All-Brite Electric v. E.I. Construction, No. Cv 91 31-09-01 (Jun. 7, 1995)

1995 Conn. Super. Ct. 7173
CourtConnecticut Superior Court
DecidedJune 7, 1995
DocketNo. CV 91 31-09-01
StatusUnpublished

This text of 1995 Conn. Super. Ct. 7173 (All-Brite Electric v. E.I. Construction, No. Cv 91 31-09-01 (Jun. 7, 1995)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All-Brite Electric v. E.I. Construction, No. Cv 91 31-09-01 (Jun. 7, 1995), 1995 Conn. Super. Ct. 7173 (Colo. Ct. App. 1995).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION This matter involves a breach of contract and resulting failure to pay monies due under the contract. The plaintiff's original complaint dated January 21, 1991 is in two counts. The first count alleges a breach of contract. The second count alleges unjust enrichment.

Thereafter the defendant filed a request to revise requesting the plaintiff set forth in its complaint the dates that the plaintiff commenced and completed its performance under the written agreement between the parties. In response thereto the plaintiff filed a revised complaint dated April 15, 1991. The plaintiff's revision was limited to adding to the first count, paragraph 5. thereof the following language, "in that the plaintiff commenced work on or about July 15, 1986 and completed work, including all `punch list' items, on or about October 15, 1987".

Thereafter, by motion to strike dated April 23, 1991, the defendant moved to strike the plaintiff's first count and second count of its revised complaint in that it fails to state a claim upon which relief can be granted by reason that the plaintiff failed to raise its claim in a timely matter as required by Article 22 of the written agreement between the parties. Article 22 reads as follows "Article 22 Action Against Contractor. No action shall be maintained against the Contractor upon any claim arising out of or based upon the Subcontract unless commenced within one (1) year after the last work was performed or material was furnished under the sub-contract". The defendant claims that the plaintiff brought its complaint more than one year after the last work was performed CT Page 7174 or material was furnished under the subcontract and therefore the plaintiff's complaint must fail. A careful review of the court file relative to the motion to strike indicates that the court did not take any action on the motion to strike as to the first count (breach of contract) but granted the motion to strike as to the second count (unjust enrichment).

Thereafter the plaintiff filed a revised complaint dated December 4, 1991. The plaintiff reiterated the exact language of its revised complaint dated April 15, 1991 but added two additional paragraphs as follows:

"7. The plaintiff requested payment which was due.

8. At the defendant's request the plaintiff not only took no formal action to collect monies due under the contract and at the defendant's further request the plaintiff testified at the defendant's arbitration hearing to assist defendant to obtain payment as provided in the contract even though the delay in payment was due to defects in the defendant's work and there were no defects in plaintiff's work or performance under the contract." This language was added to both counts.

On January 6, 1992 the defendant filed a request to revise which the plaintiff filed an objection to the defendant's request to revise under date of January 9, 1992. The plaintiff's objection to defendant's request to revise was sustained by the court on January 27, 1992.

Thereafter the defendant under the date April 3, 1992 filed an answer and special defense which special defense reads as follows: "The plaintiff failed, neglected and refused to commence the present action within one (1) year after the last work was performed or material was furnished under the subcontract pursuant to Article 22 of the agreement between the plaintiff and the defendant herein dated May 28, 1986."

The plaintiff filed a reply thereto as follows:

"1. The plaintiff has fully performed under the terms of the Agreement between plaintiff and defendant, in that the plaintiff commenced work on or about July 15, 1986 and completed work, including all `punch list' items, on or about October

2. Subsequent to the completion of all work under the CT Page 7175 Agreement, the plaintiff, at the defendant's request, not only took no formal action to collect the monies due under the contract, but at the defendant's further request, the plaintiff testified at the defendant's arbitration hearing, to assist defendant to obtain payment as provided in the contract even, though the delay in payment was due to defects in the defendant's work and there were no defects in the plaintiff's work or performance under the contract."

