American Plate Glass Co. v. Struthers-Wells Co.

201 F. 6, 119 C.C.A. 344, 1912 U.S. App. LEXIS 1987
CourtCourt of Appeals for the Third Circuit
DecidedNovember 21, 1912
DocketNo. 1,522
StatusPublished
Cited by7 cases

This text of 201 F. 6 (American Plate Glass Co. v. Struthers-Wells Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Plate Glass Co. v. Struthers-Wells Co., 201 F. 6, 119 C.C.A. 344, 1912 U.S. App. LEXIS 1987 (3d Cir. 1912).

Opinion

GRAY, Circuit Judge.

The writ of error in this case brings up for review a judgment recovered in the court below by the StruthersWells Company against the American Plate Glass Company, for $48,-461.

The statement of claim sets forth a contract which consisted of a written proposal made by the plaintiff to the defendant under date of March 9, 1906, and accepted by the defendant March 24th of that [7]*7year. By this contract, the plaintiff undertook to manufacture and supply to the defendant four 600 horse power Warren gas engines, having 600 actual brake horse power, to be 11 feet in height, 7 feet 6 inches wide, 26 feet long, and to weigh approximately 150,000 pounds. The contract also stipulated in other respects, at great length, the details of the structure to be embodied in the engines contracted for. It was provided that one engine should be shipped 5 months after the date of the contract, and one engine each succeeding 20 days thereafter until the order should be completed, subject, however, to delays due to strikes, fires, accidents, or to any causes beyond its (plaintiff’s) control. There were several guaranties contained in the contract, among which viere the following:

“We guarantee each engine to be capable of delivering continuously 600 brake H. P. at a speed of 180 It. P. M. and one operating in natural gas containing not less than 1,000 B. T. U. per cu. ft. and carrying approximately full load, we guarantee the engines will not consume to exceed 12 eu. ft. of natural gas per brake horse power per houi*.
“We also guarantee that each engine will be capable of operating for a short time with a load 10% above its normal rating, and that when driven 25-cycle alternating current generators in multiple, the engines will be capable of running in parallel with a variation in angular velocity not exceeding 2y2 electrical degrees.”

There were also guaranties for workmanship, material, etc. Plaintiff also stipulated that after engines had arrived at destination, they would furnish a rigger to superintend the work of placing the engines on foundations; also the services of a capable erecting engineer to supervise the erection, piping and starting of each engine, defendant to prepare the necessary foundations in accordance with blue prints furnished by plaintiff. The contract then provided for tests, as follows:

“After all of the engines have been completely installed and thoroughly prepared for operation, as determined by us, we are to have, if necessary, 60 days for trial runs, tests, and any other work that we consider necessary to put the engines in such condition as will enable .them to fulfill contract guaranties hereinbefore mentioned.
“During the first 30 days of the time specified, customers are to furnish, us, free of all expenses, the necessary water, gas, and oil that we require for operating the engines. If it should be necessary for us to operate the engines for trial runs, tests, etc., during the second 30 days of the time specified, we agree to pay customers Sc. per thousand cubic feet for all natural gas required by us; also agree to reimburse them for their actual cost of water and oil furnished by them to us for operating the engines.
“As soon as possible after engines have been installed and pronounced ready for operation by us, there is to be an official test, participated in by both customers and engine builders, and if this test should prove that all contract guaranties have been fully met, the entire installation is to be accepted by you.
“If each and every one of the contract guaranties hereinbefore mentioned are not fully met, we are to be allowed the opportunity of making other official test or tests at any time that we may desire during the 60 day trial period, furnishing customers information, at least two days in advance, of our intention to make such tests; and if any of these tests show that the engines are capable of fulfilling contract guaranties, engines are to be accepted. If, however, we should require more than the 60 days above specified for test purposes, all time over and above the 60 days prescribed is to be paid for by us, and we hereby agree to pay for same at the rate of $200 per day, provided [8]*8'customers’ plant is' fully equipped in every detail and ready for operation, but cannot be operated solely by the failure of engines to operate in accordance with, contract guaranties.
“The duration of this extended time of test for which we agree to indemnify customers at the rate specified, may be terminated at any time by us by giving written notice to customers that we wish to abandon the installation without securing further time for testing. And in consideration of our being relieved of all responsibility in connection with the contract, excepting the payment of $200 per day for the extended time of test period consumed by us, we will allow you the privilege of retaining the engines in your plant for a period of time sufficient to enable you to replace any or all of the engines of other make, it being understood that the engines in such event are not to remain in your plant for a period of time longer than six months from date of our giving you notice that we wish to terminate the trial period. And during the period of time that the engines are being used by you in accordance with this agreement, we will furnish to you, at our expense, a competent engineer to supervise their care and operation.”

The price of the engines, as described, was stated to be $68,000; “two-thirds of purchase price on completion of satisfactory test, establishing the fulfillment of all contract guaranties; balance 30 days thereafter.” The statement of claim then proceeds to allege performance by'the plaintiff of its contract, by the shipping and installation of said engines, fittings and fixtures, beginning on or about the month of March, 1907, and that the same were by the defendant erected on foundations on its premises and connected by defendant with its machinery, and thereafter used and employed by defendant in connection therewith in its business; “that thereafter, about the month of October, 1908, tests of the said engines were made, as provided in the contract, which showed that the engines complied with the terms of the guaranties, but the test for parallel operations on one of said engines not being completed on account of a grounded igniter, the plaintiff requested the opportunity to complete the same and tendered further performance of the contract, but the said defendant wrongfully and willfully forbade and prevented the plaintiff from further performance and discharged the plaintiff from so doing-, and defendant did not and would not' perform said agreement on its part to.be performed, and especially prevented the plaintiff from completing said tests and from further testing and from further performing said contract;” but that defendant nevertheless continued to use the said gas engine and is now using the same, etc.; “that the defendant, although duly requested, has refused and neglected to pay the said sum of $68,000, or any part thereof, except the sum of $25,-000, paid in December, 1907, and in January and March, 1908,” and suit is brought for the balance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
201 F. 6, 119 C.C.A. 344, 1912 U.S. App. LEXIS 1987, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-plate-glass-co-v-struthers-wells-co-ca3-1912.