Allen D. DeArmond v. E. Jacob Construction, Inc.

CourtLouisiana Court of Appeal
DecidedApril 8, 2022
Docket2021CA0981
StatusUnknown

This text of Allen D. DeArmond v. E. Jacob Construction, Inc. (Allen D. DeArmond v. E. Jacob Construction, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen D. DeArmond v. E. Jacob Construction, Inc., (La. Ct. App. 2022).

Opinion

STATE OF LOUISIANA COURT OF APPEAL FIRST CIRCUIT

DOCKET NUMBER 2021 CA 0981

ALLEN D. DEARMOND

VERSUS

E. JACOB CONSTRUCTION, INC.

Decision Rendered: APR 0 8 2022

APPEALED FROM THE 19th JUDICIAL DISTRICT COURT, SECTION 24 EAST BATON ROUGE PARISH, LOUISIANA DOCKET NUMBER 689, 599

HONORABLE DONALD R. JOHNSON, JUDGE

John Dale Powers Attorneys for Plaintiff/ Appellant Andrew P. Sellers, Jr. Allen D. DeArmond Baton Rouge, Louisiana

Nancy A. Richeaux Attorneys for Defendant/ Appellee Sharon B. Kyle E. Jacob Construction, Inc. Steven K. Schilling Baton Rouge, Louisiana

BEFORE: McDONALD, LANIER, and WOLFE, JJ. McDONALD, J.

Allen D. DeArmond appeals a judgment confirming an arbitration award in favor of

E. Jacob Construction, Inc. ( EJC). After review, we reverse the trial court judgment, modify

the May 25, 2020 arbitration award, and render judgment.

FACTUAL AND PROCEDURAL BACKGROUND

In April 2018, Mr. DeArmond and EJC entered a contract whereby EJC agreed to

repair flood -related damages to a house Mr. DeArmond owned in Baton Rouge, Louisiana.

The original contract price was $ 56, 758. 20, to be paid in five installments based on

completion progress. Mr. DeArmond paid EJC two installments of at least $ 27, 210. 00. After

EJC allegedly refused to complete punch list items, Mr. DeArmond did not pay the remaining

three installments, leaving an unpaid balance of $ 29, 548. 20. EJC then filed a lien against

the project.

After EJC refused to remove the lien, Mr. DeArmond filed this breach of contract suit

against EJC. EJC answered the petition and filed a reconventional demand against Mr.

DeArmond for the remaining $ 29, 548. 20. In May 2020, the parties signed a Settlement

Agreement agreeing to retain Jerry Householder, an engineer ( the Arbitrator), to arbitrate

their dispute. The Settlement Agreement pertinently provided:

1) In order to avoid the inherent risks and uncertainties of litigation the Parties hereby settle all of their respective claims and irrevocably bind themselves to the following ... :

Jerry L. Householder, P. E.[,] shall be retained at the parties' mutual and equal cost to inspect the Property, the contract between the parties, contract accounting, and the inspection report prepared by William H. Cress, Jr., A. I. A. (" Cress Report"). After said inspection( s), Dr. Householder shall determine:

A. Whether the alleged defects or deficiencies identified in the Cress Report Items") comply with industry standards and/ or whether same were included in [ EJC' s] scope of work;

B. For any item not in compliance with industry standards, whether same is included in EJC' s scope of work and should therefore result in a credit to [ DeArmond] and if so, the value of that credit;

C. Whether [DeArmond] is due any credit for work not performed and the value of same; and

D. Given all of the above, the amount of the payment, if any, [ DeArmond] shall pay to [ EJC] for the value of work performed. Or, if applicable, the amount of any payment [EJC] shall make to [ DeArmond] to correct or complete items in [ EJC' s] scope of work.

Said independent determination by Dr. Householder shall be binding on both parties. 2 According to the parties, the Arbitrator conducted an on- site arbitration hearing at

the house that was the subject of the dispute. On May 25, 2020, the Arbitrator wrote a

letter to counsel for both parties setting forth his decision. He noted that the undisputed

unpaid balance was $ 29, 548. 20, before adjustments for deficiencies or incomplete work.

He addressed eight punch list items identified by Mr. DeArmond. He found in EJC' s favor

on all but two of the items. The Arbitrator reduced the $ 29, 548. 20 unpaid balance by

860. 00 for those two items, awarded EJC $ 10, 000. 00 in attorney fees, and $ 1, 830. 00 in

interest on unpaid invoices, resulting in a final award in EJC' s favor, and against Mr.

