American Electric Co. v. Parsons RCI, Inc.

90 F. Supp. 3d 1079, 2015 WL 877923
CourtDistrict Court, D. Hawaii
DecidedFebruary 27, 2015
DocketNos. CIV. 13-00471 BMK, CIV. 14-00020 BMK
StatusPublished
Cited by1 cases

This text of 90 F. Supp. 3d 1079 (American Electric Co. v. Parsons RCI, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Electric Co. v. Parsons RCI, Inc., 90 F. Supp. 3d 1079, 2015 WL 877923 (D. Haw. 2015).

Opinion

ORDER DENYING DEFENDANT PARSONS RCI, INC.’S MOTION FOR PARTIAL SUMMARY JUDGMENT AGAINST COVANTA HONOLULU RESOURCE RECOVERY VENTURE ON ITS CLAIMS AND ■ COUNTERCLAIMS FOR LIQUIDATED DAMAGES

BARRY M. KURREN, United States Magistrate Judge.

Before the Court is Defendant/Third-Party Plaintiff Parsons RCI, Ine.’s (“Parsons”) Motion for Partial Summary Judgment against Covanta Honolulu Resource Recovery Venture on its Claims and Counterclaims for Liquidated Damages (the “Motion”). (Doc. no. 153.) Parsons seeks partial summary judgment against Covan-ta Honolulu Resource Recovery Venture (“Covanta”) on the grounds that Covanta is not entitled to liquidated damages, because the claims and counterclaims for damages are not supported by Hawaii law and are factually unsupported. Additionally, Parsons seeks summary judgment on its counterclaim against Covanta for breach of contract, as Covanta has allegedly conceded that it has failed to pay Parsons for change-order work that the latter performed.

The Motion came on for hearing before the Court on February 11, 2015.1 After careful consideration of the Motion, the supporting and opposing memoranda, and the arguments of counsel, the Court hereby DENIES the Motion.

BACKGROUND

I. FACTUAL BACKGROUND

The facts of this case are well known to the Court and the parties. (See Order (1) Denying Covanta Honolulu Resource Recovery Venture’s Motion for Partial Summary Judgment re Disallowed Claims (Doc. ho. 113) and (2) Denying Covanta Honolulu Resource Recovery Venture’s Motion for Partial Summary Judgment re Parsons, RCI, Inc.’s Duty to Defend and, With Respect to the Disallowed Claims, to Indemnify (Doc. No. 122).) Accordingly, the Court only addresses the facts pertinent to the present Motion.

[1081]*1081A. Liquidated Damages Provisions in Article 3.3 and Change Order 28

Article 3.3 of the General Contract (“Contract”) between Covanta and Parsons provides for an award of liquidated damages to Covanta if Parsons fails to meet certain milestones.2 (Covanta’s Concise Statement of Facts (“CSF”), Exh. B, Contract art. 3.3.) Article 3.3 was subsequently modified in part by Change Order 28. Change Order 28 provides that:

3.3.3In the event Contractor fails to achieve (a) the Mechanical Completion Milestone by the Scheduled Mechanical Milestones Completion Date or (b) Construction Completion by the Scheduled Construction Completion Date, in either case, Contractor agrees to pay Covanta as liquidated damages (and not as a penalty nor subject to any proof of such loss) the amounts set forth in Exhibit K-l; provided, however that the aggregate amount of liquidated damages payable hereunder shall never exceed the sum of Twenty-Five Thousand Dollars ($25,000.00) per calendar day....
3.3.4 The Parties agree that the words “Readiness for First Refuse Fire prior to April 21, 2012” shall be substituted for the words “Mechanical Completion prior to March 4, 2012” in Change Order No. 9 to this Contract. Readiness for First Fire is defined in Exhibit K-l. Contractor further agrees that it will in no event request or claim that it is entitled to an extension or modification of the April 21, 2012 date in order to obtain a bonus under Change Order No. 9. 3.3.5 The Parties agree that the amount of liquidated damages provided in this Contract is neither a penalty nor a forfeiture, and Contractor expressly waives its right to assert or plead that the liquidated damages provided for in this Contract are a penalty, forfeiture, or are unconscionable, unreasonable, disproportionate in amount, capable of being calculated and proven in a precise amount, otherwise void or unenforceable, or that Covanta has not incurred or will not incur actual damages as a result of the Contractor’s failure to complete the Work on time.

[1082]*1082(Covanta’s CSF, Exh. C, Change Order 28 (emphasis added).)

Exhibit K-l to Change Order 28 mandated a $20,000-per-calendar-day penalty for Parsons’s failure to meet the stated milestones. Exhibit K-l sets April 21, 2012 as the milestone date for the Readiness for First Refuse Fire, and the Construction Completion Date is designated as 30 days after the First Refuse Fire. (Id. at Exh. K-l.)

B. Parsons’s Alleged Failure to Meet the Milestones

In its First Amended Complaint against Parsons3, Covanta alleges that Parsons failed to meet both the Readiness for First Refuse Fire milestone, as well as the Construction Completion milestone. (Covan-ta’s First Am. Compl. ¶¶ 52-57.) Covanta claims that, even though it extended the Readiness for First Refuse Fire milestone deadline from April 21, 2012 to May 5, 2012, Parsons did not meet the Readiness for First Refuse Fire until approximately May 31, 2012.4 (Mem. in Opp’n at 6, 9.) Covanta further argues that, even though Parsons was required to meet the Construction Completion milestone deadline by July 1, 20125, it failed to do so, and Construction Completion did not occur until as late as February 15, 2013. (Mem. in Opp’n at 9.) Thus, Covanta claims that Parsons was 26-days late, in meeting the Readiness for First Refuse Fire milestone, and approximately seven-months late in meeting the Construction Completion milestone.6

Under the terms of Change Order 28, then, it appears that Covanta could be owed approximately $520,000 for Parsons’s failure to meet the Readiness for First Fire milestone, and up to approximately $4.2 million for Parsons’s failure to meet the Construction Completion milestone.

C. Covanta’s Retroactive Bonus from the City & County of Honolulu

Parsons alleges that Covanta invoiced Project owner City and County of Honolulu (the “City and County”), claiming an early completion bonus in the amount of $1,569,879.98. The bonus was supposedly premised on the City and County’s acceptance of the Project on August 4, 2012. (Mot. at 11.) However, Covanta points out that the City and County retroactively accepted the Project only after Covanta agreed to undertake certain modifications at its own expense. (Mem. in Opp’n at 10-13.) Covanta states that the City and County actually rejected Covanta’s Acceptance Test on July 23, 2012. (Id. at 11.) Covanta claims that, in order for it to meet the City and County’s retroactive Acceptance Date, it expended over $2 million fixing work performed by Parsons. (Id. at 13.)

[1083]*1083D. Covanta’s Alleged Breach of Contract

Parsons claims that Article 7 of the Contract requires Covanta to issue a change order'with any directive that will cause a material increase or decrease in the Contract price or time. (Mot. at 12.) Even if the parties disagreed on the change order, Parsons was to continue with the directed work, and Covanta was to compensate Parsons for the changed work. (Id.) Specifically, Article 7.6 provides that Covanta will continue to work on the Project:

notwithstanding that a Change Order has not been issued or that agreement has not been reached on the effects, if any, of a proposed change to the Contract Price or Completion date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
90 F. Supp. 3d 1079, 2015 WL 877923, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-electric-co-v-parsons-rci-inc-hid-2015.