Ames & Webb, Inc. v. Commercial Laundry Co.

133 S.E.2d 547, 204 Va. 616, 1963 Va. LEXIS 195
CourtSupreme Court of Virginia
DecidedDecember 2, 1963
DocketRecord 5607
StatusPublished
Cited by17 cases

This text of 133 S.E.2d 547 (Ames & Webb, Inc. v. Commercial Laundry Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ames & Webb, Inc. v. Commercial Laundry Co., 133 S.E.2d 547, 204 Va. 616, 1963 Va. LEXIS 195 (Va. 1963).

Opinion

Eggleston, C. J.,

delivered the opinion of the court.

Commercial Laundry Company, Incorporated, sometimes hereinafter referred to as the plaintiff,, filed its motion for judgment against Ames & Webb, Incorporated, and Virginia Electric & Power Company to recover damages alleged to have been done to the plaintiff’s building located at the corner of Hampton boulevard and Twenty-sixth street, in the city of Norfolk, by an excavation adjacent to the plaintiff’s premises. The motion alleged that as a direct result of the defendants’ negligence in and about the excavation, and in “disregard for the safety of the property of others,” the plaintiff’s building was damaged. Each defendant filed a general denial of negligence on its part.

There was a trial before a jury, during which the plaintiff took a nonsuit as to the defendant, Virginia Electric & Power Company. The case against Ames & Webb, Incorporated, resulted in a verdict and judgment in favor of the plaintiff for the sum of $25,000. We granted this defendant a writ of error.

*618 In its assignments of error the defendant makes these contentions: (1) The verdict and judgment are contrary to the law and the evidence in that there is no showing that the defendant was guilty of any negligence which was the proximate cause of the damage to the plaintiff’s building; (2) the trial court erred in permitting the witness, Hyman Rosenberg, to testify as an expert and answer a hypothetical question propounded to him by counsel for the plaintiff relative to the proper method in which the excavation should have been made; (3) the court erred in not granting the defendant’s motion for a mistrial when E. T. Gresham, a witness for the defendant, on cross-examination by counsel for the plaintiff, “mentioned an insurance company” under circumstances which, the defendant says, indicated to the jury that its liability was covered by insurance; (4) the court erred in its rulings on the instructions.

In view of the jury’s verdict, approved by the trial court, the evidence will be stated and considered in the light most favorable to the plaintiff.

In July, 1960 the defendant, Ames & Webb,, Incorporated, a road building contractor, entered into a contract with the Virginia Department of Highways for the installation of a drainage sewer pipe line along Hampton boulevard and other streets in the city of Norfolk. According to the plans and specifications prepared by the Department, a portion of this sewer line was designed to run along the front of the plaintiff’s building which is located on the eastern side of Hampton boulevard. The line which was specified and laid out by the Department required that the center of the pipe line be located in the sidewalk and within 8 feet of the front of the plaintiff’s brick building.

While the method of the excavation and the installation of the pipe was not specified, the ditch was to be of sufficient depth and width to contain a concrete pipe line 48 inches in diameter and resting on a 24-inch stone bedding. For this purpose the defendant undertook to excavate a ditch 12 feet deep and about 8 feet wide along and near the front wall of the plaintiff’s building.

The soil in this area is sandy and at a depth of approximately 10 feet becomes mixed with water. During the progress of the excavation it was necessary to brace or shore up the sidewalls of the ditch to prevent their caving in and dislodging the soil under the foundation of the plaintiff’s building.

According to the evidence for the defendant, it followed the usual *619 and accepted method of excavating this ditch and bracing the sidewalls in soil of this nature and under similar conditions. First, two trenches, each about 2 feet deep and 8 feet apart, were dug along the proposed sides of the ditch. In these trenches were inserted wooden braces or “walers” which were kept apart by cross braces for the proposed width of the ditch. Then sections of metal interlocking sheet piling, from 15 to 20 feet long and held in line by the “walers,” were driven into the ground for the purpose of retaining the soil on each side of the proposed excavation. When this metal piling had been thus installed, the 8-foot area between them,, constituting the width of the ditch, was dredged out with a “clamshell bucket.” After the pipe had been laid and the ditch refilled with earth, the metal piling was withdrawn.

However, there is evidence on behalf of the plaintiff that the excavation was not done in what the defendant’s witnesses said was the proper, customary and approved method. Witnesses for the plaintiff testified that the excavation reached a depth of from 5 to 6 feet before piling was installed, and that this was improper. There is other evidence that the piling should have been installed before any excavation was begun. There is also evidence that when the walls of the building showed signs of cracking, the metal piling should not have been withdrawn until the movement of the soil under the foundation had ceased.

The work in the vicinity of the plaintiff’s building was started on November 25 and completed on December 3, 1960. There is evidence on behalf of the plaintiff that during the early stages of the work the plaintiff’s officers notified the defendant that because of the excavation the building was being damaged and requested that the defendant brace or shore it up. This request was ignored.

It is undisputed that as the excavation work progressed the damage to the plaintiff’s building increased. The earth beneath the front wall foundation was dislodged and large cracks developed in the wall. The damage to the wall was so extensive that it became necessary that it be torn down and replaced. Before this could be done it was necessary that the foundation be reinforced with piling. There was other serious damage to the building which need not be detailed. Suffice it to say that under the supervision of a local architect the building was repaired at an expense of approximately $25,000. There is no contention on this appeal that this amount was excessive.

Section 1301.2 of the ordinance of the city of Norfolk with respect *620 to the support of adjoining buildings and structures reads in part as follows:

“When an excavation extends more than 5 feet below the established curb grade nearest the point of excavation under consideration, the one causing the excavation to be made, if given the necessary license to enter the adjoining premises, shall provide at his own expense the underpinning and protection required by that part of the excavation which extends to a depth greater than 5 feet below the established curb grade nearest the point of excavation under consideration, whether or not the existing footings or foundations extend to the depth of 5 feet or more below curb grade; or he may shore or brace the sides of his excavation so as to prevent effectively any soil movement into his excavation. * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael Timmons v. Lilian Mutiso
Court of Appeals of Virginia, 2018
Anthony Lewis v. Commonwealth
Court of Appeals of Virginia, 2004
Morgen Industries, Inc. v. Vaughan
471 S.E.2d 489 (Supreme Court of Virginia, 1996)
Satcher v. Commonwealth
421 S.E.2d 821 (Supreme Court of Virginia, 1992)
Nichols v. Commonwealth
369 S.E.2d 218 (Court of Appeals of Virginia, 1988)
City of Fairfax v. Swart
217 S.E.2d 803 (Supreme Court of Virginia, 1975)
Hagan v. Hicks
165 S.E.2d 421 (Supreme Court of Virginia, 1969)
Avent v. Commonwealth
164 S.E.2d 655 (Supreme Court of Virginia, 1968)
Hope Windows, Inc. v. Snyder
158 S.E.2d 722 (Supreme Court of Virginia, 1968)
Jordan v. Peyton
264 F. Supp. 946 (W.D. Virginia, 1967)
Jordan v. Commonwealth
151 S.E.2d 390 (Supreme Court of Virginia, 1966)
Norfolk and Western Railway Company v. Anderson
151 S.E.2d 628 (Supreme Court of Virginia, 1966)
Waitt v. Commonwealth
148 S.E.2d 805 (Supreme Court of Virginia, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
133 S.E.2d 547, 204 Va. 616, 1963 Va. LEXIS 195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ames-webb-inc-v-commercial-laundry-co-va-1963.