This text of 271 N.W. 828 (American Mutual Liability Insurance v. Chain Belt Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Mutual Liability Insurance v. Chain Belt Co., 271 N.W. 828, 224 Wis. 155, 1937 Wisc. LEXIS 85 (Wis. 1937).

Opinion

Nelson, J.

Did the trial court err in granting the defendant’s motion for judgment in its favor notwithstanding the verdict? On March 2, 1934,’H. P. Jensen, a contractor, was engaged in constructing a concrete sewer for the Metropolitan Sewerage District of Green Bay. American Mutual [158]*158Liability Insurance Company of Boston carried his compensation risk. The plaintiff, Kuske, was employed by Jensen. While performing services on that day he was seriously injured. He thereafter applied for and was awarded compensation, in addition to medical and hospital expenses, amounting to more than $9,000. In this action recovery is sought from the defendant, as a third party who, the plaintiffs assert, was responsible for Kuske’s injuries, and therefore liable to the plaintiffs under the provisions of sec. 102.29, Stats.

The sewer under construction was substantially horizontal and was about forty feet below the surface of the ground. From a shaft which had been sunk to the required depth, a tunnel was excavated. The tunnel was about six feet in diameter and six hundred feet long. Prior to the time that defendant’s “pumpcrete” machine was leased to Jensen and put into operation on the job, the work in the tunnel was largely done by hand labor. Circular forms were set up in the far end of the tunnel, concrete shoveled upon and around them, and tamped into the space between the forms and the surface of the tunnel. The concrete was piped from the surface to the bottom of the shaft, where it was loaded onto small cars and pushed along the tunnel to the place where required.

For about two years prior to March, 1934, the defendant was the exclusive manufacturer of “pumpcrete” machines. Those machines were constructed so as to receive concrete from a mixer and to pump it through a pipe to the place where it was to be used. A “pumpcrete” machine, when successfully operated, saved considerable labor. On or about February 27, 1934, the defendant leased one of its machines to Jensen, under a written lease. The machine was sent to Green Bay accompanied by Andrew Dickson and Floyd Beach, two of the defendant’s expert operators. The lease specified the sums that were to be paid by Jensen to the de[159]*159fendant for the services and expenses of their expert engineering representatives, “who shall be in charge of operation and care of leased property, with necessary assistants provided by lessee, and who shall be in lessor’s employ and under lessee’s direction.” On March 1st, the day before Kuske was injured, a “go-devil” was forced through the pipe with water ahead of it for the purpose of cleaning out the pipe. The “go-devil” was a dumbbell or spool-shaped contrivance constructed of steel and rubber which fitted tightly into the conveyor pipe. It was used in connection with compressed air to force sluggish or clogged concrete through the pipe. The “pumperete” machine was first put into operation on March 2, 1934. Difficulty arose during the afternoon as a result of the concrete’s hardening and clogging in the pipe. When that happened, several sections of the conveyor pipe were taken down by Jensen’s employees and the concrete shaken or pushed out by hand. The taking down of several sections of the pipe, however, did not relieve the situation and it was decided to send a “go-devil” through the conveyor pipe to force the concrete out. A “go-devil” was accordingly inserted in the pipe and air pressure applied. That “go-devil,” however, stuck in the pipe. It was then decided to insert another “go-devil” because the first one probably was permitting the air to get by it. An air compressing machine was located on the surface near to the “pumperete” machine. A heavy piece of steel, referred to in the testimony as a “deflector,” was attached to the end of the conveyor pipe, the purpose of which was to deflect the concrete downward and also to stop the “go-devil” when it reached the end of the pipe. After the second “go-devil” was inserted, and when a sufficient pressure had been attained, the “go-devils” were forced along the pipe, expelling the concrete ahead of them. When the “go-devils,” or one of them, was expelled it struck the steel deflector with such [160]*160force as to shatter it and cause broken fragments thereof to be hurled along the tunnel a distance of thirty-five to forty feet to the place where Kuske and one Frederickson were standing at that time. A fragment of the deflector struck Kuske’s right arm, severely injuring it and permanently disabling it. It was conceded by all parties that forcing a “go-devil” through the pipe was a dangerous operation to those who were in the tunnel in front of or ahead of the end of the pipe. No one connected with the defendant had ever known of a deflector’s being shattered by a “go-devil.” However, Mr. Viall, the defendant’s vice-president in charge of its construction equipment division, and Mr. Dickson, one of its experts in charge of the “pumpcrete” machine on the job, conceded the possibility of such a thing’s happening.

