Allied Erecting & Dismantling Co. v. United States Steel Corp.

CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 18, 2023
Docket22-3585
StatusUnpublished

This text of Allied Erecting & Dismantling Co. v. United States Steel Corp. (Allied Erecting & Dismantling Co. v. United States Steel Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Erecting & Dismantling Co. v. United States Steel Corp., (6th Cir. 2023).

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 23a0385n.06

No. 22-3585 FILED UNITED STATES COURT OF APPEALS Aug 18, 2023 FOR THE SIXTH CIRCUIT DEBORAH S. HUNT, Clerk

) ALLIED ERECTING AND DISMANTLING ) CO., INC., ) ON APPEAL FROM THE Plaintiff-Appellant, ) UNITED STATES DISTRICT ) COURT FOR THE NORTHERN v. ) DISTRICT OF OHIO ) OPINION UNITED STATES STEEL CORPORATION, ) Defendant-Appellee. ) ) )

Before: MOORE, CLAY, and NALBANDIAN, Circuit Judges. CLAY, J., delivered the opinion of the court in which MOORE, J., joined in full, and NALBANDIAN, J., joined in part. NALBANDIAN, J. (pp. 23–26), delivered a separate opinion concurring in part and dissenting in part.

CLAY, Circuit Judge. This diversity of citizenship action concerns a heavily litigated

contract dispute between Plaintiff Allied Erecting and Dismantling Company, Inc. (“Allied”) and

Defendant United States Steel Corporation (“U.S. Steel”). At this point, the parties have

participated in a three-week jury trial, two appeals, and two remands. See Allied Erecting &

Dismantling Co. v. U.S. Steel Corp., 726 F. App’x 279 (6th Cir. 2018) (“Allied I”); Allied Erecting

& Dismantling Co. v. U.S. Steel Corp., 814 F. App’x 21 (6th Cir. 2020) (“Allied II”). This appeal

concerns evidentiary rulings that the district court made on the second remand. We AFFIRM for

the reasons set forth below. No. 22-3585, Allied Erecting & Dismantling Co., Inc. v. U.S. Steel Corp.

I. BACKGROUND

A. Factual Background

For several decades, Allied contracted with U.S. Steel to dismantle U.S. Steel’s

steelmaking facilities and salvage the resulting scrap metal. The instant dispute involves

dismantling work at U.S. Steel’s now defunct Fairless Works steelmaking facility (“Fairless”),

which is located outside Philadelphia, Pennsylvania. The “material exchange” at the heart of the

contractual dispute between Allied and U.S. Steel “is a simple one: Allied dismantles U.S. Steel’s

Fairless plant at essentially no cost, and, in return, U.S. Steel lets Allied keep and sell the scrap

metal generated by that dismantling work.” Allied II, 814 F. App’x at 23.

The Fairless plant included a “Hot End,” where raw materials were processed and melted,

and a “Cold End,” where steel slabs were rolled, treated, or processed. Allied’s work initially

concerned the Hot End, and it was governed by two contracts executed in 1992: the 1992

Specification and the 1992 Construction Contract (collectively, the “1992 Contracts”). Through

the 1992 Contracts, U.S. Steel agreed that once Allied completed asbestos removal at a facility

that U.S. Steel intended to dismantle, U.S. Steel would assign ownership of that facility. U.S.

Steel’s assignment of ownership to Allied included: (1) “[a]ll ferrous and non-ferrous scrap1

resulting from the dismantling work[;]” (2) “[a]ll ferrous and non-ferrous scrap located within each

dismantling area[;]” and (3) “[r]ailroad track located within a specific dismantling area which

exclusively serves that dismantling area.” 1992 Specification, R. 269-2, Page ID #18069–70.

According to Allied’s president, John Ramun, Allied completed all Hot End work by 1999.

1 Ferrous scrap is made of iron or steel. Non-ferrous scrap is metal that does not contain iron or steel. -2- No. 22-3585, Allied Erecting & Dismantling Co., Inc. v. U.S. Steel Corp.

In response to disputes that arose between U.S. Steel and Allied, the parties entered into an

agreement called the 2003 Agreement in Principle (the “2003 AIP”).2 The 2003 AIP “built upon”

the 1992 Specification. Allied II, 814 F. App’x at 23. Through the 2003 AIP, U.S. Steel agreed

that “[a]ny further dismantling work” at Fairless that U.S. Steel had “released and authorized in

writing for dismantling” would “be awarded to and performed by [Allied]” pursuant to “the same

relevant terms and conditions contained in” the 1992 Specification. 2003 AIP, R. 269-4, Page ID

#18108. Like the 1992 Specification, the 2003 AIP provided that Allied would “own all ferrous

and non-ferrous scrap generated on any projects awarded to” it. Id. at Page ID #18107. U.S. Steel

also provided Allied with a $7 million advance payment. In exchange, Allied agreed to conduct

its dismantling “at no cost to U.S. Steel (other than the Advance Payment).” Id. at Page ID #18108.

