Ameristar Coil Processing, LLC v. William E. Buffington Co.

2012 OK CIV APP 2, 269 P.3d 55, 2011 Okla. Civ. App. LEXIS 116, 2011 WL 7068908
CourtCourt of Civil Appeals of Oklahoma
DecidedDecember 7, 2011
DocketNo. 108,986
StatusPublished

This text of 2012 OK CIV APP 2 (Ameristar Coil Processing, LLC v. William E. Buffington Co.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ameristar Coil Processing, LLC v. William E. Buffington Co., 2012 OK CIV APP 2, 269 P.3d 55, 2011 Okla. Civ. App. LEXIS 116, 2011 WL 7068908 (Okla. Ct. App. 2011).

Opinion

JANE P. WISEMAN, Judge.

T1 William E. Buffington Company, Inc., appeals from orders of the trial court refusing its request to compel arbitration. The [57]*57issue we address on appeal is whether the trial court erred in finding that a condition precedent had not been met rendering the arbitration clause in the parties' contract unenforceable. For the reasons that follow, we reverse the trial court's decisions and remand for further proceedings.

FACTS AND PROCEDURAL HISTORY

T2 Ameristar Coil Processing, LLC, and Ameristar Fence Products, Inc. (collectively, Ameristar), filed suit against Buffington on September 7, 2009, for negligence and fraud in connection with a construction project for which Buffington was the general contractor. Ameristar alleged that during 2003, Buffing-ton acted as general contractor for the design and construction of a steel coil processing facility for Ameristar. Ameristar claims that defects in the facility's foundation required a halt in production in late 2008. The facility's foundation was excavated in late December 2008, and Ameristar discovered the foundation "failed to meet the specifications submitted by Buffington to the County of Tulsa for a building permit." The foundation was further excavated in September 2009 and additional defects were discovered.

13 Buffington filed a motion to dismiss asserting the statute of limitations had expired, Ameristar had agreed to arbitrate all claims arising out of the contract between the parties, and Ameristar failed to plead its fraud claim with particularity. Buffington asserted the contract was signed on March 5, 2003, and the facility was completed by the end of 2003. Buffington claimed that Amer-istar noticed problems with the floor slab and equipment foundations in 2006 but failed to bring suit for fraud or negligence within the two-year. statute of limitations for these claims which are now time-barred.

T4 Ameristar filed a "Motion to Strike Defendant's Motion to Dismiss, or, in the Alternative, to Convert to a Motion for Partial Summary Judgment and Take Limited Discovery Pursuant to District Court Rule 13(d)" Ameristar claimed that although Buffington called its motion a motion to dismiss, it attached to the motion three documents outside the pleadings. In response, Buffington again asserted that the petition should be dismissed, or in the alternative, the court should summarily decide whether an enforceable agreement to arbitrate exists and compel arbitration before conducting discovery.

T5 The trial court converted Buffington's motion to dismiss to a motion for summary judgment and granted Ameristar 60 days to conduct limited discovery and to respond to Buffington's motion. The trial court later denied Buffington's motion for summary judgment on the ground that the arbitration clause in the contract between the parties was unenforceable. The day after the trial court's decision, Buffington filed a reply brief in support of its motion for summary judgment. Three days later, Buffington filed a motion to reconsider in which it asserted that its reply brief was its "first and only brief filed after limited discovery was conducted." It claimed its reply brief was its opening brief after discovery and complained the trial court entered an order without considering its brief or conducting a hearing. Ameristar asked the trial court to strike Buffington's reply brief.

T6 The trial court denied Ameristar's motion to strike finding that Buffington "had not had an opportunity to brief the issues raised after the extended discover[y] period." The court granted Buffington's motion to reconsider, vacated the ruling denying Buff-ington's motion to dismiss, which the court had converted to a motion for summary judgment, and gave the parties 20 days to supplement their briefs on the issue of arbitration.

T7 Buffington filed a supplemental brief and again asserted Ameristar agreed to submit its dispute to arbitration. Buffington cited subparagraph 4.6.2 of the parties' contract, which provides:

Claims not resolved by mediation shall be decided by arbitration which, unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect. The demand for arbitration shall be filed in writing with the other party to the Contract and with the American Arbitration [58]*58Association and a copy shall be filed with the Architect.

