Anderson v. Imhoff

51 N.W. 854, 34 Neb. 335, 1892 Neb. LEXIS 129
CourtNebraska Supreme Court
DecidedMarch 30, 1892
StatusPublished
Cited by6 cases

This text of 51 N.W. 854 (Anderson v. Imhoff) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson v. Imhoff, 51 N.W. 854, 34 Neb. 335, 1892 Neb. LEXIS 129 (Neb. 1892).

Opinion

Maxwell, Ch. J.

This is an action for extra work performed on a building, for which the plaintiff claims he is entitled to recover the [337]*337sum of $715.38. On the trial of the cause judgment was rendered in his favor for the sum of $434.28. The first errors assigned relate to the pleadings, hence it is necessary to set them out. The petition is as follows:

“ Comes now the plaintiff and for his cause of action alleges and says:
First — That on or about — day of-, 1889, he entered into a contract in writing with said Joseph J. Imhoff, whereby the said plaintiff was to furnish all the material and perform all the labor necessary for the erection and completion of the brick work for the building situate on lots 1, 2, 3, in block 67, in the city of Lincoln, Nebraska, known as the Exposition building, for the sum of $4,135, according to the plans and specifications referred to and constituting a part of said contract, all of which plaintiff duly completed as required by said contract. '
“ Second — That the reason the contract is not hereto attached is because the same is in the possession of the defendant Imhoff, which he refuses to deliver up or to allow the plaintiff to have or make a copy of the same.
“ Third — The plaintiff, at the request of the defendant Imhoff, performed a large amount of labor and furnished a large amount of material and used the same in said building in addition to the original amount required by the contract orginally entered into, which said defendant Imhoff agreed to pay for, rendered necessary by certain changes in and additions to the requirements of the original contract, amounting in all to the sum of $2,011.13, of which a full statement of the items of the extras, labor, and material is set forth in a mechanic’s lien, which was duly filed in the office of register of deeds for Lancaster county, Nebraska, on or about January 4th 1890, and within four months from the date of furnishing the last material and the performance of the last labor, a true copy of which lien is hereto attached and marked Exhibit £ A.’
“Fourth — That no action at law has been commenced [338]*338for the recovery of the said sum nor any part thereof, and no part of said sum has been paid except the sum of $5,430.75, and there remains due now to the plaintiff from the said defendant Joseph J. Imhoff, upon said orginal contract and the extras herein described, the sum of $715.38 after allowing all just credits.
“ Fifth — Further, that the defendant Joseph J. Imhoff is the owner of the land upon which the said building is erected.
“Sixth — That the defendant, the Northwestern Mutual Life Insurance Company, holds a mortgage for $35,000 against the said building, filed in the office of the register of deeds for Lancaster county, Nebraska, on September 18, 1889, book 57, page 186, mortgage record.
“Wherefore plaintiff prays that an accounting may be had between the plaintiff and said defendant Joseph J. Imhoff, and that the said plaintiff be allowed to recover in this action the sum of $715.38, or such other sum as may be found to be justly due him, and the said sum may be declared a lien on the said land and building thereon, and that a decree be entered therefor, and an order of sale duly issued directing the sale of said land and building for the payment of any judgment or decree that may be found in favor of the said plaintiff, and for such further and other relief, or both, as may be found just and equitable, together with interest and costs of this suit.”

To this petition the defendant filed the following answer:

“Now comes the said defendants, and for answer to the petition of said plaintiff says:
“First — The defendants admit that on or about the 18th day of July, 1889, the said plaintiff entered into a written contract with said defendant Imhoff, a copy of which is hereto annexed and made a part hereof, by which said plaintiff was to do and perform all the work, labor, and material necessary to construct a certain building at the [339]*339corner of N and Twelfth streets, according to the plans and specifications made a part of the said contract.
“Second — The said Imhoff, as further answer to said petition, says that he has done and performed all that by the terms of said contract he has agreed to do and perform, and has been and is willing to abide by the decision of the architect as to extra work or changes made in plans per terms of contract.
“ Third — The said Imhoff further says in answer to said petition, that the amount'found due the said plaintiff for extra work upon said building caused by change of plans, as per architect’s certificate, is $1,438, and that the said defendant has paid upon said amount the sum of $1,295, leaving a balance unpaid of $143.25, which sum he has duly tendered the said plaintiff, and which said plaintiff has refused to accept as he had agreed to do in his said contract.
“Fourth — The said defendants deny each and every allegation in said petition, except where expressly admitted in this answer.
“Wherefore the defendants pray that they may go hence and recover judgment against said plaintiff for the costs of suit.”

A reply was thereupon filed. The defendant then filed a motion as follows: “And now comes the defendant by his attorneys, and moves the court to compel the plaintiff to make his charge of fraud against the certificate of the architect more specific and definite, by stating facts and circumstances, and upon what particular work the said architect acted fraudulently, and wherein the said acts of the architect and the certificates of the architect were fraudulent.” The motion was overruled, and the overruling of the same is the first error complained of. The court did not err in overruling the motion. The reply does set up the ground of fraud, viz.: “Said architect fraudulently and collusively made, and that in said pre[340]*340tended decision of said architect no allowance whatever was made for large portions of said extra work and material, and plaintiff says that said pretended decision was made in the absence of this plaintiff and without any notice to him of the time and place when the same would be made, and that said architect refused to figure up the amount of said extra work and material in the presence of this plaintiff, or explain to this plaintiff the basis of his said pretended decision, but fraudulently and collusively refused to make the proper allowance for the material actually furnished and the work actually done by this plaintiff.” The defendant thereupon demurred to the reply because it set up a new cause of action. The demurrer was overruled and this is now assigned for error.' The court did not err in overruling the demurrer. The reply did not set up a new cause of action, but merely matter which, if true, would avoid the provision in the contract in- regard to the adjustment and certificate of the architect. This was proper to set forth in the reply. In other words, matter in explanation or avoidance of the facts stated in the answer may be pleaded in the reply.

The third error assigned is that the witness Anderson was permitted to refresh his memory from a memorandum not made at the time of the measurements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penner Installation Corporation v. United States
89 F. Supp. 545 (Court of Claims, 1950)
Keifer & Keifer v. Reconstruction Finance Corp.
97 F.2d 812 (Eighth Circuit, 1938)
Wood v. Freeman
1928 OK 237 (Supreme Court of Oklahoma, 1928)
Moran v. Wilson
133 N.E. 845 (Indiana Court of Appeals, 1922)
Davis v. State
70 N.W. 984 (Nebraska Supreme Court, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
51 N.W. 854, 34 Neb. 335, 1892 Neb. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-v-imhoff-neb-1892.