Ampersand Chowchilla Biomass v. United States

26 F.4th 1306
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 24, 2022
Docket21-1385
StatusPublished
Cited by6 cases

This text of 26 F.4th 1306 (Ampersand Chowchilla Biomass v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ampersand Chowchilla Biomass v. United States, 26 F.4th 1306 (Fed. Cir. 2022).

Opinion

Case: 21-1385 Document: 41 Page: 1 Filed: 02/24/2022

United States Court of Appeals for the Federal Circuit ______________________

AMPERSAND CHOWCHILLA BIOMASS, LLC, MERCED POWER, LLC, Plaintiffs-Appellants

v.

UNITED STATES, Defendant-Appellee ______________________

2021-1385 ______________________

Appeal from the United States Court of Federal Claims in No. 1:14-cv-00841-MCW, Senior Judge Mary Ellen Cos- ter Williams. ______________________

Decided: February 24, 2022 ______________________

STEPHEN G. LEATHAM, Heurlin, Potter, Jahn, Leatham, Holtmann & Stoker, P.S., Vancouver, WA, argued for plaintiffs-appellants.

CLINT A. CARPENTER, Appellate Section, Tax Division, United States Department of Justice, Washington, DC, ar- gued for defendant-appellee. Also represented by BRUCE R. ELLISEN, DAVID A. HUBBERT. ______________________

Before NEWMAN, HUGHES, and STOLL, Circuit Judges. Case: 21-1385 Document: 41 Page: 2 Filed: 02/24/2022

HUGHES, Circuit Judge. This is a tax case. Ampersand Chowchilla Biomass, LLC and Merced Power, LLC appeal a decision of the Court of Federal Claims denying their request for additional pay- ments of Section 1603 grants under the American Recovery and Reinvestment Act of 2009. Because we agree with the Court of Federal Claims that the relevant power facilities did not meet the requirements of the statute, we affirm. I A In 2007, California Biomass Fund I, LLC (CalBio) ac- quired two defunct facilities and began restoring them and upgrading them to biomass facilities, expecting the facili- ties to be operational in 2008. Before CalBio acquired the facilities, Pacific Gas & Electric Company had entered into power-purchase agree- ments with the facilities’ previous owner. PG&E had agreed to purchase electricity when (1) the facilities achieved commercial operations and passed initial capacity tests, (2) PG&E received performance-assurance pay- ments, and (3) the facilities received approval from the Cal- ifornia Public Utilities Commission. CalBio assumed these power-purchase agreements, and CalBio and PG&E later amended the agreements to loosen their requirements. CalBio and PG&E also entered into interconnection agree- ments that required the facilities to pass pre-parallel test- ing, which ensures that the facilities can operate at the same frequency and in the same phase as the transmission grid so that the facilities do not damage the grid. While renovating in 2007, CalBio secured Authority to Construct permits for the facilities. These permits allowed construction on the facilities and allowed the facilities to generate and sell electricity. The Authority to Construct permits could be converted into Permits to Operate after the facilities met certain conditions, like emissions tests. Case: 21-1385 Document: 41 Page: 3 Filed: 02/24/2022