The question principally litigated at the trial was whether adequate and sufficient warning had been given to Kuske as to the danger involved in forcing a “go-devil” through the concrete conveyor pipe. As before stated, the jury found that no adequate and sufficient warning was given to the men working at the end of the pipe. The testimony is almost overwhelming to the effect that the men employed in the tunnel were emphatically warned to keep away from the end or ahead of the pipe while the “go-devil” was being forced through it. Dickson testified that he warned the men at the time it was attempted to force the first “go-devil” through the pipe. Russell, Jensen’s superintendent, testified that he gave a warning. Jensen himself, who was also on the job and watching the operation, testified that he gave a warning to the men and that he himself warned Kuske. Other employees and supervisors who were in the tunnel testified that a warning was given. Kuske, however, testified that no warning whatsoever was given him, that he had no knowledge that a “go-devil” was about to be forced through the pipe or that it was dangerous for him to be where he was. The jury found Kuske guilty of negligence which con[161]*161tributed to his injury to the extent of thirty per cent. Those findings are without support in the evidence unless the jury believed that Kuske’s testimony with respect to the warning was untrue.

The defendant earnestly contends that there is no credible evidence that sustains the finding of the jury that no adequate or sufficient warning was given. We need not discuss that contention, since in our opinion no duty rested upon the defendant to warn the employees of Jensen, after it had fully and completely warned Jensen as to the dangers involved in the operation of forcing a “go-devil” through the pipe. That Jensen, the employer, was fully warned and understood the dangers involved, there can be no doubt. Jensen’s superintendent, Russell, was also warned as to the dangers involved in the operation, although he was under the impression that the danger zone did not extend beyond twenty-five or thirty feet from the end of the pipe.

At the time the first “go-devil” stuck in the pipe, Dickson was in the tunnel overseeing the operation. Shortly thereafter he and Jensen went to the surface where Dickson conferred with his associate, Beach, as to the advisability of forcing a second “go-devil” through the pipe. After it was decided to force another “go-devil” through the pipe, Jensen returned to the tunnel, but Dickson remained at the surface.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lane v. Bethlehem Steel Corp.
667 A.2d 962 (Court of Special Appeals of Maryland, 1995)
Aetna Casualty & Surety Co. v. Becker Construction Co.
284 N.W.2d 621 (Wisconsin Supreme Court, 1979)
Price v. Seidler
408 S.W.2d 815 (Supreme Court of Missouri, 1966)
Crawford Johnson & Co. v. Duffner
189 So. 2d 474 (Supreme Court of Alabama, 1966)
Hunt v. Laclede Gas Company
406 S.W.2d 33 (Supreme Court of Missouri, 1966)
Gulf Oil Corporation v. Kenneth C. Bivins
276 F.2d 753 (Fifth Circuit, 1960)
Witherspoon v. Haft
157 Ohio St. (N.S.) 474 (Ohio Supreme Court, 1952)
Blankenship v. St. Joseph Fuel Oil & Manufacturing Co.
232 S.W.2d 954 (Supreme Court of Missouri, 1950)
Tiemann v. May
292 N.W. 612 (Wisconsin Supreme Court, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
271 N.W. 828, 224 Wis. 155, 1937 Wisc. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-mutual-liability-insurance-v-chain-belt-co-wis-1937.