Allen v. Znidarsic Brothers, Inc., Unpublished Decision (12-29-2000)

CourtOhio Court of Appeals
DecidedDecember 29, 2000
DocketCase No. 99-L-088.
StatusUnpublished

This text of Allen v. Znidarsic Brothers, Inc., Unpublished Decision (12-29-2000) (Allen v. Znidarsic Brothers, Inc., Unpublished Decision (12-29-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen v. Znidarsic Brothers, Inc., Unpublished Decision (12-29-2000), (Ohio Ct. App. 2000).

Opinion

OPINION On May 12, 1988, appellee, Charles T. Allen, filed a complaint in the Lake County Court of Common Pleas against appellants, Znidarsic Brothers, Inc. ("Znidarsic Brothers"), Thomas Znidarsic, C.R.M. Construction Services, Inc.("CRM"), Leiken Oldsmobile, Inc. ("Leiken") and M.R.M. Properties, Inc. ("MRM"). The lawsuit arose out of a construction project on the Leiken Oldsmobile building, in Willoughby, Ohio. MRM owns the property at 38750 Mentor Avenue where the Leiken Oldsmobile Dealership is located. Leiken is the corporation that runs the automobile dealership and contracted with CRM to be the general contractor to remodel the dealership. Thomas Znidarsic was the construction manager for the project and an owner of Znidarsic Brothers.

In his complaint, appellee alleged that he and his company, Allen Builders, entered into an oral contract to supply and install metal studs, drywall and other construction services for Znidarsic Brothers at the Leiken project. In two of the counts of his complaint, appellee alleged that Thomas Znidarsic and Znidarsic Brothers breached their oral contract by failing to pay him for all of the work performed. In his other two counts, appellee alleged that Thomas Znidarsic, Znidarsic Brothers, MRM, Leiken, and CRM were unjustly enriched because they retained his construction services without compensating him. All of the parties sued by appellee filed answers and were represented by the same attorney. Appellants, Thomas Znidarsic and Znidarsic Brothers, filed a counterclaim alleging that appellee breached his oral contract by failing to perform in a timely manner, which caused them to incur damages by hiring others to perform the work.

A jury trial was held on February 8, 1999. At the trial, the testimony revealed that Thomas Znidarsic contacted appellee to do work on the Leiken project because they had worked together in the past. On November 25, 1996, appellee submitted a proposal to Thomas Znidarsic, based on the plans for the Leiken project, to do work on drywall, metal studs, doors, doorframes, and masonry openings for roughly $113,860, depending on certain, unspecified alternatives. On May 22, 1997, after seeing modifications to the plans, appellee submitted a proposal for an additional $1,625. The total of the original proposals was $115,485.

Appellee began work in May 1998. Appellee testified that as the project went along, changes were made to the plans that caused him to incur expenses that exceeded his initial proposals. After discussing the increase in cost with Thomas Znidarsic, the arrangement between them was for appellee to do the work and submit an invoice, which Znidarsic Brothers would pay. The new arrangement constituted a change in the contractual arrangement between the parties; instead of a contract proposing that appellee complete the proposed work for $115,485, the relationship now required that appellants pay appellee for the work he did, whether or not it exceeded the original amount.

According to the testimony of both appellee and Thomas Znidarsic, the relationship did not go smoothly; however, the parties are in dispute with regard to who was at fault. Appellee testified that the project was very disorganized, he was not informed when changes were made, and he was delayed because he had to wait for other facets of the project to be completed before beginning his work. Thomas Znidarsic testified that appellee was at fault for causing the delays and was often unable to work because he was too busy with other projects. Near the end of the project, Thomas Znidarsic hired another company, The Mentor Ridge Company ("Mentor Ridge"), to complete the work that he had hired appellee to do.

Appellee submitted three separate invoices to Thomas Znidarsic. The first two, one for $2,350 and one for $93,691, were paid in full. The third one, for $41,819, was submitted on December 7, 1997. Thomas Znidarsic paid only $25,000 of the third invoice because he believed that some of the work for which appellee was charging him was work done by Mentor Ridge.

