Andrews Distributing Co. v. Oak Square at Gatlinburg, Inc.

757 S.W.2d 663
CourtTennessee Supreme Court
DecidedOctober 3, 1988
StatusPublished
Cited by6 cases

This text of 757 S.W.2d 663 (Andrews Distributing Co. v. Oak Square at Gatlinburg, Inc.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andrews Distributing Co. v. Oak Square at Gatlinburg, Inc., 757 S.W.2d 663 (Tenn. 1988).

Opinions

OPINION

FONES, Justice.

This is an action by a materialman for enforcement of a materialman’s lien, or in the alternative for recovery under the general contractor’s labor and material payment bond. The trial court dismissed the action for failure to give timely written notice of lien and for failure to give timely notice under the terms of the bond. The Court of Appeals affirmed, and this Court granted plaintiff’s application for permission to appeal.

In October, 1984, plaintiff, Andrews Distributing Company, received a purchase order for HVAC [heating and air conditioning] units from Mike White d/b/a Kalthoff Heating and Cooling. This purchase order specified that the HVAC units were to be used in the Oak Square Condominium project in Gatlinburg, Tennessee, of which Kalthoff was the heating and air conditioning subcontractor. In addition, the purchase order directed that the HVAC units be delivered to Kalthoff’s warehouse, and not to the job site. On 21 December 1984, the units were delivered to Kalthoff’s Knoxville warehouse as directed. On 1 March 1985, the HVAC units were delivered by Kalthoff to the Oak Square job site.

Plaintiff billed Kalthoff on 27 December 1984, and on 3 January 1985, for the HVAC units but plaintiff did not receive payment for the units from Kalthoff. Therefore, on 2 April 1985, plaintiff filed a notice of ma-terialman’s lien in the Sevier County Register’s Office. On 9 April 1985, Burlison Construction Company, Inc. [Burlison], the general contractor for the Oak Square project, filed a bond to remove plaintiff’s lien pursuant to T.C.A. § 66-11-142 with Fidelity and Deposit Company of Maryland [Fidelity] as the surety. The owner of the Oak Square project, Oak Square at Gatlin-burg, Inc., joined as a principal on that bond on 15 April 1985. Kalthoff then filed a petition for relief under Chapter 7 of the Bankruptcy Code, 11 U.S.C. §§ 701 et seq. On 28 June 1985, plaintiff filed this action for enforcement of its materialman’s lien, or in the alternative, for recovery under Burlison’s labor and material bond for which Fidelity is also the surety. It is undisputed that Burlison has fully paid Kalthoff for the Oak Square work, including the HVAC units at issue here.

The chancellor held that plaintiff was not entitled to recover under either theory because of its failure to give proper notice and dismissed plaintiff’s action. On plaintiff’s action to enforce its materialman’s lien, the chancellor noted that pursuant to T.C.A. § 66 — 11—115(b) written notice of lien must be given to the property owner within ninety days of the expiration of the contract. The chancellor noted that plaintiff contracted only to deliver the units to Kal-thoff’s warehouse and held that once the units were so delivered the contract expired for the purposes of T.C.A. § 66 — 11—115(b). As the HVAC units were delivered on 21 December 1984, and plaintiff’s notice of [665]*665lien was filed on 2 April 1985, 102 days later, the chancellor held that proper notice to the owner was not given and a lien was not created. The chancellor also held that plaintiff was not entitled to recover under the labor and material payment bond because of its failure to give notice as required by the terms of the bond within ninety days of last supplying material to the project. The Court of Appeals affirmed and this Court granted plaintiff's application for permission to appeal.

I.

In this case, plaintiff is a material-man who seeks to assert a materialman’s lien pursuant to T.C.A. § 66-ll-115(a). See Dealer’s Supply Co. v. First Christian Church, 38 Tenn.App. 568, 276 S.W.2d 769 (1954); T.C.A. § 66-11-101(10). As a materialman, plaintiff may claim a statutory lien for materials which are incorporated in the improvement on the real property. T.C.A. § 66-11-101(5) and § 66-ll-115(a). However, to create this lien plaintiff must fully comply with all of the requirements of the statutory lien scheme. See General Electric Supply Co. v. Arlen Realty & Development Corp., 546 S.W.2d 210, 212 (Tenn.1977); Hamilton National Bank v. Long, 189 Tenn. 562, 568, 226 S.W.2d 293, 296 (1949); Thompson v. Baxter, 92 Tenn. 305, 306-07, 21 S.W. 668, 669 (1893).

The statutory provision relevant to this issue of notice is T.C.A. § 66-ll-115(b). That section states:

(b) Within ninety (90) days after the demolition and/or building or improvement is completed, or the contract of such laborer, mechanic, furnisher, or other person shall expire, or he be discharged, he shall notify, in writing, the owner of the property on which the building is being erected or improvement is being made, or his agent or attorney, if he reside out of the county, that said lien is claimed.

As it is undisputed that plaintiff did not give notice after the completion of the building, the issue here is whether plaintiff gave written notice to the property owner within ninety days of the expiration of its contract. Since this Court has previously held that a materialman’s contract does not “expire” until the last of the material has been “furnished,” the actual issue is whether plaintiff gave notice to the property owner within ninety days of the date the last of the material was furnished. Bird Bros. v. Southern Sur. Co., 139 Tenn. 11, 15, 200 S.W. 978 (1917).

Delivery to the actual job site is clearly the most unequivocal evidence of “furnishing” materials for the purpose of material-men’s liens. See Annotation, “Delivery of Material to Building Site as Sustaining Mechanic’s Lien — Modern Cases,” 32 A.L.R. 4th 1130, 1138 n. 8 (1984). The Tennessee statutes on materialmen’s liens place great emphasis on delivery to the job site. Section 66-11-101(5) defines the phrase “furnish materials” in pertinent part to mean “supply materials which are incorporated in the improvement.” That section also states that “delivery of materials to the site of the improvement [is] prima facie evidence of incorporation of such materials in the improvement.” T.C.A. § 66-11-101(5). A “materialman” is defined by § 66-11-101(10) as “any person who, under contract, furnishes material ... on the site of the improvement or for direct delivery to the site of the improvement.” In New Memphis Gas Light Co. Cases, 105 Tenn. 268, 60 S.W.2d 206 (1900), this Court said, “...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lanier v. Lanier
612 S.E.2d 456 (Court of Appeals of South Carolina, 2005)
Vulcan Materials Co. v. Gamble Construction Co.
56 S.W.3d 571 (Court of Appeals of Tennessee, 2001)
Ronnie Bradfield v. City of Memphis
Court of Appeals of Tennessee, 1999
Spence v. Allstate Insurance Co.
883 S.W.2d 586 (Tennessee Supreme Court, 1994)
Andrews Distributing Co. v. Oak Square at Gatlinburg, Inc.
757 S.W.2d 663 (Tennessee Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
757 S.W.2d 663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andrews-distributing-co-v-oak-square-at-gatlinburg-inc-tenn-1988.