Amdahl Corp. v. Bureau of Systems Policy & Planning

529 N.E.2d 1363, 26 Mass. App. Ct. 991, 1988 Mass. App. LEXIS 643
CourtMassachusetts Appeals Court
DecidedNovember 9, 1988
DocketNo. 88-P-447
StatusPublished
Cited by3 cases

This text of 529 N.E.2d 1363 (Amdahl Corp. v. Bureau of Systems Policy & Planning) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amdahl Corp. v. Bureau of Systems Policy & Planning, 529 N.E.2d 1363, 26 Mass. App. Ct. 991, 1988 Mass. App. LEXIS 643 (Mass. Ct. App. 1988).

Opinion

Amdahl Corporation (Amdahl), a disappointed bidder for a contract for the procurement of a mainframe computer, challenges the award of that contract by the Commonwealth2 to National Advanced Systems Corporation [992]*992(NAS). Prior to trial, a judge of the Superior Court enjoined payment to NAS pending adjudication of Amdahl’s claims. On appeal, Amdahl claims that (1) the award of the contract to NAS violated competitive bidding requirements, (2) the trial judge erred in ruling that Amdahl had an adequate remedy at law in the form of bid preparation costs, and (3) Amdahl is entitled to an order setting aside the contract with NAS and awarding the contract to Amdahl.3 We conclude that the award of the contract to NAS was proper.

The relevant facts are as follows. The office of management information systems (OMIS) data center provides data processing services to State agencies from a computer installation in Boston. In 1987, the data center operated three computers: two Amdahl 5870’s, each having a capacity of 21 MIPS (or millions of instructions per second),4 and one International Business Machines Corporation (IBM) 308IK +, having a capacity of 15 MIPS. The Amdahl computers were operating at full capacity, while the IBM computer had only enough software and peripheral equipment to take advantage of 60% of its capacity, or 9 MIPS.

Each of the three computers ran as one “system image,” in the terminology of the industry. To reflect its lower utilization, however, the data center staff referred to the IBM computer as having half a system image. Thus, the staff considered that the data center operated on two and one-half rather than on three system images.5

To plan for expansion of the center, OMIS’s capacity planners prepared a report entitled “Two-Year Growth Plan for the OMIS Data Center.” The plan projected the growth in data center services and presented an analysis of the options available for expanding the data center’s capacity. The plan predicted that the Commonwealth’s data processing needs in the fall of 1987 would be slightly more than 70 MIPS and that procurement of a new, more powerful processor in the 42-77 MIPS range would be more cost effective over a five year period than would procurement of an older technology, smaller, less expensive processor in the 21-26 MIPS range. According to the plan, acquiring a larger processor would enable the data center to reduce the number of system images it was operating to two, while acquiring smaller processors would increase the number of system images with their [993]*993attendant costs (see note 5, supra). On the basis of the plan and other ongoing studies and analyses, OMIS issued an Invitation for Bids (IFB) on June 24, 1987. The IFB called for a one system image, IBM-compatible processor having 40-60 MIPS capacity, upgradeable by February 1, 1988, to at least 75 MIPS with one system image (later reduced to 73 MIPS by an amendment to the IFB).

On July 9, 1987, the Commonwealth received eleven bids, including two from NAS and six from Amdahl. One of the NAS bids offered a 57 MIPS processor at a cost of $7,275,950. One of Amdahl’s bids offered a 42 MIPS processor at a cost of $5,091,643. Ranking the responsive bids by vendor cost using the formula described below, the selection board declared NAS’s 57 MIPS bid the lowest and awarded NAS the contract.

Prior to issuing the IFB, the selection board had prepared and filed with the State purchasing agent an evaluation formula by which to rank bids according to vendor costs. See 801 Code Mass. Regs. §§ 5.03, 5.29, 5.35 et seq. As bids could not equitably be ranked on an absolute dollar basis because of the price range of different sized processors, the formula ranked bids on a cost per MIPS basis. Bids were assigned a credit or assessed a charge, depending upon the capacity of the computer offered.

1. Credit calculation: The formula applied a credit of $269,437 to bids offering a processor with more than 48 MIPS capacity, on the theory that procurement of such a processor would enable the data center to reduce more quickly the number of its system images to two, while achieving the projected demand of 70 MIPS by the fall of 1987. The credit of $269,437 consisted of two elements: a monthly savings figure of $139,888, and a one-time savings/cost avoidance figure of $129,549. The monthly figure was intended to reflect the reduction to two system images and the associated savings in software licensing fees, peripherals, and personnel time.6 The one-time figure was intended to reflect the cost savings associated with the purchase of a new direct access storage device, or disk drive.

Amdahl attacks the assumptions underlying the evaluation formula as well as the mathematical results of the formula. Amdahl asserts that the formula contained at least two serious miscalculations which caused the selection board to misrank the two bids in issue in this case. The miscalculations, Amdahl claims, resulted in violations of the competitive bidding laws, as the contract was not awarded to the lowest responsible bidder.

We conclude that the credit component of the formula should have reflected only the monthly savings figure of $139,888, and not the one-time [994]*994cost avoidance figure of $129,549.7 In this respect we agree that the calculation of the credit element of the formula contained an error. As we shall see, however, the error does not turn out to be decisive.

2. Charge (penalty) calculation: To bids offering a processor with 48 or fewer MIPS capacity, a charge of $477,013 was applied. This charge was intended to represent both the costs associated with upgrading to full capacity the data center’s existing IBM computer until the new processor could be upgraded, and the related costs of operating a third system until the upgrade of the new processor to 73 MIPS.8 As with the credit component of the formula, the charge figure consisted of two elements: a monthly calculation of added costs and a one-time cost figure. The additional monthly costs were estimated to be $15,284 for eight months, or $122,272. This amount included the additional software licensing fees and personnel time needed to operate a third system image until the upgrade of the 48 or fewer MIPS processor projected to be eight months later. The one-time cost figure was calculated as $354,741. This figure included costs to purchase additional software, hardware and peripherals to bring the existing IBM computer up to full capacity during the eight months before the upgrade of the new processor.

The trial judge concluded that “[t]he reasons for the penalty are faulty.” In reaching that conclusión, the judge overstepped his authority. In effect, the judge was attempting to dictate how OMIS should have planned to configure its existing computers in the event the Commonwealth procured a processor with 48 or fewer MIPS. By so doing, the judge impermissibly attempted to regulate internal agency functions. “Th[e trial] court is not empowered to direct an administrative board how to perform its public duties.” Berman v. Board of Registration in Medicine, 355 Mass. 358, 360 (1969). A judge’s authority is particularly limited where, as here, the matter is within the technical competence of the agency. See Massachusetts Auto. Rating & Acc. Prevention Bureau v. Commissioner of Ins., 384 Mass. 333, 337 (1981).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. Amanti & Sons, Inc. v. R.C. Griffin, Inc.
758 N.E.2d 153 (Massachusetts Appeals Court, 2001)
Cataldo Ambulance Service, Inc. v. City of Chelsea
680 N.E.2d 937 (Massachusetts Appeals Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
529 N.E.2d 1363, 26 Mass. App. Ct. 991, 1988 Mass. App. LEXIS 643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amdahl-corp-v-bureau-of-systems-policy-planning-massappct-1988.