Anderson v. State

103 Misc. 388
CourtNew York Court of Claims
DecidedMay 15, 1918
DocketNo. 2653-A
StatusPublished
Cited by1 cases

This text of 103 Misc. 388 (Anderson v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson v. State, 103 Misc. 388 (N.Y. Super. Ct. 1918).

Opinion

Cunningham, J.

On June 13,1912, the claimant and the state of New York entered into a contract for the improvement of the highway, known as the Boonville Town Line-McKeever State Highway, Division No. 3, Highway No. 5248, in the counties of Oneida and Herkimer, according to the plans and specifications made a part of the contract.

[390]*390The highway to be improved was about eighteen miles in length, and the lump sum price was $254,-193.73. There were agreed unit prices, also, for the various items of work and material involved, as is usual in such cases.

The contract was made under the provisions of chapter 30 of the Laws of 1909, and chapter 646 of the Laws of 1911, and the acts amendatory thereof and' supplemental thereto. The claimant completed the contract and performed all the work to the satisfaction of the state, and was paid the sum of $248,414.60.

The contract, plans and specifications provided for the construction of a two-course macadam highway, each course to be built of crushed stone; known as “ run of the crusher.”

The claimant began work in July, 1912, and continued until about September 1, 1912, when he began the laying of stone pursuant to the contract. Thereupon he was halted by the state engineers in charge of the work, and was ordered and directed not to use ‘ Í run of the crusher ’ ’ stone merely, but to grade it in separate bins, or pockets, according to size, and to place in the bottom course three-inch stone, to be filled with dustless screenings and rolled. The provision of the specifications for said course reads • “A layer of broken stone consisting of the run of the crusher from dust approximately three inch stone.” He also was ordered to construct the top course of two-inch stone and one-inch stone, only. The specification for said course reads: The run of the crusher from screenings to and including two inch stone.” He further was ordered to place upon the top of the two courses so constructed a coat of bituminous asphalt, upon which should be placed one-inch stone, and upon top of the one-inch stone should be placed a second coat of asphalt, upon which should be spread a wearing [391]*391course of 'dustless screenings. All these directions of the engineer were given pursuant to instructions received by the latter from the then state commission of highways.

The claimant called the attention of the engineer to the provisions of the specifications, and protested against these directions and against complying with them. The engineer replied, in substance: “ This is the way we have got to have it; this is the way it must be done,” and refused to permit the work to be done, except pursuant to these directions, whereupon the claimant complied, and completed the work as directed.

This resulted in a very great increase in expense to the claimant. It compelled him to furnish 40,906 cubic yards additional of stone, of the value of one dollar and seventy cents per cubic yard, which was the unit price fixed by the contract for crushed stone.

During the course of the work, the claimant performed various other services, and furnished certain other materials, incident to the construction of the road, not provided for, or contemplated, by the contract, plans or specifications. It does not appear that they were performed or furnished under any contention by the state that the contract, plans or specifications required them, or that the claimant was compelled by any representative of the state to perform or furnish them, over his opposition or protest. Bather, the inference from the testimony is that these items in the nature of extra or additional work were performed by the contractor willingly, and by arrangement, or agreement with the state. Certainly, it appears from the evidence that these items were clearly and probably outside of any provisions of the contract, plans or specifications. They consisted of earth and rock excavation, iron and steel, sub-base construction, relaying drain pipe, and pipe railing and they aggregate in amount $8,720.72.

[392]*392None of the items for which this claim is made is comprised within the terms of the original, or of a supplemental, contract executed by the commission. The state contests the claim on this ground, and in substantiation of its defense calls our attention to chapter 30, Laws of 1909, section 130, which provides, State and county highways shall be constructed or improved by contract. Upon the completion and final adoption or approval, as provided by law, of the plans, specifications and estimate for the construction or improvement of a state or county highway, contracts therefor shall be executed as provided herein. * * * 9. Contingencies. All contingencies arising during the prosecution of the work shall be provided for to the satisfaction of the commission and as may be agreed upon in the original or by a supplemental contract executed by the commission.”

This provision will not defeat recovery by the claimant for the loss inflicted upon him by the directions of the engineer, in relation to the crushed stone, and the claimant’s compliance with them. The state misapprehends the nature of the claim in this respect, and the theory upon which it is predicated. The claimant does not sue for compensation for extra or additional work or materials. If he did, we agree that the statute would bar recovery, in the absence of a provision in the original, or in a supplemental, contract, executed by the commission, pursuant to which the same was done, or furnished. This item of the claim is for damages for breach of the originál contract, due to the action of the state’s representatives in compelling the claimant to grade and apply the stone in a manner not within the obligation of the contract. This action by the state was conceded on the trial.

In the case of Gearty v. Mayor, 171 N. Y. 61, a contractor was ordered by the city’s engineer to take up [393]*393and relay pavement, alleged to have been improperly constructed under the specifications. The contractor objected vigorously, but complied with the order, at substantial expense to himself. The complaint alleged these facts, among other things, and further, that the action of the engineer was unlawful and in breach of the contract. The complaint was dismissed at the close of the claimant’s case. The Court of Appeals reversed the judgment and ordered a new trial, saying in its opinion: “It is very clear that the plaintiff could have stopped work as ordered by the engineer of construction and stood upon his contention that the work had been properly done, brought his action to recover for labor and materials performed and furnished under the contract and claimed his prospective profits. (Smith v. Wetmore, 167 N. Y. 234; Roehm v. Horst, 178 U. S. 1.)

“ The important question is whether a second remedy is open to the contractor, such as is invoked in this case. The plaintiff did not choose to put himself in the attitude of refusing to obey the directions of the commissioners, thereby assuming the position of a defaulter under a contract with the city, but preferred to perform it as best he could, accepting under the final certificate such amount as the city admitted to be due him, subject to reservation of his rights under oral protests and the written release under seal, to which reference has already been made. * * ' *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Byson v. City of Los Angeles
308 P.2d 765 (California Court of Appeal, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
103 Misc. 388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-v-state-nyclaimsct-1918.