Allied Erecting & Dismantling Co Inc v. United States Steel Corp

CourtCourt of Appeals for the Third Circuit
DecidedMay 22, 2024
Docket23-1097
StatusUnpublished

This text of Allied Erecting & Dismantling Co Inc v. United States Steel Corp (Allied Erecting & Dismantling Co Inc v. United States Steel Corp) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Erecting & Dismantling Co Inc v. United States Steel Corp, (3d Cir. 2024).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

________________

No. 23-1097 ________________

ALLIED ERECTING & DISMANTLING CO INC; ALLIED CONSOLIDATED INDUSTRIES INC, Agent of for and on behalf of Allied Erecting and Dismantling Co Inc

v.

UNITED STATES STEEL CORP, Appellant _____________

On Appeal from the United States District Court for the Western District of Pennsylvania (D.C. Civil No. 2-16-cv-01379) District Judge: Honorable Patricia L. Dodge ________________

Submitted Pursuant to Third Circuit L.A.R. 34.1(a) on February 7, 2024

Before: HARDIMAN, SCIRICA, and SMITH, Circuit Judges.

(Filed: May 22, 2024) ________________

OPINION* ________________

* This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent. SCIRICA, Circuit Judge

This is a breach of contract action brought by plaintiffs/appellees Allied Erecting &

Dismantling Co., Inc. (“Allied”) and its agent Allied Consolidated Industries, Inc. against

defendant/appellant United States Steel Corporation (“U.S. Steel”). Following a bench

trial, the District Court found U.S. Steel liable in relevant part and awarded Allied damages.

U.S. Steel now appeals a portion of that damages award. For the reasons below, we will

affirm.

I.

Because we write principally for the parties, who are familiar with the factual

context and legal history of this case, we will set forth only those facts necessary to our

analysis.

Allied was U.S. Steel’s longtime industrial dismantling contractor. It has performed

over 600 dismantling projects for U.S. Steel since 1980. The parties’ relationship and

Allied’s dismantling work was governed by a series of agreements. Those agreements

granted Allied the right to perform all of U.S. Steel’s dismantling work for a 10-year period

on a “last look” basis. App. 8. Specifically, if the parties were unable to negotiate the

terms for Allied to perform a specific dismantling project, U.S. Steel would “competitively

bid the work” and determine the “most acceptable bid.” Id. at 9. The agreements required

U.S. Steel to then submit the “most acceptable bid” to Allied so that Allied could determine

whether to “match the terms of the most acceptable bid” and “agree to perform the work

on such terms.” Id. at 10.

“Last look projects were fixed price, lump sum projects” in the sense that “Allied’s

2 compensation was based on its agreement to match the price in the most acceptable bid.”

Id. at 23-24. Allied would also earn money by selling the scrap metal it generated from its

dismantling work.

The parties’ relationship has been “contentious,” resulting in a series of lawsuits

over the years. Id. at 7-8. Allied commenced the present action in September 2016,

alleging five claims for breach of contract. The claims relevant to this appeal are: (1)

failure to honor Allied’s last look rights in connection with dismantling certain

decommissioned railroad cars and barges, for which Allied sought lost profit damages

(Count II); (2) wrongfully terminating Allied from its work on the Magnetic Separator Roll

Removal Project at U.S. Steel’s Minntac facility, for which Allied sought, among other

things, “the value of scrap it removed while on the project as well as scrap removed by

others after it was terminated” (Count III), id. at 47; and (3) prohibiting Allied from

completing a dismantling project at U.S. Steel’s Fairless Works site, for which Allied

sought “the value of the scrap that was left at the Fairless site” (Count V), id. at 52.

Following a thirteen-day bench trial which concluded on November 20, 2020, as

well as post-trial closing arguments on April 26, 2021, the District Court issued a 77-page

memorandum opinion with findings of fact and conclusions of law, finding, in relevant

part, for Allied.1 The District Court awarded Allied a total of $3,758,705 in damages—

subsequently increased to $5,708,077.67 with prejudgment interest. That damages award

included $915,314 for Count II, $564,355 for the Minntac scrap metal claims in Count III,

1 U.S. Steel did not contest liability with respect to Count II pursuant to a stipulation and verdict from prior litigation. 3 and $1,387,475 for Count V. The District Court calculated damages primarily based on

evidence from Allied’s damages expert who was “Allied’s outside accountant for

approximately fifty years.” Id. at 11. The District Court found Allied’s expert to be “more

credible” than U.S. Steel’s rebuttal expert, the cross-examination of whom “revealed

inadequate investigation, a lack of understanding of the parties’ contracts and documents

and fundamental flaws in his analysis, all of which substantially undermined his credibility

as a rebuttal expert witness.” Id. at 23, 26.

This timely appeal followed.

II.2

On appeal, U.S. Steel argues Allied’s lost profits damages “were not sufficiently

reduced by the costs Allied avoided.” Appellant Br. 4. U.S. Steel urges us to apply de

novo review.

“Review of the District Court’s damages calculation is a mixed question of law and

fact.” VICI Racing, LLC v. T-Mobile USA, Inc., 763 F.3d 273, 293 (3d Cir. 2014). While

“[t]he determination of what legal standard to apply when calculating damages, and

whether that standard was properly applied, are questions of law,” “[t]he determination of

facts upon which to apply this legal standard is a question of fact.” Id. Here, U.S. Steel

does not dispute “[t]he District Court recited the proper standard, including the requirement

to reduce damages by the amount of actual costs avoided.” Id. at 294. Rather, it challenges

the District Court’s calculation of avoidance costs—in essence, a factual determination.

2 The District Court had jurisdiction under 28 U.S.C. § 1332. We have appellate jurisdiction under 28 U.S.C. § 1291. 4 We therefore review for clear error. See also Advanced Fluid Sys., Inc. v. Huber, 958 F.3d

168, 187 n.26 (3d Cir. 2020) (“The Huber Parties challenge the District Court’s factual

determination that certain costs should be excluded from its lost profits damages award.

We review that factual determination for clear error.” (citation omitted)).

“A finding of fact is clearly erroneous when it is completely devoid of minimum

evidentiary support displaying some hue of credibility or bears no rational relationship to

the supportive evidentiary data.” Berg Chilling Sys., Inc. v. Hull Corp., 369 F.3d 745, 754

(3d Cir. 2004) (internal quotation marks omitted). Furthermore, “[t]o the extent that the

District Court’s conclusions rested on credibility determinations, our review is particularly

deferential.” Travelers Cas. & Sur. Co. v. Ins. Co. of N. Am., 609 F.3d 143, 156-57 (3d

Cir. 2010).

Under this standard, we have no trouble concluding the District Court did not clearly

err in its damages calculation. The District Court’s 77-page memorandum opinion

contained detailed and thorough factual findings on damages for each of Allied’s claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Allied Erecting & Dismantling Co Inc v. United States Steel Corp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-erecting-dismantling-co-inc-v-united-states-steel-corp-ca3-2024.