Beyond the 1992 Contracts and the 2003 AIP, Allied and U.S. Steel ultimately “entered

into several subsequent contracts, bringing the total number of contracts governing the parties’

relationship to ten, none of which entirely supersedes any other.” Allied I, 726 F. App’x at 281.

One of those contracts was a Dismantling Services Agreement dated July 15, 2004 (the “2004

DSA”).

Shortly after the parties executed the 2003 AIP, John Ramun’s brother, Mike Ramun,

visited Fairless and prepared an estimate of the tons of ferrous steel to be dismantled at Fairless’

sheet and tin facilities (“Sheet & Tin”), which were in Fairless’ Cold End.3 Mike memorialized

his estimate in handwritten notes that he later converted into a typed spreadsheet (the “Original

Estimate”).

2 The disputes that led to the 2003 AIP are not related to the instant appeal. 3 John Ramun was Allied’s president. Mike Ramun prepared the estimate. For clarity, the Court refers to the two by their first names. -3- No. 22-3585, Allied Erecting & Dismantling Co., Inc. v. U.S. Steel Corp.

B. Procedural History

The evidentiary issues on appeal span the initial jury trial, the two subsequent appeals, and

the second remand. For clarity, we will first provide a broad overview of the case’s procedural

history below. We will then provide a more detailed procedural history when discussing each

issue on appeal.

1. 2015 Jury trial

Allied commenced the instant diversity of citizenship action in 2012 pursuant to 28 U.S.C.

§ 1332(a). Later that year, Allied filed its operative second amended complaint. U.S. Steel

answered Allied’s second amended complaint and asserted three counterclaims for breach of

contract. Counts I through VI of Allied’s second amended complaint arise from Allied’s

dismantling work at Fairless. After Allied I and Allied II, only Counts IV and V remain of the

second amended complaint remain. However, because Counts I and III are relevant to our analysis,

we summarize Counts I, III, IV, and V below.

• Count I. Allied sought declaratory judgment under the 2003 AIP and 2004 DSA stating: (1) that it was not obligated to perform certain work at no cost; (2) that U.S. Steel was not permitted to assess certain “backcharges,” (3) that certain concrete removal and backfilling work in the Fairless basements were within Allied’s scope of work and that U.S. Steel must compensate Allied for such additional work; and (4) that “U.S. Steel must cease and desist from continuing to perform this work and/or misappropriating Allied’s property in connection therewith.” Second Am. Compl., R. 43, Page ID #543.

• Count III. Allied sought breach of contract damages under the 1992 Construction Contract for U.S. Steel’s alleged delays in “releasing” Fairless facilities to Allied. Id. at Page ID #544–49.

-4- No. 22-3585, Allied Erecting & Dismantling Co., Inc. v. U.S. Steel Corp.

• Count IV. Allied sought compensation for the scrap value of buildings that remained at Sheet & Tin. According to Allied, “once the asbestos removal at each facility has been completed, U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Raceway Properties, Inc. v. Emprise Corporation
613 F.2d 656 (Sixth Circuit, 1980)
United States v. James F. Moored
38 F.3d 1419 (Sixth Circuit, 1994)
United States v. Adebowale Adesida
129 F.3d 846 (Sixth Circuit, 1998)
United States v. Marcus Freeman
730 F.3d 590 (Sixth Circuit, 2013)
Gass v. Marriott Hotel Services, Inc.
558 F.3d 419 (Sixth Circuit, 2009)
Abbott v. Schnader, Harrison, Segal & Lewis, LLP
805 A.2d 547 (Superior Court of Pennsylvania, 2002)
United States v. White
492 F.3d 380 (Sixth Circuit, 2007)
Shields v. Hoffman
204 A.2d 436 (Supreme Court of Pennsylvania, 1964)
Jacobs v. CNG Transmission Corp.
772 A.2d 445 (Supreme Court of Pennsylvania, 2001)
United States v. Vinesh Darji
609 F. App'x 320 (Sixth Circuit, 2015)
United States v. Kwame Kilpatrick
798 F.3d 365 (Sixth Circuit, 2015)
United States v. Russell Collins
799 F.3d 554 (Sixth Circuit, 2015)
Commonwealth v. Pace
439 A.2d 1320 (Commonwealth Court of Pennsylvania, 1982)
Cottman Transmission Systems, Inc. v. Dubinsky
550 F. Supp. 133 (E.D. Pennsylvania, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Allied Erecting & Dismantling Co. v. United States Steel Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-erecting-dismantling-co-v-united-states-steel-corp-ca6-2023.