At the conclusion of the trial, the trial court sustained appellee's oral motion for a directed verdict on appellants' counterclaim. It submitted appellee's claim to the jury and instructed it that it could render a verdict against Thomas Znidarsic, Znidarsic Brothers, and CRM for breach of contract, against CRM, MRM, and Leiken for unjust enrichment, or against none of the defendants. It also instructed the jury that if it found in favor of appellee, it was then to determine the amount of damages. Initially, the jury returned a verdict of $9,000 jointly against CRM, Thomas Znidarsic, and Znidarsic Brothers for breach of contract and against CRM, MRM, and Leiken for unjust enrichment in the amount of $9,000.

At that point, the trial court had a discussion in chambers with counsel where it was determined that the verdict was improper because the jury could not find both breach of contract and unjust enrichment. The trial court expressed its opinion to the attorneys that the jury must find that either the full amount or nothing was owed because appellants had presented no evidence that they would be entitled to any set-off from the original amount. The court stated that it would instruct the jury that if it found any of the defendants liable, it was required to award the full amount. However, in its further instructions to the jury, to which appellee did not object, the trial court instructed the jury that if it found that any of the parties were liable, they must award damages for "whatever the amount of money * * * that you determine."

At some time during their deliberations, but it is unclear from the record whether it was before or after their first verdict, the jury submitted a question to the court, which read: "Can we award one-half the amount? Or is it all or nothing? [sic]" The trial court answered as follows:

"The amount you award must be based on the evidence. You must state the amount you find from a preponderance of the evidence on the verdict form which related to the parties against whom you make your determination."

The jury returned a verdict for $9,000 in favor of appellee against Thomas Znidarsic, Znidarsic Brothers, and CRM. On February 25, 1999, appellee filed a motion for judgment notwithstanding the verdict and asked that the amount of the verdict be increased to $18,985.61. The $18,985.61 represented the $16,819 appellee claimed was due on the invoice plus interest on that amount as of that date. On May 6, 1999, the trial court sustained appellee's motion and wrote:

"This court finds no evidence which substantiates the jury's award of $9,000.00; approximately one-half the amount of damages evidenced by plaintiff at trial. The evidence presented demonstrated that if the jury found for plaintiff, the only amount due and owing to the plaintiff is $18,985.61. Reasonable minds could not have reached different conclusions regarding the evidence at trial."

Appellants raise the following assignments of error:

"[1.] The trial court erred to the prejudice of the appellants by granting the appellee's oral motion for a directed verdict on the counterclaim of appellant company and appellant Znidarsic.

"[2.] The trial court erred to the prejudice of the appellants by granting the appellee's motion for judgment notwithstanding the verdict."

Appellants' assignments of error address the trial court's decisions to grant appellee's motions for a directed verdict and judgment notwithstanding the verdict. Under Ohio law, the standards for granting either of these motions is identical.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper v. Metal Sales Manufacturing Corp.
660 N.E.2d 1245 (Ohio Court of Appeals, 1995)
American Sales, Inc. v. Boffo
593 N.E.2d 316 (Ohio Court of Appeals, 1991)
Harper v. Miller
164 N.E.2d 754 (Ohio Court of Appeals, 1957)
Chester Park Co. v. Schulte
166 N.E. 186 (Ohio Supreme Court, 1929)
Markota v. East Ohio Gas Co.
97 N.E.2d 13 (Ohio Supreme Court, 1951)
Posin v. A. B. C. Motor Court Hotel, Inc.
344 N.E.2d 334 (Ohio Supreme Court, 1976)
Wagner v. Roche Laboratories
671 N.E.2d 252 (Ohio Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Allen v. Znidarsic Brothers, Inc., Unpublished Decision (12-29-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-v-znidarsic-brothers-inc-unpublished-decision-12-29-2000-ohioctapp-2000.