Ancraft Products Co. v. Universal Oil Products Co.

427 N.E.2d 585, 100 Ill. App. 3d 694, 56 Ill. Dec. 390, 1981 Ill. App. LEXIS 3391
CourtAppellate Court of Illinois
DecidedSeptember 30, 1981
Docket79-2434
StatusPublished
Cited by38 cases

This text of 427 N.E.2d 585 (Ancraft Products Co. v. Universal Oil Products Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ancraft Products Co. v. Universal Oil Products Co., 427 N.E.2d 585, 100 Ill. App. 3d 694, 56 Ill. Dec. 390, 1981 Ill. App. LEXIS 3391 (Ill. Ct. App. 1981).

Opinion

Mr. PRESIDING JUSTICE RIZZI

delivered the opinion of the court:

This case involves a dispute over the construction of a contract between plaintiff, Ancraft Products Co., and defendant, Universal Oil Products Company, Inc. (UOP, Inc.). According to the contract, plaintiff was to build three impregnating machines for defendant. In its complaint, plaintiff alleged that it performed the work and design services required for the machines and delivered them on schedule, and that defendant owes $59,348.06 towards the total contract price. Defendant admitted that it had not paid the $59,348.06, but denied that it owed that amount. The gravamen of the dispute is that plaintiff characterizes the contract as a fixed fee contract, whereas defendant contends that it is a cost-plus contract with an upset price. The $59,348.06 represents the difference between the amount paid by defendant on the basis of time and materials, and the amount alleged by plaintiff to be the fixed price of the contract. The trial court entered judgment in favor of plaintiff but denied an award of interest on this sum from the date it became due until the date of the judgment. On appeal, defendant argues that the trial court erred in entering judgment in favor of plaintiff. Plaintiff cross-appeals, contending that the court should have ordered the payment of interest on the unpaid balance of the contract. Since we conclude that plaintiff was not entitled to the $59,348.06, we reverse.

The negotiations for the contract took place between E. W. Nyberg of Ancraft and D. A. Shepard of Hoyer-Schlesinger-Turner, Inc. (HST), an engineering firm acting as defendant’s purchasing agent. Shepard died before the trial.

In April 1973, plaintiff sent HST a letter setting forth a quotation for building the three impregnating machines which defendant sought to acquire. The essential terms were:

“The price for the machine with the plastic valves and counter clockwise rotation would be $110,000.00.”
“The price for the machines with the stainless steel valves parts and clockwise rotation would be $145,000.00 each.”
“Engineering for the stainless steel machines with clockwise rotation would be approximately $25,000.00.”
“Labor charges would be based on $13.00/Hr. Engineering charges would be based on $15.00/Hr. Materials would be billed at cost plus 15%. ”
“Payouts are to be made semimonthly with Ancraft providing copies of all invoices for purchased materials and accounting for labor and engineering hours worked.”
“Should your order be cancelled before December 30, 1973 there would be a cancellation charge of $70,000.00 plus any monies due on purchased items received or to be received, labor and engineering.”

Following further negotiations, HST sent plaintiff a letter dated May 2 which mirrored in most respects the terms contained in plaintiff’s letter. The only major addition was a paragraph inserted after the price and hourly rate provisions which stated:

“However the cost of stainless and plastic Impregnating Machines shall not exceed the above listed prices, nor shall the engineering exceed the $25,000.00 limit unless there is a change in scope and a written change order issued.”

Defendant’s purchase order, signed by Shepard and dated May 7, 1973, reads:

“1 Stainless Steel Impregnation Machine
2 Plastic Impregnation Machines
$110,000
Approximate Engineering Cost for Item 559601
Approximate Total Purchase Order Price, no crating included:
Hourly Rates will be as follows:
Labor $13.00 hour
Engineering $15.00 hour Material at cost plus 15%
Invoices will be semi-monthly * * *.
$145,000 $220,000 $ 25,000
$390,000
Should the order be cancelled on or before December 30, 1973, there will be a cancellation charge of $70,000.00 plus monies due on purchased items received or cancellation charges on items to be received, labor and engineering charges.”

