All Regions Chemical Labs, Inc. v. United States Environmental Protection Agency

932 F.2d 73, 21 Envtl. L. Rep. (Envtl. Law Inst.) 21193, 33 ERC (BNA) 1050, 1991 U.S. App. LEXIS 8571
CourtCourt of Appeals for the First Circuit
DecidedMay 6, 1991
Docket90-1715
StatusPublished
Cited by5 cases

This text of 932 F.2d 73 (All Regions Chemical Labs, Inc. v. United States Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All Regions Chemical Labs, Inc. v. United States Environmental Protection Agency, 932 F.2d 73, 21 Envtl. L. Rep. (Envtl. Law Inst.) 21193, 33 ERC (BNA) 1050, 1991 U.S. App. LEXIS 8571 (1st Cir. 1991).

Opinion

BREYER, Circuit Judge.

On Friday, June 17, 1988, two fires broke out in Springfield, Massachusetts, at a chemical plant where appellant All Regions Chemical Labs, Inc. (“All Regions”) stored TCT, a chemical used to chlorinate swimming pools. The first fire began at 10:00 a.m.; the second, thirteen hours later, at 11:00 p.m. The fires released about 180,-000 pounds of chlorine gas into the atmosphere, creating a chlorine cloud over the city and forcing the evacuation of about 30,000 people that night. Apparently, the city fire department and state Department of Environmental Quality brought the fires under control fairly quickly without loss of life. All Regions eventually paid about $1,205,000 in clean-up costs.

Federal law, in particular, § 103(a) of the Comprehensive Environmental Response, Compensation and Liability Act (“CERC-LA”), requires that a person in charge of a place that stores a hazardous chemical, such as TCT, “immediately notify” the Na *75 tional Response Center (the “NRC”) “as soon as he has knowledge of any release ... of [significant quantities of] a hazardous substance_” 42 U.S.C. § 9603(a). All Regions violated this statute, for it failed to notify the NRC “immediately.” Rather, EPA found out about the first fire when a private citizen called it at 3:00 p.m. on June 17, five hours after the fire began. It found out about the second fire when the Massachusetts Department of Environmental Quality notified the NRC at 1:00 a.m. on June 18, two hours after the second fire began. All Regions itself gave the NRC formal notice several months later.

Because All Regions itself (the “person in charge”) failed to notify the NRC on time, EPA has assessed a penalty against All Regions. Acting under the authority of a statutory provision that permits it to assess penalties of up to $25,000 per day for continuing violations of notification requirements, see 42 U.S.C. § 9609(b), EPA decided that (in light of the notice it received from others) All Regions’ violation took place on one day. It then assessed a penalty 80 percent of the maximum permitted, namely $20,000. All Regions now petitions us for review, solely of the amount of the penalty. See 42 U.S.C. § 9609(b). It says that, under the circumstances (where it was busy fighting the fires, where state authorities received notice, where EPA received actual notice very soon), EPA acted “arbitrarily, capriciously,” and therefore unlawfully, in setting the penalty so high. See 42 U.S.C. § 9609(b) (providing for judicial review of CERCLA Class II administrative penalties); 5 U.S.C. § 706(2) (setting general standards of review for agency actions); cf. Yaffe Iron & Metal Co. v. EPA, 774 F.2d 1008, 1014 (10th Cir.1985) (5 U.S.C. § 706(2) provides standard of review of penalty assessed under similar penalty provision in the Toxic Substances Control Act).

In reviewing EPA’s decision we must pay particular attention to the interpretation that it gives its own rules and regulations. See, e.g., Ford Motor Co. v. Milhollin, 444 U.S. 555, 565, 100 S.Ct. 790, 796, 63 L.Ed.2d 22 (1980) (courts should defer to agency’s interpretation of its own regulation “unless demonstrably irrational”); Donovan v. A. Amorello & Sons, Inc., 761 F.2d 61, 63 (1st Cir.1985) (“Courts must allow agencies to interpret their own rules, at least where those interpretations are reasonable.”). And, we must take account of the fact that “the relation of remedy to policy is peculiarly a matter for administrative competence.” Butz v. Glover Livestock Comm’n Co., 411 U.S. 182, 185, 93 S.Ct. 1455, 1458, 36 L.Ed.2d 142 (1973) (internal quotations omitted); see Kulkin v. Bergland, 626 F.2d 181, 184 (1st Cir.1980) (“Generally, administrative remedies or sanctions are subject to a very limited judicial review.”). Applying these deferential standards of review, we cannot find the $20,000 “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A).

All Regions makes three arguments to the contrary, each of which is a variation on a single theme. It points out that, in determining the amount of the penalty, the Administrative Law Judge decided to borrow standards that apply to related cases, cases involving violations of the Toxic Substances Control Act, see 15 U.S.C. § 2615(a); Guidelines for the Assessment of Civil Penalties under Section 16 of the Toxic Substances Control Act [hereinafter “TSCA Guidelines”], 45 Fed.Reg. 59,770 (September 10, 1980), and CERCLA “Class I” violations, see 42 U.S.C. § 9609(a)(3). Those standards, as reduced to writing in the Federal Register, provide that the AU is to examine (1) the •probability of damages (measured on a scale of 1 to 6), and (2) the extent of the potential damage (“major,” “significant,” or “minor”). See TSCA Guidelines, 45 Fed.Reg. at 59,771. The TSCA guideline would indicate a $20,000 fine here (80 percent of maximum) if the probability of damage was high and the extent of the damage was “major.” Id. While All Regions agrees that release of 180,000 pounds of chlorine could cause “major” damage, it asks how the AU could find a high probability that, in the circumstances, its violation could have caused such damage. After all, EPA received the proper notice within a few hours *76 of the release (though not from All Regions), other authorities were dealing appropriately with the problem, and, after having received notice, EPA did little, becoming involved at the scene of the accident only in a very limited way.

The answer to this question lies in the TSCA Guidelines themselves. Those Guidelines say:

The probability of harm, as assessed in specifying circumstances, will always be based on the risk inherent in the violation as it was committed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Dico, Inc.
808 F.3d 342 (Eighth Circuit, 2015)
United States v. Irizarry
98 F. Supp. 2d 160 (D. Puerto Rico, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
932 F.2d 73, 21 Envtl. L. Rep. (Envtl. Law Inst.) 21193, 33 ERC (BNA) 1050, 1991 U.S. App. LEXIS 8571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-regions-chemical-labs-inc-v-united-states-environmental-protection-ca1-1991.