Amedee Geothermal etc. v. Lessen Municipal Utility Dist. CA3

CourtCalifornia Court of Appeal
DecidedMarch 26, 2021
DocketC086978
StatusUnpublished

This text of Amedee Geothermal etc. v. Lessen Municipal Utility Dist. CA3 (Amedee Geothermal etc. v. Lessen Municipal Utility Dist. CA3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amedee Geothermal etc. v. Lessen Municipal Utility Dist. CA3, (Cal. Ct. App. 2021).

Opinion

Filed 3/26/21 Amedee Geothermal etc. v. Lessen Municipal Utility Dist. CA3 NOT TO BE PUBLISHED California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA THIRD APPELLATE DISTRICT (Lassen) ----

AMEDEE GEOTHERMAL VENTURE I, C086978

Plaintiff and Appellant, (Super. Ct. No. 59485)

v.

LASSEN MUNICIPAL UTILITY DISTRICT,

Defendant and Respondent.

Amedee Geothermal Venture I (Amedee) claims the Lassen Municipal Utility District (LMUD) caused the catastrophic failure of its generator by replacing a 34.5 kilovolt power line with one with a 12.47 kilovolt capacity. Amedee brought an unsuccessful action against LMUD in federal court before filing this case in San Francisco Superior Court. The case was subsequently transferred to Lassen County and the claims for negligence causing a dangerous condition and breach of contract were tried to a jury. The jury returned a defense verdict, and a bench trial on Amedee’s inverse condemnation also found in favor of LMUD.

1 On appeal, Amedee contends (1) the trial court erred in refusing to categorically exclude LMUD ratepayers from the jury, (2) the jury misinterpreted a limitation of liability clause in the transmission agreement between Amedee and LMUD, (3) the trial court erroneously dismissed Amedee’s claim for negligence under Government Code section 815.21 based on governmental immunity, and (4) the trial court committed reversible error in denying the inverse condemnation claim by relying on findings not actually made by the jury.2 We conclude Code of Civil Procedure section 229, subdivision (d), did not require categorical exclusion of all LMUD ratepayers from the jury for implied bias. We further conclude Amedee has not preserved for appeal the issue of the jury’s interpretation of the transmission agreement. Amedee did not timely raise the issue when the issue could have been properly addressed in the first instance in the trial court. The trial court correctly concluded the decision to replace the power line to Amedee’s geothermal plant with a different voltage capacity was an action subject to immunity under section 820.2. Finally, the record shows the trial court engaged in independent and detailed fact finding before determining Amedee had not proven its inverse condemnation claim. Accordingly, we affirm the judgment. BACKGROUND

Jury Trial on Breach of Contract and Dangerous Condition Claims As this court has previously admonished, “In every appeal, ‘the appellant has the duty to fairly summarize all of the facts in the light most favorable to the judgment.’ [Citation.] ‘Further, the burden to provide a fair summary of the evidence “grows with

1 Undesignated statutory citations are to the Government Code. 2 While at the end of each section of its brief LMUD includes an argument that the cause of action is barred by the applicable statute of limitations, we shall decide this appeal based on the merits of the arguments.

2 the complexity of the record.” ’ ” (Myers v. Trendwest Resorts, Inc. (2009) 178 Cal.App.4th 735, 739, quoting Boeken v. Philip Morris, Inc. (2005) 127 Cal.App.4th 1640, 1658.) Ignoring this duty, Amedee recites the evidence in its favor and mostly ignores the evidence supporting the defense verdict. Based on our review of the transcripts, the evidence in the light most favorable to the judgment showed the following: Amedee is a geothermal power plant located in Lassen County to take advantage of energy from local hot springs to generate electricity for sale to the Pacific Gas & Electric (PG&E) company. While the Amedee plant was being planned, PG&E offered 10-year contracts to purchase power at rates favorable to electricity providers. The Amedee geothermal project was designed by Barber-Nichols Engineering (Barber- Nichols). At the Amedee plant, hot water comes up from underground and runs into a tank filled with small tubes containing R-114 (freon). The freon turns into a high-pressure gas that turns a turbine that in turn generates electricity. The freon flows through a cooling tower, returns to liquid form, and cycles back to the heat exchanger tank. When operational, Amedee is a net power generator. However, the geothermal plant requires an external source of electricity to start the brine pumps that bring up the geothermally heated water to initiate the power generation cycle. When Amedee’s geothermal power plant was completed in 1988, it received electrical service from CP National Corporation (CP National) pursuant to a transmission agreement (the transmission agreement). Amedee received power through a 34.5 kilovolt line. CP National’s utility system was subsequently purchased by LMUD, which assumed responsibility for CP National’s service obligations and the transmission agreement with Amedee. The transmission agreement provides, in part: “In the event that changes required to be made to [LMUD’s] system require [Amedee] to change its small power production facility and interconnection facilities in order to continue

