American Steel Co. of Cuba v. Transmarine Corp.

36 F.2d 246, 1929 U.S. Dist. LEXIS 1665
CourtDistrict Court, S.D. New York
DecidedSeptember 6, 1929
StatusPublished
Cited by1 cases

This text of 36 F.2d 246 (American Steel Co. of Cuba v. Transmarine Corp.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Steel Co. of Cuba v. Transmarine Corp., 36 F.2d 246, 1929 U.S. Dist. LEXIS 1665 (S.D.N.Y. 1929).

Opinion

FRANK J. COLEMAN, District Judge.

The principal question presented is whether the carrier is legally responsible for a long delay which occurred in certain deliveries of steel in Havana during the period of intense congestion, 1920-21, which has already been considered by the federal courts. The Poznan (D. C.) 276 F. 418; Transmarine Corp. v. Levitt (C. C. A.) 25 F.(2d) 275; see also Koppel Industrial C. & E. Co. v. Baltimore S. S. Co. (D. C.) 287 F. 203, affirmed (C. C. A.) 299 F. 158. The respondent Transmarine Corporation was the carrier and was a subsidiary of the respondent Submarine Boat Corporation, but it is not important to go into the details of their relationship, because for the purposes of this decision it will be assumed that the two corporations were practically one.

. Libelant was a large manufacturer and dealer in steel produets in Havana and purchased 10,500 tons of steel from the Consolidated Steel Company in this country under e. i. f. contracts which required that 7,000" tons of the purchase would be placed on board ship not later than June 30, 1920, and the balance before January 1, 1921. The Consolidated Steel Company found difficulty in procuring a carrier for the steel on account of the congestion in the port of Havana, and finally in April, 1920, made an arrangement with the respondent at rates lower than those prevailing, well knowing that the steamship service to Havana was a new enterprise to the respondent and that the latter had no special facilities there. The arrangement called for delivery by respondent “in accordance with the custom of the port” at libelant’s wharf in Havana, which had not sufficient depth of water to permit a steamship to berth, and it was understood that lighterage would be necessary.

It was further understood between the respondent and the Consolidated that the steel was not to be shipped in entire cargoes, but was to form a part of general cargoes carried by respondent’s vessels. No time was specified for delivery, except that the steel was “to be promptly discharged and delivered” on arrival at Havana, and that the parties “believed” there would be about three sailings a month. The parties both knew the conditions prevailing in that port and must be assumed to have contracted with them in view.

Thereafter the Consolidated forwarded approximately 8,075 tons of steel from its plants in this country to respondent’s dock in Port Newark for shipment to libelant in Havana. These deliveries to respondent commenced in June, 1920, and continued until October, 1920. Before the steel was loaded on the boats, respondent issued bills of lading to the Consolidated, which was naméd as consignee, and the Consolidated, after indorsement, forwarded them with other shipping documents to libelant. Upon the receipt of each bill of lading libelant returned to the Consolidated a trade acceptance for the purchase price of the steel involved, which has since been paid.

The claim for damages for delay in delivery is based upon the time that elapsed between the dates of the various bills of lading and the dates of the deliveries in Havana. These periods varied from 114 to 285 days, and the principal question presented in the case is whether reasonable diligence on respondent’s part could have shortened that time. There were 173 bills of lading altogether, and they were dated from June 3, 1920, to October 16, 1920. The deliveries in Havana commenced October 30, 1920, and ended November 4, 1921. The shipments were made by nine steamers which arrived in Havana on various' dates from August 18, 1920, to January 6, 1921, and were delayed in unloading for various periods from 33 days to 170 days, calculating from the dates of arrival to the dates of the final deliveries from the respective vessels.

The underlying cause for the delay was the intense congestion in the port of Havana which . had commenced before respondent agreed to earry the steel and continued throughout the period under consideration. [248]*248Every available warehouse and shelter for goods was filled, with the result that general merchandise could not be unloaded from the vessels. The steel was necessarily placed in the lower parts of the holds of respondent’s ships, and consequently could not be unloaded until the rest of the cargo was removed. Furthermore, since Havana had very few piers and wharves at which steamships could dock, it was, generally speaking, a lighterage port; and the congestion exhausted the supply of available lighters. Also, labor conditions were greatly demoralized, and it was extremely difficult to get an adequate supply of stevedores.

Respondent took some special measures to obviate these conditions, which were not specifically required by its agreement with the Consolidated nor by the bills of lading. One of the vessels was loaded entirely with steel at a considerably increased risk to it. To partially overcome the shortage of lighters, respondent purchased seven of them in the United States and sent them to Havana, though there was an unfortunate delay in their utilization due to a variety of causes for which respondent was not at fault. Furthermore, respondent supplied from the United States a stiff-legged derrick for use on libelant’s wharf in the unloading of the lighters. It also, late in the period, secured the preferential use of a wharf at a considerable outlay of money. In addition, respondent’s officers and managers made trips to Havana to study conditions and to try to devise a solution.

Respondent’s duty to libelant was founded upon the bills of lading. Though the original agreement between the Consolidated and the respondent called for “prompt” discharge and delivery “in accordance with the custom of the port” and possibly for about three sailings a month, that was not made by the Consolidated as agent for the libelant, and the latter was not a party to it. In fact, it included some steel that was not destined to libelant at all. Furthermore, it was made with full knowledge of the conditions prevailing in Havana and of respondent’s facilities, and at lower than the prevailing rates. If it placed an additional burden on respondent, libelant cannot avail itself of it, because the only contractual relations which libelant had with respondent were established 'by the acceptance of the bills of lading from the Consolidated Steel Company.

Libelant contends that there was a deviation which abrogated the bills of lading and deprived respondent of the protection of such special clauses as they contained.® This deviation is predicated upon the delay in discharging at Havana and also a delay in commencing certain of the trips from the United States after the vessels had been loaded. It is undisputed that several of the ships were detained in New York Harbor for weeks and even months after they were loaded because of the fact that they would otherwise have had to spend that period in Havana awaiting discharge, with greater damage to the general merchandise. It is plain that the ultimate delivery of the steel was not deferred one day because of the detention of the boats at New York. The bills of lading provided for such detention, and under all the circumstances I am of the opinion that there was no deviation either because of it or because of the delay in discharge.

Whether the bills of lading remained in full force or not, the extent of respondent’s obligation to libelant was to use reasonable efforts to make an early delivery with such facilities as the port of Havana afforded. The shipper knew respondent had no special facilities and there was ho term in the contract or in the bills of lading which required the acquisition of them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Plow City
23 F. Supp. 548 (E.D. Pennsylvania, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
36 F.2d 246, 1929 U.S. Dist. LEXIS 1665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-steel-co-of-cuba-v-transmarine-corp-nysd-1929.