American International Contractors, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMay 29, 2018
DocketASBCA No. 60948, 61166
StatusPublished

This text of American International Contractors, Inc. (American International Contractors, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American International Contractors, Inc., (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) American International Contractors, Inc. ) ASBCA Nos. 60948, 61166 ) Under Contract No. W912ER-14-C-0002 )

APPEARANCES FOR THE APPELLANT: Scott M. Heimberg, Esq. Mark J. Groff, Esq. Elise A. Farren, Esq. Akin Gump Strauss Hauer & Feld LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Rebecca L. Bockmann, Esq. Sarah L. Hinkle, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE O'CONNELL ON THE PARTIES' CROSS-MOTIONS FOR SUMMARY JUDGMENT

Pending before the Board are the parties' cross-motions for summary judgment on appellant's claim seeking the return of liquidated damages withheld by the government. We grant the government's motion in part and deny it in part. We deny appellant's motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS

Unless otherwise noted, the following facts are undisputed or uncontroverted.

1. On 21 January 2014, the U.S. Army Corps of Engineers, Middle East District (Corps), and American International Contractors, Inc. (AICI) entered into a contract for a project entitled United Kingdom Maritime Component Command (UKMCC) Development, Mina Salman Port, NSA II, Kingdom of Bahrain, at a price of$9,788,000 (ASUMF 1 ,i 1; GSMF 2 ,i 1; R4, tab 8 at 2-3). A limited number of contract provisions are relevant to the pending motions.

1 Appellant's Statement of Undisputed Material Facts. 2 Government's Statement of Material Facts. 2. As awarded, the contract had 12 contract line item numbers (CLINs). The largest of these were CLIN 0002 providing for the construction of a Forward Support Services (FSU)/Forward Logistics Site (FLS) facility priced at $4,354,184, and CLIN 0004 providing for the construction of a Command Headquarters (HQ) facility priced at $4,255,742 (ASUMF i1 1; GSMF i1 1; R4, tab 8 at 4-9).

3. The contract required AICI to complete the HQ facility and related CLINs by 7 March 2015 and the FSU/FLS facility and related CLINs by 6 April 2015 3 (R4, tab 8 at 9-10, 32-33).

4. The contract contained the Federal Acquisition Regulation (FAR) 52.21 i-12, LIQUIDATED DAMAGES-CONSTRUCTION (SEP 2000) clause. Pursuant to FAR l l .503(b ), the contracting officer has the authority to revise this clause to provide for different liquidated damages amounts for separate parts of the work, but she did not do so here. Accordingly, the contract did not differentiate liquidated damages for the HQ facility work to be completed on 7 March 2015 and the FSU/FLS work to be completed on 6 April 2015. It simply provided: "If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,447.00 for each calendar day of delay until the work is completed or accepted." (ASUMF ,-r 2; GSMF ,-r 2; R4, tab 8 at 33)

5. Finally, the contract also contained FAR 52.211-13, TIME EXTENSIONS (SEP 2000), which provides:

Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.

(App. mot. at 9; R4, tab 8 at 33)

6. AICI did not complete the original contract work on time. In a 5 February 2015 letter, the contracting officer (CO) notified AICI that she would assess liquidated

3 These are the dates listed at page 10 of the contract and the dates used by the parties in their briefs (ASUMF ,-i 1; GSMF ,-r 1). As discussed below, the Corps did not use these dates for assessing liquidated damages. 2 damages starting on 10 March 2015 at a daily rate of $1,223.50 (one-half the rate specified in the contract) for failure to complete the HQ facility (R4, tab 22). After AICI failed to complete the HQ facility by 9 March 2015 the Corps subsequently withheld $26,917 in liquidated damages (22 x $1,223.50) from AICI's March 2015 invoice (ASUMF ,r 3; GSMF ,r 3 ).

7. AICI also failed to complete the FSU/FLS facility on time. In AICI's April 2015 invoice, the Corps withheld an additional $63,622 in liquidated damages. This amount consisted of $9,788 for the HQ facility only from 1-8 April 2015 (8 x $1,223.50), and $53,834 for both facilities for the remainder of the month at the contractual rate of $2,447 per day (22 x $2,447). 4 (ASUMF ,i 4; GSMF ,i 4; R4, tab 151) Finally, the CO withheld an additional $68,516 from 1-28 May 2015 (28 x $2,447), at which point the Corps agreed that the facilities were substantially complete (ASUMF ,i 7; GSMF ,i,i 6-7; R4, tab 152 at 1). The Corps withheld a total of $159,055 in liquidated damages.

8. There is a material dispute of fact as to whether the buildings were sufficiently complete on 18 May 2015 to stop the assessment of liquidated damages (ASUMF ii 6; GSMF ,r 6; R4, tab 3 at 3-4).

9. On 5 January 2016, after AICI had demobilized from the site, the Corps issued RFP-0007 seeking a proposal from AICI for a variety of work in the HQ facility (R4, tab 128). AICI submitted an original and then a revised proposal (R4, tabs 84, 92). The parties engaged in negotiations but ultimately were unable to agree upon a final price for the work (GSMF ,i 8; app. reply to GSMF ,i 8).

10. Neither party has directed the Board to any extrinsic evidence indicating that the parties discussed or contemplated remission of the previously withheld liquidated damages as part of the modification for the RFP-0007 work.

11. After the conclusion of these negotiations, on 11 March 2016, the CO issued unilateral Modification No. POOOl 1 for $168,710. The modification required AICI to do the following in the HQ facility: add cooling in the server and operations room; add a security grill in Room 204; remove a window in Room 102; and modify cabinets in Room 208. Modification No. POOO 11 contained the following language:

4 The parties have not explained why the liquidated damages assessment began slightly later than the completion dates identified above (see ASUMF ,i 1; GSMF ,i 3). One explanation is that the contract also provided for completion within 395 and 425 days for the HQ and FSU/FLS facilities, respectively, after receipt of the notice to proceed (on 7 February 2014) (see R4, tab 8 at 32, tab 23). 3 The Period of Performance has increased for CLIN 0004 for a period of two-hundred-thirty-two (232) days from the effective date ofthis modification of March 11, 2016. This results in a Period of Performance end date of October 29, 2016. This Period of Performance covers work under this modification only, not for the overall contract.

(ASUMF ,r 8; GSMF ,r 8; app. reply to GSMF ,r 8; R4, tab 19 at 2)

12. Modification No. P00012 extended the completion date a further 59 days. It stated:

[T]he Period of Performance is extended for the work under modification POOO 11 on CLIN 0004 from October 29, 2016 to December 27, 2016. This Period of Performance covers work under modification POOOl 1 only, the Period of Performance for the overall contract remains unchanged.

(ASUMF ,r 9; GSMF ,r 9; gov't resp., attach. 4 at 5-6)

13. AICI completed the Modification Nos. POOOl land P00012 work prior to the 27 December 2016 deadline (ASUMF ,r 10; GSMF ,r 10).

14. On 6 September 2016, AICI submitted an uncertified claim to the CO seeking return of the liquidated damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Abcon Associates, Inc. v. United States
49 Fed. Cl. 678 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
American International Contractors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-international-contractors-inc-asbca-2018.