American Building Innovations v. Balfour Beatty Construction

CourtCalifornia Court of Appeal
DecidedSeptember 3, 2024
DocketG062471
StatusPublished

This text of American Building Innovations v. Balfour Beatty Construction (American Building Innovations v. Balfour Beatty Construction) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Building Innovations v. Balfour Beatty Construction, (Cal. Ct. App. 2024).

Opinion

Filed 9/3/24

CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION THREE

AMERICAN BUILDING INNOVATION LP, G062471, G062965 Plaintiff and Appellant, (Super. Ct. No. 30-2019-01072989) v. OPINION BALFOUR BEATTY CONSTRUCTION, LLC, et al.,

Defendants and Respondents.

Appeals from a judgment and postjudgment order of the Superior Court of Orange County, Nathan R. Scott, Judge. Affirmed. Roxborough, Pomerance, Nye & Adreani, Drew E. Pomerance, Joseph C. Gjonola, and David R. Ginsburg for Plaintiff and Appellant. Finch, Thornton & Baird, Jason R. Thornton, Daniel P. Scholz, and Scott M. Bennett for Defendants and Respondents. * * * As a condition precedent to the issuance, continued maintenance, or reinstatement of a contractor’s license, California law requires applicants and licensees to have on file “at all times” a current and valid certificate of workers’ compensation insurance. If the applicant or licensee has no employees or is not otherwise subject to workers’ compensation laws, this 1 requirement is inapplicable. (Bus. & Prof. Code, § 7125, subd. (a) & (b).) Failure to obtain or maintain the required coverage results in the automatic and immediate suspension of the contractor’s license by operation of law. (§ 7125.2, subd. (a).) Such a suspension impacts the contractor’s ability to litigate claims for compensation: a party who was not “duly licensed . . . at all times during the performance of” its contracting work generally cannot bring or maintain an action to collect compensation for that work. (§ 7031, subd. (a); cf. id., subd. (e) [substantial compliance exception].) A suspended contractor’s license can be retroactively reinstated if the licensee obtains and submits to the registrar a valid certificate of workers’ compensation insurance within 90 days of the certificate’s effective date. (See §§ 7125.2, subd. (c), 7125.1, subd. (a).) If the certificate is submitted to the registrar more than 90 days after its effective date, however, retroactive reinstatement is available only if the licensee shows “that the failure to have a certificate on file was due to circumstances beyond the control of the licensee.” (Id., subd. (b).) This appeal involves the interplay of these statutes and what circumstances are “beyond the control of the licensee” for purposes of retroactive license reinstatement. In this case, plaintiff American Building Innovation LP (ABI) had a workers’ compensation policy when it started

1 All further undesignated statutory references are to this code.

2 work on a project. Its insurer canceled the policy, however, because ABI refused to pay outstanding insurance premiums charged on a prior policy, since ABI believed (correctly as it turns out) it was being overcharged. As a result of the policy cancellation, ABI’s contractor’s license was suspended mid-project. Fully aware it was unlicensed and uninsured, ABI nevertheless continued its work. ABI later sued to recover amounts allegedly owed for its work on the project. Several years into that litigation, ABI settled its old premium dispute with its workers’ compensation insurer and had the canceled policy retroactively reinstated as part of the settlement. ABI then applied to the Contractors’ State License Board (the Board) for retroactive reinstatement of its contractor’s license, asserting that ABI’s failure to file a certificate of workers’ compensation coverage had been “due to circumstances beyond [its] control,” in that the policy had been canceled “unbeknownst to” ABI. The Board accepted ABI’s representation and retroactively reinstated its contractor’s license under section 7125.1. We must now decide whether ABI was “duly licensed . . . at all times during the performance of” its work; if not, section 7031 bars ABI from bringing or maintaining the present action. We conclude section 7031 does indeed bar ABI’s current claims. A suspended contractor’s license can be retroactively reinstated under section 7125.1 only if “the failure to have a certificate on file was due to circumstances beyond the control of the licensee.” (Id., subd. (b).) In this case, the lapse in coverage was not beyond ABI’s control. The record before us demonstrates the policy cancellation occurred because ABI chose not to pay billed insurance premiums. ABI learned of the policy cancellation days after it took effect, yet ABI did not procure replacement coverage until years later when it settled the premium

