American Bridge Co. v. United States

72 Ct. Cl. 344, 1931 U.S. Ct. Cl. LEXIS 308, 1931 WL 2316
CourtUnited States Court of Claims
DecidedJune 1, 1931
DocketNo. H-364
StatusPublished
Cited by3 cases

This text of 72 Ct. Cl. 344 (American Bridge Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Bridge Co. v. United States, 72 Ct. Cl. 344, 1931 U.S. Ct. Cl. LEXIS 308, 1931 WL 2316 (cc 1931).

Opinion

Booth, Chief Justice,

delivered the opinion:

The plaintiff is a New Jersey corporation. On December 26,1918, it entered into a written contract, identified as No. 3604, with the Navy Department through the Bureau of Yards and Docks to furnish, deliver, erect, and paint all the structural steel specified therein, essential to the construction of a furnace building, a machine shop, an open-hearth building, and a heat-treatment building at the Naval Ordnance plant, South Charleston, West Virginia. Plaintiff was to receive $0,054 for each pound of steel in place in the four buildings. The contract was to be completed in 240 calendar days from the date of its delivery to the plaintiff. The contract was delivered to the plaintiff on January 27, 1919, and hence was to be completed by September 24, 1919. The Government officials in charge were by the terms of the contract obligated to construct the foundations upon which the steel was to be superimposed, and after the contract was executed the Government officials expressly agreed to complete the foundations upon the following dates: the open hearth and machine shop foundations by May 1, 1919; the forge and furnace building by June 15, 1919, and the foundation for the heat-treatment building by June 1, 1919. The plaintiff proceeded to perform the contract until March, 1920, at which time all four buildings were about ninety per cent completed, it being conceded that plaintiff had then proceeded as far as [357]*357it was possible to proceed because substantial portions of the foundations had not been constructed by the defendant. The plaintiff then, with the consent of the defendant, removed its force of workmen from the site of the work and requested the defendant to engage someone else to complete the work. Subsequently, the date not being shown, the defendant requested the plaintiff to return its organization to the site and complete the work. The plaintiff in response requested the defendant to increase the consideration for performance of the contract because of the increased cost due to the defendant’s delays and failure to provide the essential foundations. The defendant thereupon appointed a board of changes under the general provisions of contract No. 3604. As a result of the recommendations of this board an agreement known as supplemental contract No. 3604Y, dated September 15, 1920, was entered into by the parties. Contract No. 3604Y recited that because of the failure of the defendant to furnish the necessary foundations and thereby permit the plaintiff to effectively prosecute the work as provided in contract No. 3604, and because of the increase in cost of performance due to this delay, the parties agreed that contract No. 3604 would be and was modified to the extent stipulated in No. 3604Y. The material factor with which this case is concerned, as to this item, is centered in the change of consideration for completing the contract. Contract No. 3604 provided for $0,054 per pound. Contract No. 3604Y added to this $11 per ton in place.

The plaintiff thereafter reorganized its company, proceeded to the site of the buildings, and engaged in doing so much of the work as it was possible for it to do. On December 22, 1920, the plaintiff completed all the work and was willing and ready to proceed to completion, but was prevented from going forward by the failure of the defendant to furnish foundations, so for the second time it was, with the consent of the defendant, compelled to remove its workmen and equipment from the site and was not thereafter able to resume work until June 8, 1921. On January 20, 1922, the plaintiff was for the third time, for the same reasons stated above, compelled to withdraw its work[358]*358men and equipment from the site with the defendant’s consent, receiving on February 10, 1922, a notice from the defendant to permanently discontinue work.

On February 27,1920, a contract, identified as No. 3604X, was executed by the parties. This contract called for the furnishing of 400 tons of structural steel for a substation building, a building in addition to those mentioned in No. 3604 at the Naval Ordnance plant, South Charleston, West Virginia.

It is conceded, and the facts indisputably establish, that the plaintiff was willing, ready, and capable of observing its obligations under the contracts involved, and that its failure to complete the work in accord therewith was solely attributable to defendant’s failure to furnish the essential foundations. The record shows that because of the failure of the defendant to furnish foundations for the furnace and heat-treatment buildings they were not completed until June 14, 1920, and January 20, 1922, respectively.

The Bureau of Yards and Docks conceded that there was due the plaintiff under the terms of the foregoing contracts a balance of $19,340.24 and prepared and submitted to it a voucher for this sum. The Comptroller General on or about November 27, 1926 (Finding XIII), ruled in a written opinion that the sum of $28,149, being the sum stated to be due the plaintiff under the increased prices stipulated in supplemental contract No. 3604Y, was illegally paid to it, and in pursuance of such ruling checked against and recouped said sum by applying the voucher for $19,-340.24 and other sums due the contractor in settlement thereof. This suit is for the recovery of the said sum of $28,149 and for other items of loss to be discussed hereafter.

If we correctly apprehend the determinative principle in the opinion of the Comptroller General, it is the rule that where one engages to do a certain thing at a stated price, an increase in price by way of a supplemental contract to do that precise thing is without consideration and hence not allowable. It is true, as said in the opinion, that the contract provided for delays, extension of time, liquidated damages, changes, unavoidable delays, and the usual provisions [359]*359of Government contracts, but it does not impress us that any of these provisions are applicable to the existing record. The defendant, so far as the present record discloses, did not change the specifications for the foundations for the buildings. The dereliction complained of is that the defendant did not act except in a most dilatory manner and frequently not at all. The contract obviously covered delays due to activities with respect to construction and not inaction, in no way ascribable to such a cause. The defendant failed to proceed as it agreed and offers no excuse for the failure. When action was taken, the board of changes, viewing the situation from the standpoint of facts, recommended the increased compensation and the defendant accepted the recommendation, acting thereon by executing with the plaintiff supplemental contract No. 3604Y. The defendant had agreed to furnish the foundations upon specific dates and had not done so. The plaintiff could not proceed until they were furnished, and nothing remained for it to do except withdraw its force of employees from the work and escape the expense incident to their maintenance. It is not suggested in the record that the defendant’s delay was due to any change in the specifications for the foundations; the changes contemplated embraced other features of construction that, in so far as the findings show, bear no relation to the foundations upon which the buildings were to rest. This case apparently falls within the recent case of Worthington Pump & Machinery Corp. v. United States, 66 C. Cls. 230: a case in all substantial respects precisely similar to this one. The present case is essentially different from the Eric Lange case, 61 C. Cls. 666.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ozark Dam Constructors v. United States
153 Ct. Cl. 120 (Court of Claims, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
72 Ct. Cl. 344, 1931 U.S. Ct. Cl. LEXIS 308, 1931 WL 2316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-bridge-co-v-united-states-cc-1931.