Alvey-Ferguson Co. v. Ernst Tosetti Brewing Co.

178 Ill. App. 536, 1913 Ill. App. LEXIS 1087
CourtAppellate Court of Illinois
DecidedApril 3, 1913
DocketGen. No. 18,006
StatusPublished
Cited by6 cases

This text of 178 Ill. App. 536 (Alvey-Ferguson Co. v. Ernst Tosetti Brewing Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alvey-Ferguson Co. v. Ernst Tosetti Brewing Co., 178 Ill. App. 536, 1913 Ill. App. LEXIS 1087 (Ill. Ct. App. 1913).

Opinion

Mr. Justice Fitch

delivered tlie opinion of the court.

From a judgment in favor of the defendant, the plaintiff appeals, and assigns a number of alleged errors. The declaration is in assumpsit and consists of three special counts and the common counts. Each of the special counts sets out in haec verba, a written contract, dated April 21, 1908, between the plaintiff, a Kentucky corporation, and defendant, an Illinois corporation, by the terms of which plaintiff agreed “to construct and install,” upon defendant’s premises in Chicago, a system of conveyors according to specifications and drawings thereto attached, the construction to be completed within sixty days and the contract to be fully complied with on the part of the plaintiff when the system shall have been constructed, installed and in successful operation; for which defendant agreed to pay $2000 in instalments. The specifications state that the system of conveyors is covered by letters patent owned and controlled by the Alvey-Ferguson Co., and consists of a gravity conveyor and elevators of steel, a roller chain with flights or carriers, sprocket wheels, shafting and pulley, all supported by iron hangers and stands. The drawings consist merely of a blueprint, showing the arrangement and dimensions of the conveyors, supports and other parts of the system. It is then averred that plaintiff at once began the work of making the system of conveyors and completed and shipped the same to the defendant within sixty days in accordance with the contract; that it also furnished at the time and place of delivery, “the necessary experts, labor, materials and other facilities for the installation of said system of conveyors and was then and there ready and willing, and tendered and offered to deliver the same to the defendant;” bnt that defendant would not accept it, nor permit the plaintiff to install it, and would not pay for it. The first and second counts conclude with a clause alleging that plaintiff has been damaged to the amount of $2000. The third' count concludes in the form of indebitatus assumpsit for the contract price of the conveyors.

It appears from the evidence that the contract was signed on behalf of defendant by Otto Tosetti, its vice-president, in Chicago, in the presence of a traveling salesman of the plaintiff; that at that time certain pencil memoranda were made upon the blueprint attached to the contract, indicating sundry changes to be made in some features of the plan as shown by the blueprint, and that it was agreed that a corrected blueprint should be made and sent to Mr. Boetter, secretary of the defendant company, for his approval.' The plaintiff’s salesman then mailed the contract to the office of the plaintiff in Louisville, where it was signed on behalf of plaintiff by the plaintiff’s vice-president. Thereupon plaintiff wrote to the defendant, acknowledging receipt of the signed contract, and adding: “We will, of course, make up the conveyor exactly in accordance with our plans submitted, except for the changes which have been fully explained by our Mr. Koehler. In accordance with their promise we shall be pleased to have our drafting department prepare a new drawing showing changes and as soon as completed will send you full particulars for approval.” To this letter defendant replied on April 30th, as follows: “We are in receipt of your favor of the 27th inst., and note contents. We would say that we are not yet prepared to install snob, machinery and would advise yon not to do anything for the present in this matter.” Meanwhile, plaintiff had begnn work on the conveyors and the necessary material had been marked out and cut in defendant’s shop. On May 7th plaintiff wrote to defendant: “Deferring to onr letter of April 27th and the promise of onr Mr. Koehler, we beg’ to enclose herewith revised bine print showing arrangement of conveyors for which yon favored ns with order.” To this letter defendant replied on May 11th by telegraph as follows: “Have received bine print. Ton have onr letter April 30th, 1908, not to ship any goods. Please acknowledge.” Instead of answering this at once, plaintiff sent its salesman to see Mr. Boetter. What occurred at this interview is in dispute. The salesman testified that Boetter said that after thinking over the matter, he had concluded not to install the conveyors at that time, unless plaintiff would reduce the price; to which the salesman replied that plaintiff was making the conveyors and would go ahead with its part of the contract; and that all Boet-ter said to this was that he had no objection, if plaintiff would reduce the price. Boetter, on the other hand, testified that he told the salesman at that time that the blueprint had not been approved; that he had changed his mind and did not like the system; that he also told the salesman not to manufacture or ship the goods, and that if plaintiff shipped the conveyor defendant would not accept it nor permit it to be installed. On May 18th, plaintiff wrote to defendant, saying that it had learned from the salesman “that Mr. Boetter was inclined to cancel the contract * * * simply because he thought he could secure a conveyor system at a cheaper price;” that “the contract is a legal, binding obligation upon you, and we propose to comply with it so far as we are concerned. We trust that when you have duly considered the matter you will see it as we do. In the meantime, we will proceed with the construction and be ready to ship the conveyors within contract time.” Plaintiff then finished the construction work, and on June 15th, shipped the conveyors and mailed the hill of lading for the same to defendant at Chicago. Defendant returned the hill of lading, saying: “We have come to the conclusion that we do not want to install your conveyor system at the present time.” Plaintiff nevertheless sent workmen to defendant’s place of business to install the conveyors, hut defendant refused to permit the car containing them to he unloaded, and they were thereupon trans-shipped to Louisville and stored in plaintiff’s warehouse.

The court instructed the jury that “if you find from the evidence that on April 30,1908, the defendant notified the plaintiff that it would not accept the conveyors described in the contract in evidence, and that, at that time, the plaintiff had not completed the manufacture of said conveyors, then the plaintiff is not entitled to recover the purchase price of the conveyors, and your verdict should be for the defendantThere was no claim on the part of the plaintiff that it had completed the manufacture of the conveyors on April 30th. The evidence shows, without contradiction, that at that time the manufacture of the conveyors had hut just begun. This being true, the instruction in terms directed the jury to find a verdict for the defendant if they found from the evidence that the letter of April 30th “notified the plaintiff that defendant would not accept the conveyors.” That letter contains no such language, nor are the words of the letter fairly susceptible of any such meaning. Its words are: “We are not yet prepared to install such machinery and would advise you not to do anything for the present in this matter.” This letter was written more than fifty days before the expiration of the time within which the conveyors were required, by the terms of the contract, to he installed. Non constat hut that the defendant might he fully “prepared to install” the conveyors when the time arrived for such installation; and in the meantime, the parts had to he assembled and pnt together so that plaintiff would he ready and able to install them when that time came.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RSA Properties Mission Hills, P.C. v. Mission Hills Homeowners Ass'n
2024 IL App (1st) 231526 (Appellate Court of Illinois, 2024)
Brubaker v. Community Unit School District No. 16
360 N.E.2d 1228 (Appellate Court of Illinois, 1977)
Claeson v. Hennessey
156 N.E.2d 234 (Appellate Court of Illinois, 1959)
Refrigeradora Del Noroeste, S. A. v. Appelbaum
138 F. Supp. 354 (N.D. Illinois, 1956)
McNeff v. White Eagle Brewing Co.
13 N.E.2d 493 (Appellate Court of Illinois, 1938)
Kieper v. American Coal & Supply Co.
187 Ill. App. 131 (Appellate Court of Illinois, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
178 Ill. App. 536, 1913 Ill. App. LEXIS 1087, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alvey-ferguson-co-v-ernst-tosetti-brewing-co-illappct-1913.