3 dispute with its insurer. The insurer’s retroactive reinstatement of the policy following that settlement was essentially meaningless because it occurred long after the statute of limitations ran on any workers’ compensation claims, rendering the coverage illusory. We agree with the trial court that section 7031 bars the present action, and we therefore affirm the judgment. We also affirm the award of attorney fees under the subcontract’s prevailing party attorney fee provision. STATEMENT OF FACTS Defendant Balfour Beatty Construction, LLC (Balfour Beatty) was hired by a local school district to construct a two-story classroom building at an elementary school. In June 2017, Balfour Beatty hired ABI as a subcontractor to perform concrete, framing, and structural steel work on the project and agreed to pay ABI over $700,000 for its work. ABI was on the project from August 2017 through May 2018. ABI concedes that its work on the project required it to be licensed by the Board and that it had to maintain workers’ compensation insurance throughout the project in order to maintain its license. (See §§ 7026, 7028, 7125, 7125.2.) When ABI began its work on the project in August 2017, it had a workers’ compensation insurance policy issued through State Compensation Insurance Fund (State Fund). In December 2017, State Fund sent ABI a notice of cancellation, informing ABI that its 2017-2018 workers’ compensation policy would be canceled in January 2018 if ABI did not pay approximately $33,000 in outstanding premiums, which State Fund asserted were owed for ABI’s 2015-2016 policy based on an audit State Fund had performed in 2017.2

2 State Fund first audited ABI’s 2015-2016 policy in spring 2017

4 ABI received Stand Fund’s notice of cancellation; it nonetheless failed to make payment. Accordingly, State Fund canceled ABI’s 2017-2018 policy on January 25, 2018. Both the Board and ABI’s insurance broker notified ABI of the cancellation in writing shortly thereafter. ABI’s principal, Tin Vo, admittedly became aware of the policy cancellation no later than February 1, 2018. According to Vo, he was “blindsided” by the cancellation because State Fund had previously suspended collection of policy premiums during the audit dispute and had not previously canceled ABI’s policies. As a result of the policy cancellation, ABI’s contractor’s license was suspended by operation of law on January 25, 2018, due to ABI’s “failure . . . to . . . maintain workers’ compensation insurance coverage.” (§ 7125.2.) The Board gave ABI notice of the license suspension on January 29 and informed ABI that its contractor’s license would be suspended if ABI failed to submit a valid insurance certificate or exemption certificate within 45 days. (See § 7125.2, subd. (b) [requiring registrar to give notice of license suspension].) ABI did neither. In mid-March, the Board sent ABI a letter notifying ABI that its license had been retroactively suspended effective January 25 under section 7125.2.

and told ABI it owed about $48,000 in premiums. ABI disputed the audit and the resulting bill, and State Fund put a hold on the bill to further investigate the matter. In late 2017, State Fund issued ABI a revised audit statement for roughly $15,000 less than had been previously billed. Still not satisfied, ABI continued to dispute the revised audit bill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hydrotech Systems, Ltd. v. Oasis Waterpark
803 P.2d 370 (California Supreme Court, 1991)
White v. Cridlebaugh
178 Cal. App. 4th 506 (California Court of Appeal, 2009)
Pacific Custom Pools, Inc. v. Turner Construction Co.
94 Cal. Rptr. 2d 756 (California Court of Appeal, 2000)
Wright v. ISSAK
58 Cal. Rptr. 3d 1 (California Court of Appeal, 2007)
Buzgheia v. Leasco Sierra Grove
60 Cal. App. 4th 374 (California Court of Appeal, 1997)
MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co.
115 P.3d 41 (California Supreme Court, 2005)
Mountain Air Enters., LLC v. Sundowner Towers, LLC
398 P.3d 556 (California Supreme Court, 2017)
Santisas v. Goodin
951 P.2d 399 (California Court of Appeal, 1998)
California-American Water Co. v. Marina Coast Water Dist.
227 Cal. Rptr. 3d 110 (California Court of Appeals, 5th District, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
American Building Innovations v. Balfour Beatty Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-building-innovations-v-balfour-beatty-construction-calctapp-2024.