Andrew Lohr Bottling Co. v. Ferguson

122 Ill. App. 270, 1905 Ill. App. LEXIS 498
Appellate Court of Illinois·Decided September 8, 1905·Published·Cited by 3 cases

Opinion

Mr. Presiding Justice Higbee

delivered the opinion of the court.

This was an action in assumpsit on a written contract for the erection of a factory building in the city of Cairo Illinois, entered into by appellant with appellee.

The first count of the declaration filed by appellee, declared on the contract and there were also a' count upon a quantum meruit and a common indebitatus count. A plea for the general issue was filed by appellant and there was a stipulation signed by the attorneys for the respective parties, providing that all objections to the declaration were waived and all competent and proper evidence to prove appellee’s case might be introduced under the declaration, and also that appellant, under the plea of the general issue, might introduce any proper and competent evidence, the same as though special pleas had been filed.

The contract price to be paid appellee for the construction of the building was $19,385, which was to be paid in six installments, of different amounts.

In the special count of his declaration, appellee admits that the first four installments and one-half of the fifth had been paid. He seeks to recover the balance of. the fifth, amounting to $2,000, and all of the last payment. He also charges for certain extras added and gives credit for certain things omitted and some material furnished by appellant and claims a balance to be due him of $5,120.41 and interest.

Appellant complains that the suit was prematurely brought because a certificate that the building was free from mechanics’ liens and other claims, was not furnished ten days prior to its commencement, .such certificate being in fact furnished only two days before; that the verdict was manifestly against the weight of the evidence, which appellant claims showed the building was not completed in substantial compliance with the contract; and that there was error in the giving of certain instructions for appellee and in the modification and refusal of others offered by appellant. The provision in the contract concerning the certificate of freedom from liens and claims, is as follows: “ The balance of $3,877 to be paid within ten days after the building is completed and finished, according to the plans and specifications, in a good, true and workmanlike manner, and to the satisfaction of the said architects, and after a satisfactory certificate has been obtained to the effect that the estate or building upon „or for which the work is done, is at present time, when payment is made, free from all mechanics’ liens and other claims chargeable upon said building or estate incurred by the party of the first part.” "While it is true that the contract provides that the payment is not to be made until ten days after the building is completed and finished, yet it is not clear from the reading of the contract, that the ten days’ limit was also to apply to the furnishing of the certificate, but it might reasonably be inferred that the certificate of freedom from liens and claims could be furnished appellant at any time after the completion of the building and prior to demand for payment. The building appears to have been completed about April 28, 1902, while this suit was not commenced until April 30,. 1903, so there is no question that a sufficient time had not elapsed between the completion of the building and the bringing of the suit, but the certificate of freedom from liens was not furnished by the architects until two days prior to the bringing of the suit. However, even if appellant’s contention that by the terras of the contract the certificate was to be furnished ten days before the last installment was due be conceded, such condition was waived by appellant. On several occasions before suit was brought, Mr. Becker, president of the appellant company, refused to pay appellee the balance due on the contract, and based his refusal on appellee’s alleged failure to construct the building in accordance with the contract and not on his failure to obtain such certificate and at the time the certificate was delivered to Mr. Becker two days before suit was brought, he announced that he would not pay the bill. Such facts were sufficient to constitute a waiver of the condition. Supreme Lodge v. Meister, 204 Ill. 527; Downey v. O’Donnell, 92 Ill. 559; Williamsburg City Fire Ins. Co. v. Cary. 83 Ill. 453.

Appellant contends that under appellee’s declaration, he should not be permitted to show a waiver of the condition in regard to the certificate. The stipulation in regard to the pleadings above set forth, was, however, sufficiently broad to permit appellee to introduce evidence of and rely upon the waiver.

Free access — add to your briefcase to read the full text and ask questions with AI

Andrew Lohr Bottling Co. v. Ferguson, 122 Ill. App. 270, 1905 Ill. App. LEXIS 498 (Ill. Ct. App. 1905).

122 Ill. App. 270 (Andrew Lohr Bottling Co. v. Ferguson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Edward Edinger Co. v. Willis
260 Ill. App. 106 (Appellate Court of Illinois, 1931)
Hansell-Elcock Co. v. Frankfort Marine Accident & Plate Glass Insurance
177 Ill. App. 500 (Appellate Court of Illinois, 1913)
Masek v. Chmelik
169 Ill. App. 589 (Appellate Court of Illinois, 1912)