American Metal Ceiling Co. v. New Hyde Park Fire District

172 A.D. 763, 158 N.Y.S. 11, 1916 N.Y. App. Div. LEXIS 10378
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 17, 1916
StatusPublished
Cited by1 cases

This text of 172 A.D. 763 (American Metal Ceiling Co. v. New Hyde Park Fire District) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Metal Ceiling Co. v. New Hyde Park Fire District, 172 A.D. 763, 158 N.Y.S. 11, 1916 N.Y. App. Div. LEXIS 10378 (N.Y. Ct. App. 1916).

Opinion

Thomas, J.:

It is a question of priority of mechanics’ liens. The electors of the New Hyde Park fire district (composed of the two Hempsteads in Nassau county) voted to raise by taxation a sum not to exceed $5,000, spread over several years, for the purpose of erecting a building for keeping and storing apparatus. That was on December 16,1913. The fire commissioners, on May 25, 1914, made a contract to do the work for $4,994, which, on the part of the contractor, was signed J. E. Heidtmann, (l. s.) per J. H. Heidtmann.” J. E. Heidtmann (full name John E. Heidtmann), defendant here, residence Sayville, was brother of J. H. Heidtmann, first [765]*765name Jesse, one of the fire commissioners, residence New Hyde Park. Hnder the same date a bond was given for the faithful performance of the contract purporting to be executed by “J. E. Heidtmann, George Christ, Mae Heidtmann.” John E. Heidtmann’s name was forged by Jesse Heidtmann to the contract and signed without authority to the bond. Jesse also forged John’s name to the order that all checks should be made to him. The contract did not cover the metal ceiling, heating or finished plumbing. Later the fire commissioners decided that such omitted work should be done, and on June thirtieth the taxpayers adopted a resolution to levy a tax also, payable through a long period, not to exceed $2,000, “ for the purpose of installing necessary plumbing metal work and heating in the new fire house now in the course of construction.” On July 13, 1914, an addendum was made to the original contract, signed “J. E. Heidtmann per J. H. Heidtmann.” Jesse H. had no authority to execute the supplementary contract in behalf of his brother John. The additional agreement did not specify the work to be done, but there seems to be no doubt but that it was to supply the work covered by the second resolution, and what was omitted in the first contract. In terms it added a payment. Whereas under the first contract the fourth payment was the final one upon due completion of the building, it was by the supplementary contract made the fifth payment, while the fourth payment, was stipulated to be $1,714, c ‘to be paid when the metal ceiling is completed.” The commissioners paid Jesse as follows: First payment, $200, due upon completion of foundation; second payment, $1,300, due when building was sheathed; third payment, $1,500, in July, when the outside was completed and first coat of paint was on, and $1,714, the sum named as the fourth payment under the additional contract, which payment was due when metal ceiling was completed. About August eleventh Jesse absconded, and Christ, who was a surety, finished the building. At the completion of the work there was in the hands of the commissioners $1,964. The question is, what lienors should have it ? Three are claiming it, to wit, the plaintiff, respondent (lien first in time), who put up the metal ceiling; Christ, a respondent (liens third in time), who did the [766]*766plumbing and finished the building, and the Nassau Lumber Company, appellant (lien second in time), who furnished material that went into the general construction. The judgment gives it to plaintiff, and to Christ on his plumbing contract, and the balance to Christ for finishing the budding, as if for that he was an independent contractor. The parties base their several claims to priority upon a number of grounds, which must be taken up seriatim. The plaintiff’s lien is first in time and should prevail on that account, but I must discuss its argument that it and Christ have first liens because the $2,000 was authorized for metal work, plumbing and heating, and is held in trust for that purpose, upon the principle used in such cases as Swift v. Mayor, etc. (83 N. Y. 528); People ex rel. Rohr v. Owens (110 App. Div. 30); Davidson v. Village of White Plains (121 id. 287). How does it appear that the money now on hand is part of the money last ordered to be raised for metal work and plumbing? Respondent’s answer in effect is that all the money was to be raised by tax through several years, and meantime the commissioners borrowed it, in the first instance the $5,000 initially authorized, and then the $2,000, later authorized, and all the four payments to the contractor, aggregating $4,714, were made out of the $5,000 and a balance was left. So that when the last money of the $1,714 was paid to Jesse H. Heidtmann on July 25, 1914, none of the $2,000 had come to the hands of the commissioners. Such seems to be the fact. Therefore, the plaintiff’s argument is that none of the $2,000 was in hand when the contractor was paid, and hence it must be the money now in hand. But the fourth payment was to be made only upon the completion of the metal ceiling, and the $250 paid to Jesse on July sixteenth and the payment of $1,464 on July twenty-fifth, aggregate $1,714, were on the fourth payment of that amount. Hence, it must have been on account of the metal ceiling, at least in part. But I note that the respondent urges that plaintiff’s work on the metal ceiling was begun July sixteenth and finished August sixth; that when the $250 was paid to Jesse the metal work was half done, had not been inspected, and that the architect had not consulted the parties to the contract as to the object of the payment, or inspected the [767]*767metal ceiling to determine its due completion. But when the payment was made on July twenty-fifth the ceiling was substantially completed, as Christ states. Nevertheless the facts show that the payment was to cover at least the metal ceiling, even though the payment was premature. Jesse Heidtmann gave plaintiff two checks, one on August 1, 1914, for $400, and one on August tenth, for $500, but neither was paid. Those checks were intended as “Payments for installing the metal ceiling.” Such payment necessarily covered the metal ceiling, for the additional contract stipulated that it was due only on such completion. If the $1,714 did not come from the fourth payment, it must have come from the fifth payment, which was due only upon the completion of the building. That is not conceivable. The intention, then, was to pay whatever a fourth payment was applicable to pay, that is, among other things, the metal ceiling. I will later consider Christ’s claim for the plumbing. The ceiling was not done until August sixth. Then the payment was in advance. But the parties could agree to advance it and did so. No claim is made against the owner on that account, and the fact cannot be used to displace other hens. None of the $2,000 had then been actually received. Therefore, the commissioners borrowed from the $5,000 fund to meet payments of work chargeable to the $2,000 fund. If the payment was to cover the ceiling, it is unimportant to the plaintiff where the commissioners got the money to pay the contractor, whether from their own pockets or those of another. The question is, why and for what was the contractor paid ? He was paid for the ceiling because that item was payable from the fourth payment, and it was the fourth payment that was advanced. Moreover, it is evident that practically the two funds could not be segregated for the purposes of payments. The plumbing and heating and ceiling must progress in harmony with the other work. Pipes must become a part of general construction, and what was due the contractor for plumbing, or general work, could not be well dissociated. If the owner paid the contractor from the first fund for work payable from the second fund, it was a matter between the parties. He could not complain, and, if it was done in good faith, those [768]*768with whom he contracted should not be permitted to do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N. P. Nelson Iron Works, Inc. v. Berry
237 A.D. 575 (Appellate Division of the Supreme Court of New York, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
172 A.D. 763, 158 N.Y.S. 11, 1916 N.Y. App. Div. LEXIS 10378, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-metal-ceiling-co-v-new-hyde-park-fire-district-nyappdiv-1916.