AMPERSAND CHOWCHILLA BIOMASS v. US 3

Biomass facilities, though, often have some difficulty pass- ing environmental tests. So instead of shutting down bio- mass facilities at the first sign of noncompliance—which could lead to agricultural waste being burned in open fields, causing more environmental pollution—the San Joaquin Valley Air Pollution Control District has a Notice of Violation process in which the District fines and oversees noncompliant facilities until they are brought back into compliance. The Chowchilla and Merced facilities had their “initial fires” in April and July 2008, respectively. CalBio labeled the facilities “in operation” as of May 15, 2008 and August 23, 2008. And the facilities passed pre-parallel testing un- der the PG&E interconnection agreements on June 17, 2008 and August 24, 2008. Following these events, the facilities began selling elec- tricity on the spot market. On December 12, 2008, Chowchilla met the requirements under its power-pur- chase agreement and accordingly started selling its elec- tricity exclusively to PG&E. Although Merced did not start selling its electricity exclusively to PG&E until February 21, 2009, the parties recognized that Merced had met the requirements under its power-purchase agreement based on data from the third and fourth quarters of 2008. From May 15, 2008 until the end of that year, the Chowchilla facility operated at 34.1% of its rated capacity, generating 20,553 MWh of electricity and $1,408,941 in revenue. And from August 23, 2008 through the end of 2008, the Merced facility operated at 42.1% capacity, gen- erating 14,306 MWh of electricity and $851,152 in revenue. The facilities operated fairly continuously throughout 2009, during which the Chowchilla facility operated at 53.9% capacity and the Merced facility operated at 51.2% capacity. The facilities occasionally were noncompliant with emissions regulations, but the District allowed the Case: 21-1385 Document: 41 Page: 4 Filed: 02/24/2022

facilities to continue operating and never revoked their Au- thority to Construct permits. B In 2009, Congress passed the American Recovery and Reinvestment Act “[t]o assist those most impacted by the [2008] recession.” American Recovery and Reinvestment Act of 2009 (ARRA), Pub. L. No. 111-5, § 3(a), 123 Stat. 115, 115–16. Stated purposes of this statute were “[t]o provide investments needed to increase economic efficiency” and invest in “environmental protection[] and other infrastruc- ture that will provide long-term economic benefits.” Id. One provision allowed entities to receive federal grants if they “placed in service” a renewable energy facility during 2009 or 2010 or if they began constructing property in 2009 or 2010 that they later placed in service before the relevant credit-termination date. Id. § 1603(a)(1)–(2), 123 Stat. at 364–66. The government intended that these “Section 1603” grants would “increase investment in domestic clean energy production” by “reimburs[ing] eligible applicants for a portion of the cost of installing the specified energy prop- erty.” See U.S. Dep’t of Treas., 1603 Program: Payments for Specified Energy Property in Lieu of Tax Credits, https://home.treasury.gov/policy-issues/financial-markets- financial-institutions-and-fiscal-service/1603-program- payments-for-specified-energy-property-in-lieu-of-tax- credits (last visited Jan. 18, 2022). CalBio was experiencing financial difficulties at that time, so it investigated whether it could apply for Section 1603 grants for the Chowchilla and Merced facilities. Cal- Bio ultimately concluded that it could not apply for Section 1603 grants because its facilities had been placed in service in 2008, outside of the statute’s required period. Finding no resolution to its continuing financial problems, CalBio sus- pended operations in June 2010 and decided to sell the fa- cilities. Case: 21-1385 Document: 41 Page: 5 Filed: 02/24/2022

AMPERSAND CHOWCHILLA BIOMASS v. US 5

On December 28, 2010, Akeida Environmental Fund LP acquired the facilities. Akeida spent nearly $15 million improving the facilities, which passed emissions tests in August 2011. In October 2011, Akeida applied for Section 1603 grants, claiming that the facilities were placed in ser- vice when Akeida’s emissions improvements were certified on August 11, 2011. Akeida requested a $12 million grant for each facility. The United States Department of Treasury largely rejected Akeida’s claims because, according to Treasury, most of the property had been placed in service in 2008. Instead, Treasury granted only $1.1 million for each facility, awarded for the additional property that was eligible based on the date Akeida placed it in service. Appellants, the direct owners of the two facilities and subsidiaries of Akeida, sued in the Court of Federal Claims for the remainder. The Court of Federal Claims held for the government, agreeing that the facilities were placed in ser- vice in 2008.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winston v. United States
Federal Claims, 2025
White v. United States
Federal Claims, 2025
Tippins v. United States
93 F.4th 1370 (Federal Circuit, 2024)
Lambro v. United States
90 F.4th 1375 (Federal Circuit, 2024)
Keltner v. United States
Federal Claims, 2023
Olsen v. CIR
52 F.4th 889 (Tenth Circuit, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
26 F.4th 1306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ampersand-chowchilla-biomass-v-united-states-cafc-2022.