American Senior Development, L.L.C. v. Parkside of Collierville, L.L.C.

102 F. App'x 890
CourtCourt of Appeals for the Sixth Circuit
DecidedJune 9, 2004
DocketNo. 02-6346
StatusPublished
Cited by1 cases

This text of 102 F. App'x 890 (American Senior Development, L.L.C. v. Parkside of Collierville, L.L.C.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Senior Development, L.L.C. v. Parkside of Collierville, L.L.C., 102 F. App'x 890 (6th Cir. 2004).

Opinions

RUSSELL, District Judge.

American Senior Development (“ASD”), the Appellant, and Parkside of Collierville,1 the Appellee, entered into a Development Management Agreement on August 13, 1998. This contract governed the design, development, construction, and management of a senior citizens’ housing development outside Memphis, Tennessee. As a part of this development, ASD purchased and transferred to Parkside approximately 14 acres of undeveloped land.

Under the contract ASD was meant to receive 6% of the development’s budgeted cost in exchange for its service as a project manager. Before construction began, however. Parkside sold the property to another developer. ASD sued for damages under the contract, including the balance of the 6% development fee. The United States District Court for the Western District of Tennessee dismissed ASD’s case pursuant to Federal Rule of Civil Procedure 12(b)(6).

For the reasons given below, we affirm.

I.

The following background is taken from the district court’s opinion and is substantially uncontested:

In 1997, ASD, through its president Carlton A. Raff, began negotiating with Parkside Senior Services to acquire, construct, and develop a senior housing planned development project in Collier-ville, Tennessee, to be known as Wynfield Village. In furtherance of this plan, ASD entered into an agreement to acquire approximately 14.058 acre of unimproved real property located in Collierville, Tennessee (the “subject property”). In addition, ASD negotiated with the Town of Collierville to obtain approval of a planned unit development (“PUD”) on this property.
On August 13, 1998, ASD and Park-side of Collierville entered into a development management agreement (“the Agreement”), which governed the development and construction of the PUD on the subject property acquired by ASD. Section 1.1 of the Agreement states that ASD assigns its rights to purchase the property to Parkside of Collierville. Section 2.1 provides that Parkside of Collierville retains ASD “to provide supervisory and development management services for the Project, including without limitation, in connection with the design, budgeting, development, permitting and construction of the Project.”
Section 4.2, which governs the termination of the contract, states that “this Development Agreement shall terminate, solely at [Parkside’s] election in its sole discretion, upon ... (II) the sale or other transfer of all or substantially all of the Property. Such election to terminate this Development Agreement shall be made by written notice from [Park-side] to [ASD].” Section 7.2 of the Agreement, which identifies “Event[s] of Default by [Parkside],” provides in relevant part that:
Upon such an event of Default by [Parkside] or in the event that [Park-side] elects, at its option, to terminate this Development Agreement under Section 4.2(i) or Section 4.2(ii).[ASD] shall be entitled to all sums due and owing to [ASD] hereunder as of the date of the occurrence of the Event of Default, including, without limitation payment to [ASD] of the approved [893]*893Pre-Development Costs incurred to the date of termination and the remainder of the entire Development Fee, as set forth in Section 6.2.
Section 20 of the agreement contains an “Anti-Competition Covenant.” which bars ASD from acquiring an interest in any property within a ten-mile radius which would be in competition with the project for a period of two years after the completion date. Section 26 states that “time is of the essence of this Development Agreement.”
ASD states that it has performed all of its duties and obligations under the Agreement. Specifically, ASD obtained bids and commitments to build the project. As of January 27, 2000, ASD developed a budget in the amount of $16,129,593.00 for the Wynfield Village Project, which it conveyed to the defendants. However. Parkside of Collier-ville has not begun construction of the project.

Parkside has since sold the 14-acre property to another developer planning to build single-family homes. Parkside has not yet provided any letter or other notice to ASD notifying the latter that the contract is terminated.

The district court concluded “[u]pon examination of the language used in section 4.2(ii), the court agrees with defendants that the provision clearly and unambiguously states that termination does not occur automatically because of Parkside’s sale or transfer of the subject property, but rather requires that Parkside actually elect to terminate the agreement in addition to such a sale or transfer.”

Under section 7.2 of the contract, if Parkside terminated the agreement then ASD would be due the full 6% of development costs, or approximately $967,776.00. ASD had already received $267,400.00 in incremental payments by the time it sued, and seeks the remainder, or “balance due.” of $700,376.00. ASD also seeks reimbursement for certain other items under the terms of the agreement.

Besides the claims relating to the development, ASD sought in its complaint a declaration from the district court that the anti-competition covenant—section 20 of the contract—was void, and also damages for various other projects in Tennessee, Florida,-and South Carolina. The district court dismissed ASD’s request for declaratory relief because ASD had not shown that it has standing because the anti-competition covenant only becomes effective upon the project’s completion. Given that neither party expects the project ever to be completed, the covenant will never be effective. The district court allowed ASD’s claims arising from the other projects to proceed, but ASD voluntarily dismissed them so that it could pursue this appeal.

II.

“This court reviews de novo a district court’s dismissal of a complaint pursuant to Federal Rule of Civil Procedure 12(b)(6). To survive a motion to dismiss, the plaintiffs complaint must allege facts, which if proved, would entitle the claimant to relief. The reviewing court must construe the complaint in a light most favorable to the plaintiff, accept all of the factual allegations as true and determine whether the plaintiff can prove no set of facts in support of his claims that would entitle him to relief.” Arrow v. Federal Reserve Bank of St. Louis, 358 F.3d 392, 393 (6th Cir.2004) (citations omitted).

Tennessee’s law of contracts governs the substantive law of this case, and its courts apply standard rules of contract interpretation:

[894]*894The cardinal rule in the construction of contracts is to ascertain the intent of the parties. If the contract is plain and unambiguous, the meaning thereof is a question of law, and it is the Court’s function to interpret the contract as written according to its plain terms. The language used in a contract must be taken and understood in its plain, ordinary, and popular sense. In construing contracts, the words expressing the parties’ intentions should be given the usual, natural, and ordinary meaning.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
102 F. App'x 890, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-senior-development-llc-v-parkside-of-collierville-llc-ca6-2004.