DeArmond, of $40, 598. 20. 1

On June 9, 2020, pursuant to the Louisiana Arbitration Law, La. R. S. 9: 4210, etseq.,

Mr. DeArmond filed a Motion to Vacate, Modify, or Correct Arbitration Award, claiming the

Arbitrator was evidently partial or had so imperfectly executed his powers that a mutual,

final, and definite award was not made. EJC responded with a Motion to Confirm Arbitration

Award, contending none of the exclusive statutory grounds for vacating, modifying, or

correcting the award existed. The trial court held a hearing on the motions, and at the

hearing' s conclusion, directed the parties to submit proposed findings of fact and conclusions

of law. After those submissions, the trial court signed a judgment on June 7, 2021, denying

Mr. DeArmond' s motion, granting EJC' s motion, and confirming the Arbitrator' s May 25, 2020

arbitration award.

Mr. DeArmond appealed from the adverse judgment. After the appeal was lodged,

this court issued an interim order instructing the trial court to sign an amended judgment

and to attach the arbitration award. The trial court complied; thus, this court supplemented

the appellate record with the amended judgment, and maintained the appeal.

On appeal, Mr. DeArmond contends the trial court erred in confirming the arbitration

award. He claims the Arbitrator's award should be vacated because: ( 1) the award shows

evident partiality; ( 2) the Arbitrator exceeded his powers in awarding EJC attorney fees

under the Louisiana Open Account Statute and in awarding ECJ interest on unpaid invoices;

and, ( 3) the award shows a material mathematical miscalculation.

1 We address a mathematical error in the award later in this opinion. 3 LOUSIANA ARBITRATION LAW

As a matter of public policy, Louisiana strongly favors arbitration; thus, arbitration

awards are presumed valid. Crescent Prop. Ptrs, LLC v. American Mfrs Mut. Ins Co., 14-

0969 ( La. 1/ 28/ 15), 158 So. 3d 798, 803. A court may vacate, modify, or correct an

arbitration award based only on the exclusive grounds specified in La. R. S. 9: 4210 and 4211,

which do not include errors of law or fact. Id, at 803- 04. Of relevance here, under La. R. S.

9: 4210B and D, the trial court shall vacate an arbitration award where the arbitrator was

evidently partial or corrupt, or where the arbitrator exceeded his powers or so imperfectly

executed them that he did not make a mutual, final, and definite award upon the subject

matter.2 And, under La. R. S. 9: 4211A, a trial court shall modify or correct an arbitration

award where the award contains an evident material miscalculation of figures. A court,

however, is not entitled to substitute its judgment for that of the arbitrator chosen by the

parties. Crescent Prop. Ptrs, LLC, 158 So. 3d at 803. Rather, a court's determination is

limited to whether the party challenging the award has proven one or more of the specific

statutory grounds for invalidation. Id, at 804; St. George Fire Prot. Dist. No. 2 v. J. Reed

Constr., Inc., 17- 1006 ( La. App. 1 Cir. 2/ 20/ 18), 243 So. 3d 145, 148. An appellate court

conducts a de novo review of a trial court judgment confirming or vacating an arbitration

award. Goodrich Petroleum Co., LLC v. MRC Energy Co., 13- 1435 ( La. App. 4 Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Firmin v. Garber
353 So. 2d 975 (Supreme Court of Louisiana, 1977)
In Re Arbitration Betweem US Turnkey Exp. and Psi, Inc.
577 So. 2d 1131 (Louisiana Court of Appeal, 1991)
JK DEVELOPMENTS v. Amtek of Louisiana, Inc.
985 So. 2d 199 (Louisiana Court of Appeal, 2008)
Frey Plumbing Co., Inc. v. Foster
996 So. 2d 969 (Supreme Court of Louisiana, 2008)
St. Tammany Manor v. Spartan Bldg. Corp.
509 So. 2d 424 (Supreme Court of Louisiana, 1987)
DeVore v. IHC Hospitals, Inc.
884 P.2d 1246 (Utah Supreme Court, 1994)
Mack Energy Co. v. Expert Oil and Gas, L.L.C.
159 So. 3d 437 (Supreme Court of Louisiana, 2015)
Goodrich Petroleum Co. v. MRC Energy Co.
137 So. 3d 200 (Louisiana Court of Appeal, 2014)
St. George Fire Prot. Dist. No. 2 v. J. Reed Constructors, Inc.
243 So. 3d 145 (Louisiana Court of Appeal, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Allen D. DeArmond v. E. Jacob Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-d-dearmond-v-e-jacob-construction-inc-lactapp-2022.