Anchor Operating Company v. Gulfwest Drilling Company

CourtCourt of Appeals of Texas
DecidedAugust 30, 1995
Docket03-94-00539-CV
StatusPublished

This text of Anchor Operating Company v. Gulfwest Drilling Company (Anchor Operating Company v. Gulfwest Drilling Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anchor Operating Company v. Gulfwest Drilling Company, (Tex. Ct. App. 1995).

Opinion

Anchor v. Gulfwest

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN



NO. 03-94-00539-CV



Anchor Operating Company, Appellant



v.



Gulfwest Drilling Company, Appellee



FROM THE DISTRICT COURT OF FAYETTE COUNTY, 155TH JUDICIAL DISTRICT

NO. 92V-211, HONORABLE DAN R. BECK, JUDGE PRESIDING



PER CURIAM



This appeal concerns a disputed drilling contract. Appellee Gulfwest Drilling Company contracted to drill a series of oil wells for appellant Anchor Operating Company, the operator of the lease. Gulfwest drilled two wells, but was unable to complete a third, the Voss #1 well. Because damage to the Voss #1 well rendered it unusable, each side sued the other in separate lawsuits: Anchor claimed breach of the drilling contract, and Gulfwest sought a declaratory judgment as well as amounts due for services performed under the contract. The trial court consolidated the two suits into one, which was tried to a jury. Following the jury's verdict in favor of Gulfwest, the court rendered judgment on the verdict. We will affirm the judgment of the trial court.

In its first point of error, Anchor attacks the amount of damages Gulfwest recovered. The trial court submitted the case to the jury on the theory that the damage to the Voss #1 well and the subsequent inability to complete it were caused by the failure of the casing in the well. The jury found that the casing failure was not caused by Gulfwest's operations. The jury then awarded Gulfwest $164,485.46 as the amount due under the contract. The court rendered judgment for the same amount. Anchor argues that this amount was not based on the formula set out in the drilling contract and that the evidence is both legally and factually insufficient to support the amount of damages. Anchor does not challenge the court's theory of submission that the casing failure damaged the well.

To review Anchor's no-evidence challenge, we consider only the evidence and inferences tending to support the finding. If any probative evidence supports the finding, it must be upheld. Responsive Terminal Sys., Inc. v. Boy Scouts of Am., 774 S.W.2d 666, 668 (Tex. 1989); Southern States Transp., Inc. v. State, 774 S.W.2d 639, 640 (Tex. 1989). To review Anchor's factual-sufficiency challenge, we consider all the evidence and will set aside the finding only if the evidence supporting it is so weak, or the evidence to the contrary so overwhelming, as to make it clearly wrong and unjust. Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986); West v. Watkins, 594 S.W.2d 800, 802 (Tex. Civ. App.--San Antonio 1980, writ ref'd n.r.e.).

The drilling agreement between the parties is on a preprinted form contract promulgated by the International Association of Drilling Contractors, titled "Drilling Bid Proposal and Footage Contract - U.S." Anchor and Gulfwest altered certain terms of the form contract by lining through its language and inserting their own.

In arguing that damages were incorrectly calculated, Anchor relies on article 6.3(c) of the contract, which carries the heading "Early Termination Compensation." Article 6.3(c) states:



Subsequent to Spudding: If such work stoppage occurs by or through the fault of Operator after the spudding of the well, Operator shall pay the Contractor the lesser of (1) the amount owing Contractor at the time of such work stoppage under the footage rate, or (2) the applicable daywork rate, and standby rate; but in such event Operator shall pay Contractor for a minimum footage of 1,300 feet regardless of whether or not the well has been drilled to such depth at the time of work stoppage.



Article 6.3(c), however, is a subpart of article 6, titled "Stoppage of Work by Operator or Contractor." Articles 6.1 and 6.2 of article 6 permit the operator and the contractor to order drilling to stop before the well is completed under stated conditions. See Owen L. Anderson, The Anatomy of an Oil and Gas Drilling Contract, 25 Tulsa L.J. 400-02 (1990). The contractor's right to terminate the contract is narrowly drawn, limited to the events of force majeure, total loss of the drilling rig, the operator's failure to pay timely, and the operator's financial impairment. The operator, by contrast, can order the contractor to stop work at any time, even though the contractor has made no default under the contract. See id.

Should either the operator or the contractor order drilling to cease as permitted, articles 6.1 and 6.2 specify that the compensation due the non-terminating party is that set out in article 6.3. Article 6.3 contains three sections that tailor the compensation to the timing of the order to cease operations: (a) before operations have commenced, (b) after commencement but before spudding, and (c) after spudding.

The drilling contract further provides that Gulfwest will be compensated for drilling each well based on the number of feet drilled, but that for certain other operations it will be compensated a fixed amount each day. The evidence shows that, after Gulfwest determined that the casing had parted and notified Anchor that it was switching to the dayrate portion of the contract, Gulfwest's president, Charles Major, talked to Anchor's president, Alfred Pampell, in Pampell's office. The two disagreed over who was responsible for the drilling problems, following which Major told Pampell that Gulfwest would cease operations, secure the well, and move the rig off the wellsite. Gulfwest's determination to discontinue operations due to the casing failure was not authorized by article 6.2. Neither were operations discontinued at Anchor's order pursuant to article 6.1. Therefore, article 6.3(c), governing compensation when either the operator or the contractor terminates the contract under article 6, does not apply to this case.

The facts of this case instead invoke article 18 of the contract, titled "Responsibility for Loss or Damage." Article 18.6, which applies when operations are occurring on a footage basis, provides:



If the hole is lost or damaged as a result of the failure of Operator's casing or equipment either during or after the running and setting of such casing, or as a result of subsequent failure of the cementing job resulting in parted casing, such loss shall be borne by Operator and Contractor shall nevertheless be paid: (a) For all footage drilled and other work performed by Contractor prior thereto; (b) For work performed in an effort to restore the hole to such condition as that further drilling or other operations may be commenced at the applicable daywork rate; and (c) . . . . (1)



Under the contract, Anchor was responsible for furnishing the casing and cement for the Voss #1 well. Anchor does not dispute the fact that the casing in the Voss #1 well failed. The evidence shows that this failure occurred while operations were being conducted on the footage portion of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sharp v. Broadway National Bank
784 S.W.2d 669 (Texas Supreme Court, 1990)
Alvarado v. Farah Manufacturing Co.
830 S.W.2d 911 (Texas Supreme Court, 1992)
Clark v. Trailways, Inc.
774 S.W.2d 644 (Texas Supreme Court, 1989)
Responsive Terminal Systems, Inc. v. Boy Scouts of America
774 S.W.2d 666 (Texas Supreme Court, 1989)
Southern States Transportation, Inc. v. State
774 S.W.2d 639 (Texas Supreme Court, 1989)
Gannett Outdoor Co. of Texas v. Kubeczka
710 S.W.2d 79 (Court of Appeals of Texas, 1986)
Satterwhite v. Safeco Land Title of Tarrant
853 S.W.2d 202 (Court of Appeals of Texas, 1993)
Lopez v. Foremost Paving, Inc.
796 S.W.2d 473 (Court of Appeals of Texas, 1990)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
West v. Watkins
594 S.W.2d 800 (Court of Appeals of Texas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
Anchor Operating Company v. Gulfwest Drilling Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anchor-operating-company-v-gulfwest-drilling-compa-texapp-1995.