, R.H. White commenced startup of the LFG Facility, and the

first day of landfill gas sales occurred on November 7, 2012.

The LFG Facility ran intermittently from November 7, 2012

through December 20, 2012. On December 21, 2012, the facility

was shut down entirely because it was not working properly.

From December 2012 through March 2014, the LFG Facility

experienced frequent unexpected shutdowns caused by multiple

failing components, including the regeneration cooler, the air

heat exchanger on the compressor skid, the glycol cooler, the

compressor motor, and the odorant system.

R.H. White asked SHA to perform an analysis of the LFG

Facility to identify the cause of the problems. SHA determined

that at least part of the problem arose when some of the

landfill gas being sent through a part of the system, the

dessicant dryer, was recycled back through the system (the

“regeneration gas”).

In early 2014, based on SHA’s recommendation and design,

R.H. White installed a “side flare” to divert and “burn off” the

regeneration gas before it was sent through the LFG Facility.

The purpose of the side flare was to determine if the

regeneration gas was causing the clogging and corrosion problems

in the various components of the system.

4 In March 2014, the side flare began operating, and the LFG

Facility stayed “on line” consistently thereafter. R.H. White

asked the District to deem the side flare a “permanent solution”

to the problems the facility had experienced and an acceptable

change to the original design. R.H. White also asked the

District to pay it the $496,000 retainage fee it had held back

pending completion of the project. The District did not deem

the side flare an acceptable permanent solution, because it

reduced the amount of landfill gas that was supposed to be

treated and eventually sold, and did not pay R.H. White the

retainage fee.

While the District and R.H. White attempted to resolve the

dispute, the District noticed staining of soil, metal roofs, and

equipment in the area immediately beneath and surrounding the

side flare. The District tested the stained soil, which showed

elevated levels of certain heavy metals, including arsenic,

chromium, lead, and nickel. The contamination levels are

highest at the point of the side flare, which is consistent with

the side flare being the cause of the contamination.

The District informed the New Hampshire Department of

Environmental Services (“DES”) of its soil testing findings.

Based on initial discussions with DES, the District expects that

it will need to remediate the contaminated topsoil around the

5 side flare and that it will likely need to discontinue the side

flare or redesign it to preclude further contamination. The

District’s engineers have begun trying to redesign the side

flare, but even if successful, some landfill gas will still be

diverted from the pipeline, leaving the District with less gas

to sell than what was contemplated under the Agreement.

Under the original terms of the Agreement, the District was

obligated to pay R.H. White $2,108,130, plus an additional

$160,000 for ledge removal. After several “change orders,” the

total price under the Agreement rose to $3,275,508.40.

Discussion

R.H. White moves to dismiss three of the District’s claims

(doc. no. 91) and two of SHA’s third-party counterclaims (doc.

no. 92). The court addresses these motions separately below.

I. Motion to Dismiss District’s Claims

The District asserts nine claims against R.H. White in its

amended complaint: (1) Breach of Contract (Count I); (2) Breach

of the Implied Covenant of Good Faith and Fair Dealing (Count

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrew Hall v. Lorettann and Nikolas Gascard
2017 DNH 110 (D. New Hampshire, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 DNH 093, Counsel Stack Legal Research, https://law.counselstack.com/opinion/androscoggin-valley-regional-refuse-disposal-district-v-rh-white-nhd-2017.