The purchase order concluded with the following statement: “This confirms Letter of Intent dated May 2, 1973, to Mr. Ernest W. Nyberg.”

On September 7, HST sent plaintiff a letter requesting semimonthly status reports. The letter further stated:

“We also wish to confirm our verbal statement that no changes increasing the cost of these machines will be effective until such changes have been approved by myself and a written Change Order issued to your firm. Under no circumstance will the total Purchase Order price be exceeded.”

Five changes were made in defendant’s original order, and Shepard signed the purchase order sheets reflecting the changes and showing an increase of $70,900 in the total cost of the machines.

Plaintiff billed defendant semimonthly on the basis of engineering charges, labor and materials (at cost plus 15%). Defendant paid all invoices except for the final one involving the disputed $59,348.06. The trial court determined that plaintiff was entitled to receive this sum but that plaintiff was not entitled to interest for the interval between July 26, 1974, when the amount became due, and the date of the entry of judgment.

Defendant argues that the trial court erred in determining that the contract was a fixed fee contract rather than a cost plus contract with a maximum price. We agree.

In construing a contract, the primary objective is to determine and give effect to the intentions of the parties (In re Estate of Klinker (1979), 80 Ill. App. 3d 28, 30, 399 N.E.2d 299, 301) at the time they entered into the contract. (Cedar Park Cemetery Association, Inc. v. Village of Calumet Park (1947), 398 Ill. 324, 335,75 N.E.2d 874, 880.) If the contract terms are unambiguous, then the parties’ intent must be determined solely from the language of the contract. (Schek v. Chicago Transit Authority (1969), 42 ILl. 2d 362, 364, 247 N.E.2d 886, 888.) If, however, the contract language is ambiguous, extrinsic evidence as to facts surrounding formation of the contract may be considered in determining the parties’ intent. (La Throp v. Bell Federal Savings & Loan Association (1977), 68 Ill. 2d 375, 384, 370 N.E.2d 188

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gordon v. Landfill, LLC
2021 IL App (5th) 200383-U (Appellate Court of Illinois, 2021)
In re Marriage of Ring
2020 IL App (1st) 191761-U (Appellate Court of Illinois, 2020)
Daniel v. Ripoli
2015 IL App (1st) 122607 (Appellate Court of Illinois, 2015)
Homeowners Choice, Inc. v. Aon Benfield, Inc.
938 F. Supp. 2d 749 (N.D. Illinois, 2013)
Urban Sites of Chicago, LLC v. Crown Castle USA
2012 IL App (1st) 111880 (Appellate Court of Illinois, 2012)
Village of Palatine v. Palatine Associates
2012 IL App (1st) 102707 (Appellate Court of Illinois, 2012)
Berg v. Ehome Credit Corp.
848 F. Supp. 2d 841 (N.D. Illinois, 2012)
Bright Horizons Children's Centers, LLC v. Riverway Midwest II, LLC
931 N.E.2d 780 (Appellate Court of Illinois, 2010)
Fleet Business Credit, LLC v. Enterasys Networks, Inc.
816 N.E.2d 619 (Appellate Court of Illinois, 2004)
Schwinder v. Austin Bank of Chicago
809 N.E.2d 180 (Appellate Court of Illinois, 2004)
Schwinder v. Austin Bank
Appellate Court of Illinois, 2004
Wojcik v. Aetna Life Insurance & Annuity Co.
901 F. Supp. 1282 (N.D. Illinois, 1995)
Groshek v. Frainey
654 N.E.2d 467 (Appellate Court of Illinois, 1995)
Meyer v. Marilyn Miglin, Inc.
652 N.E.2d 1233 (Appellate Court of Illinois, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
427 N.E.2d 585, 100 Ill. App. 3d 694, 56 Ill. Dec. 390, 1981 Ill. App. LEXIS 3391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ancraft-products-co-v-universal-oil-products-co-illappct-1981.