Therefore the instant case is presented to the court based on the following pleadings:

Revised complaint dated December 4, 1991.

Answer dated April 3, 1992.

Special Defense April 3, 1992.

Reply dated April 8, 1992.

At the outset of the trial of this case on January 18, 1995 the defendant orally moved that the plaintiff's revised complaint dated December 4, 1991 should be stricken and judgment enter for the defendant. The defendant's oral motion was based on its contention that it was the law of the case that the plaintiff's complaint as initially revised had been stricken and further that the revised complaint dated December 4, 1991 did not state a cause of action upon which relief could be granted as it was for all intents and purposes the same complaint as initially revised. Technically speaking the motion to strike dated April 23, 1991 was granted only as regards the second count and the court did not take any action as regards the first count of the revised complaint dated April 15, 1991. Thereafter by revised complaint dated December 4, 1991 the plaintiff amended its complaint by adding additional paragraphs number 7 8 of the first count of the revised complaint dated December 4, 1991 and reiterating the same language as paragraphs 10 and 11 of the, second count of the plaintiff's revised complaint dated December 4, 1991. The defendant's oral motion to strike the revised complaint dated December 4, 1991 fails for several reasons. The allegations added to the revised complaint dated December 4, 1991 provide a basis for the court to find said contractual limitation provision in the underlying contract has been waived or there is a valid excuse for non performance and therefore relief could be granted to the plaintiff. Furthermore the defendant filed a motion to revise the CT Page 7176 complaint dated December 4, 1991 to which the plaintiff objected. The plaintiff's objection was sustained by the court.

Thereupon the defendant filed its answer under the date of April 3, 1992. Section 112 of the Connecticut Rules of Court provides the order of pleadings and thus the defendant waived its opportunity to move to strike the revised complaint dated December 4, 1991. The defendant's oral motion to strike the plaintiff's revised complaint dated December 4, 1991 is denied and the revised complaint dated December 4, 1991 stands.

The court finds that the plaintiff, All-Brite Electric, Inc., was a Connecticut Corporation with its principal place of business in West Haven, Connecticut.

The defendant, E.I., Constructors, Inc., was a New Jersey corporation with a place of business at Milford, Connecticut.

On or about May 28, 1986, the plaintiff and the defendant entered into a written Agreement whereby the plaintiff agreed to provide all necessary labor, material, tools and equipment pertaining to electrical work on a certain construction project located and known as Schultz Electric Company, 30 Gando Drive, New Haven, Connecticut. A copy of said written agreement was introduced to the court as plaintiff's exhibit A.

The total contract price pursuant to said agreement including approved change orders was $502,526.00. The plaintiff has fully performed under the terms of the agreement which work was accomplished in a good and workmanlike manner having commenced work on or about July 15, 1986 and completing its work including all punch list items on or about October 15, 1987.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franks v. Lockwood
150 A.2d 215 (Supreme Court of Connecticut, 1959)
Connecticut National Bank v. Chapman
216 A.2d 814 (Supreme Court of Connecticut, 1966)
Monteiro v. American Home Assurance Co.
416 A.2d 1189 (Supreme Court of Connecticut, 1979)
Cecio Bros. v. Town of Greenwich
244 A.2d 404 (Supreme Court of Connecticut, 1968)
Schleicher v. Schleicher
182 A. 162 (Supreme Court of Connecticut, 1935)
Providence Electric Co. v. Sutton Place, Inc.
287 A.2d 379 (Supreme Court of Connecticut, 1971)
Hartford Whalers Hockey Club v. Uniroyal Goodrich Tire Co.
649 A.2d 518 (Supreme Court of Connecticut, 1994)
Polverari v. Peatt
614 A.2d 484 (Connecticut Appellate Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
1995 Conn. Super. Ct. 7173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-brite-electric-v-ei-construction-no-cv-91-31-09-01-jun-7-1995-connsuperct-1995.