Anchorage v. United States

123 F.4th 1315
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 16, 2024
Docket22-1719
StatusPublished
Cited by1 cases

This text of 123 F.4th 1315 (Anchorage v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anchorage v. United States, 123 F.4th 1315 (Fed. Cir. 2024).

Opinion

Case: 22-1719 Document: 69 Page: 1 Filed: 12/16/2024

United States Court of Appeals for the Federal Circuit ______________________

ANCHORAGE, A MUNICIPAL CORP., Plaintiff-Appellee

v.

UNITED STATES, Defendant-Appellant ______________________

2022-1719 ______________________

Appeal from the United States Court of Federal Claims in No. 1:14-cv-00166-EJD, Senior Judge Edward J. Damich. ______________________

Decided: December 16, 2024 ______________________

JASON N. SMITH, Seyfarth Shaw LLP, Washington, DC, argued for plaintiff-appellee. Also represented by EDWARD VICTOR ARNOLD, BENNETT DAVID GREENBERG; DONALD FEATHERSTUN, San Francisco, CA; ANNE HELZER, ROBERT OWENS, Municipality of Anchorage, Anchorage, AK.

EVAN WISSER, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for defendant-appellant. Also represented by BRIAN M. BOYNTON, VINCENT DE PAUL PHILLIPS, JR., STEVEN JOHN GILLINGHAM, DANIEL HOFFMAN, PATRICIA M. MCCARTHY, KARA WESTERCAMP. Case: 22-1719 Document: 69 Page: 2 Filed: 12/16/2024

______________________

Before TARANTO, HUGHES, and CUNNINGHAM, Circuit Judges. HUGHES, Circuit Judge The United States appeals a decision from the United States Court of Federal Claims holding that the United States breached two contracts with the municipality of Anchorage to improve the Port of Alaska. Anchorage and the United States signed a Memorandum of Understanding in 2003 and a Memorandum of Agreement in 2011 to upgrade and expand the Port of Alaska. The Court of Federal Claims held that the government breached the 2003 agreement by not delivering a defect-free port and breached the 2011 agreement by settling subcontractor claims without conferring with Anchorage. Because the 2003 Memorandum of Understanding did not require the United States to deliver a defect-free port, we vacate the Court of Federal Claims’ decision as it relates to the 2003 Memorandum of Understanding and remand for further proceedings as described below. We affirm the Court of Federal Claims’ determination that the United States breached the 2011 Memorandum of Agreement by settling subcontractor claims without conferring with Anchorage, as well as the court’s award of damages to Anchorage for the United States’ breach of the 2011 Memorandum of Agreement. I A The Port of Alaska (Port), formerly the Port of Anchorage, is a critical national seaport and the “kingpin in Alaska’s corridor of commerce.” J.A. 5698. An estimated 90% of the merchandise goods for 85% of Alaska’s populated areas pass through the Port annually. Additionally, jet fuel for military operations at Joint Base Case: 22-1719 Document: 69 Page: 3 Filed: 12/16/2024

ANCHORAGE v. US 3

Elmendorf-Richardson and for the Ted Stevens Anchorage International Airport arrives via the Port. Prior to 2003, “[t]he Municipality of Anchorage determined that the facilities at the Port . . . were deteriorating and outdated.” J.A. 3. Anchorage envisioned a multi-year project that would help increase the Port’s ability to serve Anchorage, the State of Alaska, commercial tenants, and the United States military. “Not having the expertise to undertake the [p]roject on its own, [Anchorage] sought a party to provide the requisite technical expertise.” Id. After considering the private sector, Anchorage contracted with the Maritime Administration (MARAD), within the U.S. Department of Transportation “to embark on a port infrastructure development program.” Id. Anchorage selected MARAD for its “purported expertise in designing, constructing, and overseeing port development projects and its authority to administer federal and non- federal share funds.” Compl. at ¶ 17, Anchorage v. United States, Case No. 1:14-cv-00166 (Fed. Cl. Feb. 28, 2014), ECF No. 1. Anchorage and MARAD executed two contracts over the life of the project. The first contract was a Memorandum of Understanding executed in 2003 (2003 Memorandum), which “described project administration, funding, and the obligations of the parties.” J.A. 3. The express terms of the 2003 Memorandum required Anchorage to “[p]rovide overall program requirements and direction of Port Expansion to MARAD.” J.A. 16044. The 2003 Memorandum also specified, with regard to the level of program control to be exerted by Anchorage, that Anchorage had the responsibility to “[r]eview all plans, specifications, and status reports submitted by the primary contractor and its subcontractors before submission to MARAD.” J.A. 16045. “[Anchorage] was also responsible for certifying completion and acceptance of the work.” J.A. 3. Specifically, Anchorage was required to certify that a Case: 22-1719 Document: 69 Page: 4 Filed: 12/16/2024