3 deliveries of energy and capacity pursuant to this Agreement, [Amedee] may elect to make such changes at no cost to [LMUD] or terminate this Agreement. [LMUD] represents that, as of the date of this Agreement, it has no plan to change its transmission voltage in the foreseeable future.” The transmission agreement also contains the following limitations on liability of the parties in section 8: “8.1 Nothing in this Agreement shall be construed to create any duty to, any standard of care with reference to, or any liability to any person not a party to this Agreement. Neither Party shall be liable to the other for consequential, indirect, or incidental damages. “8.2 Neither Party shall be liable to the other for damages, whether direct, indirect, consequential, incidental, or general in nature, that arise by reason of electrical disturbances or faults caused by the operation, faulty operation, or nonoperation of the Party’s facilities, whether or not such operation, faulty operation, or nonoperation was occasioned by or accompanied with the active or passive negligence of the Party.” The transmission agreement does not specify that power to the geothermal project must be provided at 34.5 kilovolts. Operations at Amedee’s plant turned out to generate less power that its planners had forecast during the planning phase. In some years, there was insufficient income to pay Amedee’s investors. After the initial 10-year PG&E pricing structure expired, income dropped substantially for Amedee’s plant. In 1997, Amedee’s plant manager reported to the county assessor’s office that Amedee “is not currently profitable and the situation is only expected to worsen as the power price declines radically after the end of the fixed price period.” Similarly negative reports were filed with the county assessor in 1998 and 2000. Amedee’s plant manager, who had been there from the beginning, left the project at the end of 2000 to further reduce operating costs. When the plant manager left, he knew Amedee had a problem in its dependence on freon for its operations.

4 In the 1990’s, freon was banned from production and sale in the United States. By 2003, Amedee’s plant manager reported, “A lack of R-114 freon is the biggest problem.” Equipment at the plant had to be shut down for lack of sufficient freon. The freon problem worsened as aging equipment leaked the fluid. Amedee’s plant suffered from the age of its mechanical components.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Boyette
301 P.3d 530 (California Supreme Court, 2013)
Thompson v. County of Alameda
614 P.2d 728 (California Supreme Court, 1980)
Lipman v. Brisbane Elementary School District
359 P.2d 465 (California Supreme Court, 1961)
Orange County Water District v. City of Riverside
343 P.2d 450 (California Court of Appeal, 1959)
Kimbley v. Kaiser Foundation Hospitals
164 Cal. App. 3d 1166 (California Court of Appeal, 1985)
Burgdorf v. Funder
246 Cal. App. 2d 443 (California Court of Appeal, 1966)
Odello Brothers v. County of Monterey
63 Cal. App. 4th 778 (California Court of Appeal, 1998)
County of Los Angeles v. Superior Court
181 Cal. App. 4th 218 (California Court of Appeal, 2010)
Myers v. Trendwest Resorts, Inc.
178 Cal. App. 4th 735 (California Court of Appeal, 2009)
Boeken v. Philip Morris Inc.
26 Cal. Rptr. 3d 638 (California Court of Appeal, 2005)
Masters v. San Bernardino County Employees Retirement Ass'n
32 Cal. App. 4th 30 (California Court of Appeal, 1995)
Aguilar v. Atlantic Richfield Co.
24 P.3d 493 (California Supreme Court, 2001)
People v. Thornton
161 P.3d 3 (California Supreme Court, 2007)
People v. Partida
122 P.3d 765 (California Supreme Court, 2005)
People v. Ledesma
140 P.3d 657 (California Supreme Court, 2006)
Duran v. U.S. Bank National Assn.
325 P.3d 916 (California Supreme Court, 2014)
McKernan v. Los Angeles Gas & Electric Co.
116 P. 677 (California Court of Appeal, 1911)
Ham v. County of Los Angeles
189 P. 462 (California Court of Appeal, 1920)
Central Valley Gas Storage, LLC v. Southam
11 Cal. App. 5th 686 (California Court of Appeal, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Amedee Geothermal etc. v. Lessen Municipal Utility Dist. CA3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amedee-geothermal-etc-v-lessen-municipal-utility-dist-ca3-calctapp-2021.