American Transmission Co. v. Dane County

2009 WI App 126, 772 N.W.2d 731, 321 Wis. 2d 138, 2009 Wisc. App. LEXIS 572
CourtCourt of Appeals of Wisconsin
DecidedJuly 23, 2009
Docket2008AP2604
StatusPublished
Cited by6 cases

This text of 2009 WI App 126 (American Transmission Co. v. Dane County) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Transmission Co. v. Dane County, 2009 WI App 126, 772 N.W.2d 731, 321 Wis. 2d 138, 2009 Wisc. App. LEXIS 572 (Wis. Ct. App. 2009).

Opinion

VERGERONT, J.

¶ 1. This action for a declaratory judgment arises out of a dispute between American Transmission Co., LLC, and Dane County over whether the construction of three transmission lines in Dane County are subject to county ordinance requirements for various permits. The construction projects were each authorized by the Wisconsin Public Service Commission (PSC) through the issuance of a certificate of public convenience and necessity. The circuit court agreed with American Transmission that Dane County does not have the authority to enforce any ordinance with respect to matters that were or could have been addressed by the PSC in the proceedings on the certificates. Dane County appeals, contending that the circuit court erred in its construction and application of Wis. Stat. § 196.491(3)(i) (2007-08), 1 which provides: "If installation or utilization of a facility for which a certificate of convenience and necessity has been granted is precluded or inhibited by a local ordinance, the installation and utilization of the facility may nevertheless proceed." Id.

¶ 2. We conclude that in Wis. Stat. § 196.491(3)(i) the legislature has expressly withdrawn the power of municipalities to act, once the PSC has issued a certificate of public convenience and necessity, on any matter that the PSC has addressed or could have addressed in that administrative proceeding. We also conclude that *141 the local power that is withdrawn by the statute includes requiring the application for local permits of the type that are in dispute in this case. Accordingly, we affirm the circuit court.

BACKGROUND

¶ 3. American Transmission proposed to build three separate high-voltage transmission lines within Dane County. Wisconsin Stat. § 196.491(3)(a) and (l)(e) prohibit a person from beginning construction on a high voltage transmission line unless the PSC has issued a certificate of public convenience and necessity. 2 American Transmission applied for a certificate of public convenience and necessity for each of the projects and the PSC issued an order for each project granting a certificate, with the first order issued in July 2007 and the third issued in June 2008.

¶ 4. American Transmission involved Dane County officials in certain aspects of the planning of these projects, particularly the two that were wholly within Dane County and involved new rights-of-way. After the first of the three certificates was issued, Dane County took the position that construction could not begin on that project until American Transmission obtained a shoreland erosion control permit under Dane County, Wis., Ordinances § 11.05 (2007) ("Shoreland Erosion Control") and a wetland zoning permit under Dane County, Wis., Ordinances § 11.08(4) (2007) ("Uses . . . Allowed in Shoreland-Wetland . . . Districts Subject to . . . Zoning (Land Use) Permit"). With respect to the second project, Dane County's position was that a *142 general erosion control permit under Dane County, Wis., Ordinances ch. 14 (2009) (". . . Erosion Control and Stormwater Management") was necessary. American Transmission did not apply for these permits because of its view that the county permit process would "inhibit" the construction of the projects within the meaning of Wis. Stat. § 196.491(3)(i) and Dane County therefore did not have the authority to require these permits.

¶ 5. As soon as the PSC issued a certificate of public convenience and necessity for the third project, American Transmission filed this action seeking a judgment declaring that Dane County does not have the authority to require permits relating to the construction of projects for which the PSC has issued a certificate of public convenience and necessity under Wis. Stat. § 196.491(3). The circuit court denied Dane County's motion for summary judgment and entered summary judgment in favor of American Transmission. The court concluded that § 196.491(3)(i) preempts a local ordinance where the PSC or the Department of Natural Resources (DNR), acting in partnership with the PSC, 3 has the authority to consider the same subject matter as that of the ordinance in issuing a certificate of public convenience and necessity. Accordingly, the court entered a judgment declaring that Dane County does not have the authority to enforce or apply any ordinance with respect to matters that were addressed or could have been addressed in any adminis *143 trative proceeding conducted either by the PSC or the DNR concerning American Transmission's applications for certificates of public convenience and necessity.

DISCUSSION

[13

¶ 6. On appeal Dane County challenges the circuit court's construction of Wis. Stat. § 196.491(3)(i), asserting that the plain language of the statute does not prevent local regulation unless it "blocks" a project. Dane County contends that simply requiring American Transmission to apply for permits does not have that effect. According to Dane County, the statute does not expressly preempt local regulation and the alternative standards for establishing preemption are not met.

¶ 7. American Transmission responds that Wis. Stat. § 196.491(3)(i) plainly and expressly preempts the local ordinances Dane County seeks to enforce. According to American Transmission, requiring American Transmission to apply for permits under the Dane County ordinances on shoreland erosion control, wetland zoning, and general erosion control would plainly "inhibit" the construction of the three projects for which the PSC has issued certificates of public convenience and necessity. 4

¶ 8. We review de novo the grant or denial of summary judgment, employing the same methodology as the circuit court. Green Spring Farms v. Kersten, 136 Wis. 2d 304, 314-15, 401 N.W.2d 816 (1987). Where, as *144 here, there are no material factual disputes, the issue is which party is entitled to judgment as a matter of law. See Wis. Stat. § 802.08(2). In this case the answer to that question requires that we interpret Wis. Stat. § 196.491(3)(i) in the context of the preemption doctrine. 5

¶ 9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Savanah R. Thom v. 1st Auto & Casualty Insurance Company
2021 WI App 33 (Court of Appeals of Wisconsin, 2021)
Town of Grant v. Portage County
2017 WI App 69 (Court of Appeals of Wisconsin, 2017)
LIR Investments LLC v. Stokelbusch
2017 WI App 63 (Court of Appeals of Wisconsin, 2017)
State v. Stanley
2014 WI App 89 (Court of Appeals of Wisconsin, 2014)
Milwaukee Police Ass'n v. Flynn
2011 WI App 112 (Court of Appeals of Wisconsin, 2011)
Adams v. State Livestock Facilities Siting Review Board
2010 WI App 88 (Court of Appeals of Wisconsin, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2009 WI App 126, 772 N.W.2d 731, 321 Wis. 2d 138, 2009 Wisc. App. LEXIS 572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-transmission-co-v-dane-county-wisctapp-2009.