Allentown Supply Corp. v. Stryer

31 Pa. D. & C.2d 723, 1962 Pa. Dist. & Cnty. Dec. LEXIS 51
CourtPennsylvania Court of Common Pleas, Lehigh County
DecidedAugust 21, 1962
Docketno. 179
StatusPublished
Cited by1 cases

This text of 31 Pa. D. & C.2d 723 (Allentown Supply Corp. v. Stryer) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Lehigh County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allentown Supply Corp. v. Stryer, 31 Pa. D. & C.2d 723, 1962 Pa. Dist. & Cnty. Dec. LEXIS 51 (Pa. Super. Ct. 1962).

Opinion

Scheirer, J.,

On October 26, 1959, plaintiff and defendant entered into a contract wherein plaintiff agreed to furnish and install a heating and air conditioning system in defendant’s warehouse. Plaintiff’s suit in assumpsit is for the balance due on the heating system and for profits on the air conditioning system which was not installed. Defendant filed a counterclaim for costs expended to rectify the heating system. The jury found for defendant in plaintiff’s suit and for plaintiff in defendant’s counterclaim. Plaintiff filed motions for a new trial and judgment n.o.v.

The contract above referred to was in the form of a letter of proposal from plaintiff to defendant which the latter signed following the word “accepted”. The proposal used the terminology “we will furnish and install” followed by the trade name of the heating and air conditioning equipment. At defendant’s suggestion, the following guarantee was added to the phraseology [725]*725describing the heating proposal: “We guarantee to heat said building to a temperature of 70° at zero weather.” The cost of the installation of both heating and air conditioning equipment was $14,315. The figure of $15,515 was crossed out and the letter began with the words: “As per your request we are pleased to requote on the above mentioned project.”

It is admitted that defendant paid $7,000 on account of the contract price. In addition, plaintiff claims $2,-321.30 allegedly due for materials and labor and $3,-019.00 for loss of profit. The estimated cost of labor and materials according to plaintiff’s testimony was $11,296 which subtracted from the contract price of $14,315 leaves $3,019 designated “profit”. Plaintiff’s Exhibit B attached to its statement of claim reveals labor and materials furnished in the amount of $9,-321.30 which would leave a balance owing of $2,321.30 after a credit of $7,000 paid by defendant is given. It would thus appear that the cost of labor and materials not provided would be $1,974.70, but the full profit of $3,019 is claimed.

Defendant filed a counterclaim for the sum of $3,-797 based upon plaintiff’s failure to perform the contract and the resultant cost to defendant of correcting the system. The total proved by defendant and submitted to the jury was $2,242.35.

The only reasons filed by plaintiff in support of its motion for a new trial were the following:

“1. The verdict was against the evidence.

“2. The verdict was against the weight of the evidence.

“3. The verdict was against the law.

“4. The failure of the Court to charge Point 1 of Points for Charge and Binding Instructions.”

The points for charge and binding instructions were: (1) “Under the evidence the verdict must be [726]*726for the plaintiff”; (2) “Under the law the verdict must be for the plaintiff”. No additional reasons for a new trial were filed within 15 days, nor to this day, after the filing of the notes of testimony.

Our review of the testimony and plaintiff’s brief leads us to the conclusion that the evidence presents issues of material facts for the jury.

“Since the statute authorizing the granting of a judgment n.o.v. was not intended to authorize the court to invade the province of the jury, it is very well established that if the evidence on a material point presented an issue of fact for decision by the jury, a motion for a judgment n.o.v. is improper. It follows that if there is a conflict of testimony upon a material point, such a situation not only does not furnish a ground for a judgment n.o.v., but the court is precluded, by such conflict, from entering such a judgment, ...

“Obviously, if there is reasonable support in the evidence for the verdict which was rendered, and if the verdict is otherwise lawful, a motion for a judgment n.o.v. will not be granted, the weight of the evidence being for the jury, and the proper remedy, if it be thought that the verdict is contrary to the weight of evidence, being not a motion for a judgment n.o.v., but a motion for a new trial.

“As to whether there is reasonable support in the evidence for the verdict, it may be noted that the evidence may be found sufficient, though it be meager or uncorroborated”: 20 P. L. Encyc. Judgment, §145.

Accordingly, since there are issues of material facts in this case, the motion for judgment n.o.v. is improper and will be refused.

Should we find that the verdict was capricious or was against the weight of the evidence and resulted in a miscarriage of justice, it would be our duty to grant a new trial: Bohner v. Eastern Express, Inc., 405 Pa. 463, 175 A. 2d 864. We cannot so find.

[727]*727An examination of the testimony will reveal many conflicts as to material issues which were submitted to the jury. We shall attempt to pin-point the relevant conflicts as we review the testimony.

Work was begun by plaintiff on November 13, 1959, and, according to defendant, substantially completed by December 13, 1959. Plaintiff does not agree that the installation was substantially completed on December 13 and we shall present its reasons later. The warehouse was almost completed either by December 10, 1959, or December 18, 1959. The letter of proposal was brief and lacking in detailed specifications. Nor was the exact time mentioned when the guarantee to heat the building at 70 degrees in zero weather was to take effect. Considerable conflict occurred over the location of the unit heaters. Counsel for plaintiff in his brief said:

“It is important to note at this point that C. Lewis Stryer is a builder with vast experience, and it is inconceivable that Mr. Stryer should sign a contract for the installation of a $14,000.00 heating and air-conditioning system without approving plans showing the design of installation.” It seems clear, however, that defendant did sign the contract without approving a “design of installation”. The testimony of plaintiffs is that defendant submitted a plan of the building which had the location of the unit heaters marked for the center of the warehouse. The plan was prepared by an engineer, not called as a witness, but who informed the court following our inquiry that it was to be used for the purpose of securing approval of the Department of Labor and Industry and that the heat unit locations were not placed on the plan by him. Further, the height of the heaters was not indicated on the plan. There was no reference in the contract to the plan. Defendant made a statement that is contradictory to plaintiff’s position that he, defendant, knew the “design of installation”. He said:

[728]*728“A. Well, since Allentown Supply never gave me any indication of where they were going to hang these heaters, I took it for granted they knew what they were doing and since they made a guarantee of 70 degrees at zero, I wasn’t too much worried as to what their activities were, going to be. So I happened to come over one morning and I saw them hanging the heaters down about 12 feet from the floor.

“Q. About when was that, please?

“A. Approximately November 13th.

“Q. 1959?

“A. 1959.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allentown Supply Corp. v. Stryer
195 A.2d 274 (Superior Court of Pennsylvania, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
31 Pa. D. & C.2d 723, 1962 Pa. Dist. & Cnty. Dec. LEXIS 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allentown-supply-corp-v-stryer-pactcompllehigh-1962.