American Manufacturing Co. v. Champion Manufacturing Co.

79 S.E. 485, 13 Ga. App. 551, 1913 Ga. App. LEXIS 252
Court of Appeals of Georgia·Decided October 7, 1913·No. 4939·Published·Cited by 4 cases

Opinion

Pottle, J.

The American Manufacturing Company brought suit on open account against the Champion Manufacturing Company, a partnership composed of two named persons. The account was made up of 6,333 bag-holders, which had been delivered to and [552] accepted by the defendants at the agreed price of 17% cents each; of 4,360 bag-holders on hand which the defendants refused to accept, and 39,307 bag-holders which the defendants agreed to take, but which had not been manufactured by the plaintiff. Against this item the plaintiff credited the expense of manufacturing the bag-holders which had not been made up. There were also in the account several items for a number of cane-strippers, and an item for the cost of extra material. The total amount claimed to be due on the account was $9,306.46, less a credit of cash paid, $1,820.13, together with a deduction of $409.27,' the estimated expense of completing the contract, and credit memoranda of shortage of $1.55, making the net balance, claimed to be due on 'account, of $6,989.51. The items of the account for the purchase-price of the bag-holders was based on a written contract dated June 2, 1911, in which the plaintiff agreed to sell and the defendants to buy 50,000 bag-holders, of certain dimensions, at 17% cents each, f. 0. b. Chattanooga, Tenn.; deliveries to begin on July 15, and the entire number to be shipped out by September 15, 1911. The terms of payment were, $1,000 within five days from date of the contract, and the balance to be paid thirty days after shipment. The shipments were to be made direct to customers upon the defendants’ orders, and any bag-holders remaining on hand on September 15, 1911, were to be shipped to the defendants at Macon, Georgia. In the event the stakes for the bag-holders were lengthened, the defendants were to pay for the additional cost of the material. The defendants admitted the execution of the contract; admitted the delivery of the ,6,333 bag-holders, averred that the plaintiff had been paid in full for.these bag-holders, and denied all of the other material 'allegations in the petition.

From the evidence offered in behalf of the plaintiff, it appears that in August; 1911, the plaintiff had manufactured and delivered, in accordance with the contract, 6,333 bag-holders, and had on hand 4,360, for which no shipping instructions had been given by the defendants. The defendants notified the plaintiff that they would be unable to use the remainder of the bag-holders contracted for, and requested that some arrangement be made by which they might be relieved from the. contract or have its • completion postponed until a year later. No agreement was reached by correspondence, and on August 26 one of the defendants went to Chattanooga to [553] take up the matter in person with the president of the plaintiff company. The plaintiff declined to.release the defendants from the contract, but it was finally agreed that if the defendants would pay the amount then due, and pay for the 4,360 bag-holders on hand and also pay for the material on hand which had been bought for the purpose of manufacturing the bag-holders contracted for, the plaintiff would extend the time for the completion of the contract for one year. The past-due account then owing by the defendants to the plaintiff amounted to $830. Subsequently the defendants paid the plaintiff this amount, but they have never paid for the material on hand, nor for the 4,360 bag-holders. The plaintiff could have completed the contract on September 15 if it had not been notified by the defendants that they would not' take and pay for the remainder of the bag-holders. After the agreement between the parties'on August 36, several letter passed between them, indicating a difference of opinion as to what was the real agreement entered into on August 36. Propositions of settlement were made by the defendants, but were not accepted by the plaintiff. Finally on November -3, 1911, the plaintiff notified the defendants that it would go forward and complete the contract and hold the remainder of the bag-holders, as well as the 4,360 bag-holders then on hand, subject to the defendants’ order. Later the plaintiff wrote, submitting a further proposition and stating that if it was accepted the plaintiff would defer completion of the contract until the next year. This proposition was, however, rejected by the defendants. The parties being unable to reach an adjustment, suit was brought on November 13, 1913, more than a year after the time when the contract was to have been completed, under the agreement of August 36, 1911. The trial judge granted a nonsuit, and the plaintiff excepted.

Free access — add to your briefcase to read the full text and ask questions with AI

American Manufacturing Co. v. Champion Manufacturing Co., 79 S.E. 485, 13 Ga. App. 551, 1913 Ga. App. LEXIS 252 (Ga. Ct. App. 1913).

79 S.E. 485 (American Manufacturing Co. v. Champion Manufacturing Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dunaway v. Colt Co.
106 S.E. 599 (Court of Appeals of Georgia, 1921)
Neely v. Willard Bag & Manufacturing Co.
99 S.E. 167 (Court of Appeals of Georgia, 1919)
Blackstock, Hale & Morgan v. Phillips-Jones Co.
95 S.E. 265 (Court of Appeals of Georgia, 1918)
Mill Wood & Coal Co. v. Flint River Cypress Co.
85 S.E. 943 (Court of Appeals of Georgia, 1915)