Buffington claimed Ameristar erroneously relied on subparagraph 4.6.1 which provides:

Any Claim arising out of or related to the Contract, except Claims relating to aesthetic effect and except those waived as provided for in Subparagraphs 4.3.10, 9.10.4, and 9.10.5, shall, after decision by the Architect or 30 days after submission of the Claim to the Architect, be subject to arbitration. Prior to arbitration, the parties shall endeavor to resolve disputes by mediation in accordance with the provisions of Paragraph 4.5.

Buffington asserted that subparagraph 4.6.1 "deals with timing of the arbitration, not the fundamental question of whether claims are subject to arbitration." (Emphasis added.) Section 4.4.1 provides in part: "Claims including those alleging an error or omission by the Architect ... shall be referred initially to the Architect for decision. An initial decision by the Architect shall be required as a condition precedent to mediation, arbitration or litigation of all Claims...." Buffing ton claimed subparagraph 4.4.1 contemplates that arbitration will be the final remedy if there is no decision by the architect. Buff-ington asserted that although the contract gives the architect an opportunity to consider a claim, the ultimate resolution of a claim must be obtained through arbitration.

T8 Ameristar responded that because there was no architect on the project, the condition precedent to arbitration cannot be met and the arbitration clause is therefore unenforceable.

T9 The trial court denied Buffington's motion for summary judgment and agreed with Ameristar, finding "the arbitration clause in the contract contained a condition precedent that was not met and is therefore unenforceable." Buffington filed another motion to reconsider, which the trial court denied.

"I 10 Buffington appeals.

STANDARD OF REVIEW

111 Although the orders from which Buffington appeals include an order denying its motion for summary judgment and an order denying its motion to reconsider, this is not an appeal from summary proceedings. The effect of the trial court's rulings is a denial of Buffington's attempt to compel arbitration, and the appeal is interlocutory in nature. Okla. Sup.Ct. R. 1.600), 12 O.S. Supp.2010, ch. 15, app. 1;1 12 0.8.2001 § 1879. We review de novo the "question as to the existence of valid enforceable agreements to arbitrate." Oklahoma Oncology & Hematology P.C. v. U.S. Oncology, Inc., 2007 OK 12, ¶ 19, 160 P.83d 986, 944.

ANALYSIS

12 The title of the contract used by the parties was "Standard Form of Agreement Between Owner and Contractor." The contract was the 1997 version of the American Institute of Architects (AIA) owner-contractor agreement. The agreement states the owner is Eddy Gibbs of Ameristar Fence, the contractor is Buffington Co., Inc., the project is Ameristar Steel Warehouse, and the architect is "None. Buffington Co., Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bivins v. State Ex Rel. Oklahoma Memorial Hospital
1996 OK 5 (Supreme Court of Oklahoma, 1996)
Tillman Park, LLC v. Dabbs-Williams General Contractors, LLC
679 S.E.2d 67 (Court of Appeals of Georgia, 2009)
Shaffer v. Jeffery
1996 OK 47 (Supreme Court of Oklahoma, 1996)
Board of Governors of the Registered Dentists v. Melton
1967 OK 113 (Supreme Court of Oklahoma, 1967)
Auchter Co. v. Zagloul
949 So. 2d 1189 (District Court of Appeal of Florida, 2007)
Rogers v. Dell Computer Corp.
2005 OK 51 (Supreme Court of Oklahoma, 2005)
Dunbar Engineering Corp. v. Rhinosystems, Inc.
2010 OK CIV APP 49 (Court of Civil Appeals of Oklahoma, 2010)
Oklahoma Oncology & Hematology P.C. v. US Oncology, Inc.
2007 OK 12 (Supreme Court of Oklahoma, 2007)
Hai v. Baptist Healthcare of Oklahoma, Inc.
2010 OK CIV APP 3 (Court of Civil Appeals of Oklahoma, 2009)
Rogers v. Dell Computer Corp.
2005 OK 51 (Supreme Court of Oklahoma, 2005)
Bank of the Wichitas v. Ledford
2006 OK 73 (Supreme Court of Oklahoma, 2006)
Mellor v. Wasatch Crest Mutual Insurance
2012 UT 24 (Utah Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2012 OK CIV APP 2, 269 P.3d 55, 2011 Okla. Civ. App. LEXIS 116, 2011 WL 7068908, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ameristar-coil-processing-llc-v-william-e-buffington-co-oklacivapp-2011.