contractor’s work was acceptable and, if so, would issue a certificate of completion to MARAD. Only with the completed certificate of completion could MARAD accept the work and pay the contractor. The 2003 Memorandum also outlined MARAD’s responsibilities, which included “[c]oordinat[ing] with other Federal agencies that receive annual Congressional appropriations for Port Expansion” to increase funding for the project. J.A. 16045. Additionally, MARAD was responsible for executing all financial documents, accepting transfers of non-federal funds, and to “[o]bligate and disburse funding for Port Expansion project oversight, program management, study, environmental analysis, engineering, design, construction, or rehabilitation pursuant to Port Expansion requirements consistent with contract requirements.” J.A. 16046. Either party could terminate the 2003 Memorandum by providing ninety days’ notice to the other party. To complete the project, MARAD contracted with Integrated Concepts and Research Corporation (ICRC) in 2003 (the MARAD-ICRC contract). ICRC, in turn, was to “[sub]contract[] with other design/engineering firms and contractors to complete various aspects of the work.” Compl. at ¶ 31, Anchorage, Case No. 1:14-cv-00166 (Feb. 28, 2014), ECF No. 1. The contract between MARAD and ICRC “included contract clauses which provided [MARAD] the right to require ICRC to correct defective work without charge.” Id. at ¶ 35. Problems with the project were discovered during a third-party inspection in 2010, when “large-scale damage was found in the installed sheet piles”, which protect an excavated area from earth and groundwater. J.A. 3. While ICRC and its subcontractors performed the work, Anchorage ultimately blamed the project issues on MARAD, alleging that MARAD failed to “develop[] [p]roject management or inspection protocols” over ICRC and its Case: 22-1719 Document: 69 Page: 5 Filed: 12/16/2024

ANCHORAGE v. US 5

subcontractors, and “abdicated its responsibilities” to oversee the project. Compl. at ¶¶ 61–65, Anchorage, Case No. 1:14-cv-00166 (Feb. 28, 2014), ECF No. 1. The damage resulted in “large sections of the [Port] being unsuitable for use.” J.A. 3 The damage was the “impetus for [Anchorage and MARAD] entering into a second agreement in 2011.” J.A. 3.

The 2011 Memorandum of Agreement (2011 Memorandum), which supplemented the 2003 Memorandum, “redefined the roles and responsibilities of Anchorage and [MARAD], outlined authorities, and assured accountability for the [p]roject” through joint oversight by both parties. J.A. 3–4. “It created a Port Oversight and Management Organization [] to ‘provide overall executive leadership, vision, policy, strategic objectives, and priorities for the project.’” Id. (internal citations omitted). The Port Oversight and Management Organization consisted “of a committee of decision makers from both Anchorage and MARAD, who would hold frequent meetings to address issues related to the Port construction.” J.A. 16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mostafa v. United States
Federal Claims, 2026
Causam Enterprises, Inc. v. Itc
Federal Circuit, 2025

Cite This Page — Counsel Stack

Bluebook (online)
123 F.4th 1315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anchorage-v-united-states-cafc-2024.