ALLIED CONSOLIDATED INDUSTRIES, INC. v. UNITED STATES STEEL CORPORATION

District Court, W.D. Pennsylvania·Decided October 19, 2020·No. 2:16-cv-01379·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANIA

ALLIED ERECTING AND ) DISMANTLING CO., Inc., ) ) Plaintiff, ) ) v. ) Civil Action No. 16-1379 ) UNITED STATES STEEL ) CORPORATION, ) ) Defendant. )

MEMORANDUM ORDER Pending before the Court is Defendant United States Steel Corporation’s (“U.S. Steel”) Motion in Limine to Exclude Parol Evidence. (ECF No. 156.) For the reasons discussed below, U.S. Steel’s motion will be denied. I. RELEVANT PROCEDURAL BACKGROUND In this lawsuit, Plaintiff Allied Erecting and Dismantling Co., Inc. (“Allied”) alleges, among other things, that U.S. Steel breached the parties’ 2010 Dismantling Services Agreement (“2010 DSA”) by failing to honor Allied’s “last look” rights on various projects. As the Court explained in its Memorandum Opinion that addressed U.S. Steel’s Daubert motion, the 2010 DSA provides in relevant part that: Allied had to provide U.S. Steel with a “project cost estimate” setting forth its costs to perform any dismantling work. The parties would then negotiate to come to mutually agreeable terms. If an agreement was reached, Allied would perform work on a “negotiated” basis (“Negotiated Projects”). Allied performed all Negotiated Projects on a “target gross margin basis,” under an agreed formula and profit margins. If the parties were unable to negotiate the terms however, U.S. Steel could competitively bid the work and invite Allied to participate in the bidding. After the work was competitively bid, Allied had “last look” rights that allowed it to match the terms of the “most acceptable bid” and perform the work. (ECF No. 150 at 2 (citations omitted).) In seeking partial summary judgment at an earlier stage in this proceeding, U.S. Steel questioned the methodology employed by Allied’s damages expert with respect to Allied’s initial project cost estimates. Based upon those estimates, U.S. Steel argued that Allied could not have profitably performed some of the “last look” projects and, therefore, could not have sustained any damages. Allied countered that its initial project cost estimates were typically higher than its

subsequent “last look” contract price. According to Allied, this was because those estimates were calculated as a worst-case scenario using an agreed formula, mark-ups, and profit margins which did not apply to competitively bid work. In rejecting U.S. Steel’s motion for partial summary judgment, the Court explained that “while U.S. Steel may certainly question the methodology and damage calculations of Allied’s expert in a Daubert motion or at trial, it has not shown that Allied’s damage calculations fail as a matter of law.” (ECF No. 121 at 28.) U.S. Steel later filed a Daubert motion seeking to exclude the testimony and opinions of Allied’s expert witness. Allied’s initial project cost estimates were again at issue. While

acknowledging that Allied’s expert had testified that those estimates were calculated on a worst- case basis, U.S. Steel argued that the expert’s testimony was unreliable because he used those estimates when it inured to Allied’s benefit to do so. In denying U.S. Steel’s Daubert motion, the Court noted that whether the initial project cost estimates were calculated as a worst-case approach is a disputed fact. (ECF No. 150 at 8.) Therefore, the Court ruled that Allied’s expert may rely on that factual assumption and that U.S. may challenge this reliance at trial. (Id. at 8–9.) In its pending motion in limine, U.S. Steel seeks to preclude Allied from offering any evidence with respect to whether those estimates were worst-case because it represents inadmissible parol evidence. II. DISCUSSION As indicated in a footnote, U. S. Steel moves to exclude parol evidence related to all of the contracts at issue in this case but focuses on the 2010 DSA because it claims that Allied has repeatedly attempted to alter its terms. Allied denies having done so or that it intends to introduce any such evidence at trial.

As an initial matter, this case will be tried as a bench trial. As such, issues as to the admissibility or exclusion of evidence are most appropriately raised in context and resolved during the trial, particularly with respect to a motion to exclude unspecified parole evidence. The right of the parties to raise any such objection at trial are expressly reserved. However, the specific parol evidence issue raised in U.S. Steel’s motion will be addressed here. In the absence of fraud, accident or mistake, earlier oral representations, understandings or agreements are superseded by the subsequent written contract, and parol evidence is inadmissible to vary, modify or supersede the written contract. Yocca v. Pittsburgh Steelers Sports, Inc., 854 A.2d 425, 436 (Pa. 2004).1 Moreover, as U.S. Steel notes, the inclusion of an integration clause in

a contract is indicative of the parties’ intent that the writing is intended to be their entire agreement. Id. The 2010 DSA includes an integration clause. (2010 DSA § 4(F).) If the parties have integrated their agreement into a single writing, “all prior negotiations and agreements in regard to the same subject matter, whether oral or written, are excluded from consideration.” Martin v. Monumental Life Ins. Co., 240 F.3d 223, 233 (3d Cir. 2001). Thus, once it is determined that a single integrated agreement exists, “the parol evidence rule applies and evidence of any previous oral or written negotiations or agreements involving the same subject matter as the contract is almost always

1 Pennsylvania substantive law applies in this diversity action. See, e.g., Chamberlain v. Giampapa, 210 F.3d 154, 158 (3d Cir. 2000) (citing Erie R.R. v. Tompkins, 304 U.S. 64, 78 (1938)). inadmissible to explain or vary the terms of the contract.” Yocca, 854 A.2d at 436. “[T]he parol evidence rule bars only prior or contemporaneous oral agreements, not subsequent ones.” Nicolella v. Palmer, 248 A.2d 20, 23 (Pa. 1968). U.S. Steel argues that the parol evidence rule bars Allied from offering evidence that U.S. Steel directed Allied to calculate the initial project cost estimates as a worst-case approach because

by doing so, Allied seeks to alter the terms of the 2010 DSA. According to U.S. Steel, Allied claims that its initial project cost estimates are unreliable because they were artificially inflated by Allied at U.S. Steel’s direction. In addition, Allied also asserts that these estimates are applicable only to the Negotiated Projects and were calculated as a worst-case basis because the 2010 DSA does not allow change orders for the Negotiated Projects. These two contentions, U.S. Steel argues, are directly refuted by the following language of the 2010 DSA: [Allied’s] Final Total Project Cost on any [Negotiated] Project shall not be in excess of the Estimated Project Cost shown on the Final Project Cost Estimate, unless there has been a formal written change order issued by [U.S. Steel] due to (a) a change in the scope of the project; or (b) [U.S. Steel’s] acceptance of a change in or to the work methods, the schedules, work scopes and/or dismantling plans submitted by [Allied]. 2010 DSA § 3(H)(iii). In opposing U.S. Steel’s motion, Allied asserts that it is not attempting to alter the terms of the 2010 DSA. Further, it does not contend that the project cost estimates are unreliable; rather, its position is that they are not relevant in the way that U.S. Steel suggests.

Free access — add to your briefcase to read the full text and ask questions with AI

ALLIED CONSOLIDATED INDUSTRIES, INC. v. UNITED STATES STEEL CORPORATION, (W.D. Pa. 2020).

ALLIED CONSOLIDATED INDUSTRIES, INC. v. UNITED STATES STEEL CORPORATION (ALLIED CONSOLIDATED INDUSTRIES, INC. v. UNITED STATES STEEL CORPORATION) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related